ORDINARY MEETING AGENDA 21 JULY 2022
External Works
23. Toolar Street must be upgraded for the length of its frontage to the subject site.
The works must be undertaken in accordance with an Operational Works approval
and must include in particular:
a. construction of a pedestrian footpath in accordance with the conditions of this
Decision Notice;
b. removal of the existing property accesses and reinstatement of the kerb,
footpath and verge area to match the balance of the site frontage, including
the provision of topsoil and turf where the existing verge is grassed.
Condition 23 is imposed pursuant to s145 of the Planning Act 2016 being non-
trunk infrastructure.
Site Access and Driveways
24. A sealed access driveway must be provided from Toolar Street to all parking and
manoeuvring areas of the development. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. a driveway crossover generally in accordance with Council’s Standard
drawing RS-051 and any associated addendum.
b. a driveway generally in accordance with the approved plans.
c. suitable safety measures, including warning signage, to improve driver
awareness of pedestrians and enhance pedestrian safety.
Car Parking
25. A minimum of 15 car parking spaces must be provided and marked on the site and
made available and accessible at all times. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. 3 visitor parking spaces within the total, which are clearly marked for that
purpose and accessible at all times for visitor use;
b. dimensions, crossfalls and gradients in accordance with Australian Standard
AS/NZS2890.1:2004 - Parking Facilities;
c. The additional visitor car space must be provided adjacent to one of the
proposed visitor spaces.
26. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
27. Directional signage must be provided to direct visitors to the car parking spaces
provided on site.
Pedestrian and Bicycle Facilities
28. Pedestrian and bicycle facilities must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and must
include in particular:
a. a 2.0 metre wide footpath within the road verge for the entire length of the
site’s frontage to Toolar Street together with transitions to the existing
pathway on either side of the site
Condition 28 is imposed pursuant to s145 of the Planning Act 2016 being non-
trunk infrastructure.
Stormwater Drainage
29. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge. The works must be undertaken in accordance with an
Page 11 of 30
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.