                      60.     When requested by Noosa Council, a Noise Impact Assessment Report (NIAR) showing
                              monitoring and recording of noise levels must be undertaken to investigate any non-
                              vexatious complaint caused by noise emissions from operations at the premises. Such
                              monitoring must be undertaken and completed within a reasonable and practicable
                              timeframe as nominated by Council and be performed by a suitably qualified and
                              experienced person.
                      61.     The NIAR is to be submitted to Council detailing the results of such monitoring and
                              recommendations for any measures to achieve compliance with noise emission limits
                              set out in Conditions 58 and 59.
                      RECONFIGURATION OF A LOT
                              Approved Plans
                      62.     Development undertaken in accordance with this approval must generally comply with
                              the approved plan listed in the following table unless otherwise amended by these
                              conditions.

                                 Plan No.              Rev.    Plan/Document Name                            Date

                                 7254 prop sub         C       Proposed Subdivision Plan                     28   February
                                                                                                             2019

                      63.     An underground connection to reticulated water and sewerage must be provided to each
                              lot in accordance with the standards and requirements of Northern SEQ Distributor–
                              Retailer Authority (Unitywater).
                      64.     A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
                              (Unitywater) must be submitted to Council that certifies an underground connection to
                              reticulated water and sewerage has been provided to each lot.
                      65.     Prior to sealing of the plan of survey the following works must be completed to the
                              reasonable satisfaction of Council:
                              (a)      The required noise attenuation works to the existing IGA building.
                              (b)      All driveway accesses to each lot.
                              (c)      All pedestrian pathways.
                      66.     Any future subdivision of the Visitor accommodation – Type 4 development within Stage
                              2 on the approved plans must be a community title scheme building format plan with:
                              (a)      the twenty (20) separate lots in the format plan being defined by the footprint of
                                       each dwelling unit building
                              (b)      the balance area of that part of the subject land being included in relevant common
                                       property, and
                              (c)      the curtilage of each of the particular dwelling units being allocated to that dwelling
                                       unit as exclusive use area.
                              Easements
                      67.     Easement for the purposes of:
                              (a)      All stormwater quality treatment devices;
                              (b)      Bushfire access;
                              (c)      Pedestrian access from the motel (lot 2) to connect to the IGA Shopping Centre
                                       through lot 3; and
                              (d)      Driveway vehicle access to each lot,




Document Set ID: 20933247
Version: 1, Version Date: 16/07/2019
Log in to download the original file

2019-09-30 Special Meeting Agenda - Item 1 - Attachment 4 - Court Judgement(PDF, 6MB).pdf · 6.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.