ADG Dewatering Management Plan · OPW21/0315
Plans and drawings: the text below has words only, no drawings.
ADG Consulting Pty Ltd
The proposed monitoring locations are shown in Figure 1, Appendix A are a subject to confirmation
following mobilisation of dewatering gear to site.
Monitoring will be undertaken at the following frequencies:
− Daily monitoring of field parameters (pH, electrical conductivity, dissolved oxygen, temperature
and turbidity) in the treated discharge water and pH of the untreated extracted groundwater (to
determine potential acidification). Daily monitoring will be undertaken by a suitably trained site
employee under the supervision of the Site Manager.
− Weekly monitoring of field parameters (pH, electrical conductivity, dissolved oxygen,
temperature and turbidity) in the untreated extracted groundwater, treated discharge water,
receiving waters and background waters by ADG Consulting.
− Weekly laboratory analysis of treated discharge water and receiving waters for suspended solids
and dissolved 0.45µm filterable metals (aluminium, arsenic, cadmium, chromium, copper, iron,
lead, nickel, zinc and mercury). Total aluminium and iron will also be analysed for, if required.
− Pre-discharge/initial monitoring of field parameters (pH, electrical conductivity, dissolved
oxygen and oxidation-reduction potential) in the extracted groundwater (prior to treatment) to
assess changes in groundwater chemistry associated with PASS oxidation.
− Pre-discharge/initial laboratory analysis of extracted groundwater (prior to treatment) for
suspended solids, dissolved 0.45µm filterable metals (aluminium, arsenic, cadmium, chromium,
copper, iron, lead, nickel, zinc and mercury) and for soluble sulfate and chloride to assess
changes in groundwater chemistry associated with PASS oxidation. Total aluminium and iron will
also be analysed for, if required.
− Laboratory analysis of untreated groundwater would also be performed periodically (monthly)
if changes in untreated groundwater pH levels are detected that may indicate local acidification,
and to determine any changes in local groundwaters that may require further investigation of
potential environmental impacts.
All samples will be recovered by a suitably qualified Environmental Scientist and submitted to a National
Association of Testing Authorities (NATA) accredited laboratory for analysis.
6.5.3 Monitoring responsibilities
The persons responsible for undertaking the compliance monitoring described in Section 6.5.2 above are
shown in Table 5.
Table 5 Monitoring responsibilities
Activity Frequency Responsibility Person
Monitoring of field parameters in discharge water
Daily Site Manager Site Manager
and untreated extracted groundwater
Monitoring of field parameters in untreated
Environmental
extracted groundwater, discharge water, Weekly ADG Consulting
Consultant
receiving waters and background waters
Laboratory analysis of samples recovered from Environmental
Weekly ADG Consulting
discharge water and receiving waters Consultant
Monitoring of field parameters in extracted Environmental
Weekly ADG Consulting
groundwater (pre-treated) Consultant
ADG1290.21 Dewatering Management Plan_Rev0_12.10.21 Page 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
ADG Dewatering Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.