Council archive · source document
Appendix E- Traffic Impact Statement · MCU23/0078
Very large file (17.1 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Original PDF page 34, section 1. The text section number identifies this passage in the reader.
Stockwell Development Group Pty Ltd SLR Ref No: 620.30926-R01-v1.0 TIA 20230524.docx
Traffic Impact Assessment May 2023
Proposed Noosa Civic Village Mixed Use Development
Table 15 I1 - Hofmann Dr / Noosa Civic Access Rd Roundabout – SIDRA Output
Weekday PM Peak Saturday Midday Peak
Scenario Critical Critical
95%tile 95%tile
Max DOS Delay Max DOS Delay
Queue (m) Queue (m)
(sec/veh) (sec/veh)
2022 Survey 0.34 13.8 16.2 0.35 14.2 17.0
2026 Background 0.36 13.9 17.2 0.37 14.4 18.1
2026 With Development 0.44 14.0 23.8 0.51 14.7 28.7
2036 Background 0.39 14.0 19.6 0.40 14.6 20.5
2036 With Development 0.48 14.2 26.8 0.52 15.0 29.4
The results presented in Table 15 indicate that the Hofmann Dr / Noosa Civic Access Rd Roundabout would
operate within acceptable performance thresholds under all assessment scenarios.
8.9.2 I2 - Hofmann Dr / Rene St / Loading Bay Access Roundabout
The Hofmann Dr / Rene St / Loading Bay Access Roundabout is an existing four-leg roundabout. The existing
intersection form is shown in Figure 14. Summary output from the SIDRA assessment is presented in Table 16,
with detailed output provided at Appendix E.
Figure 14 Hofmann Dr / Rene St / Loading Bay Access Roundabout Form
Page 34
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix E- Traffic Impact Statement.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.1 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.