Appendix F - engineering report
Attached to the e-mail MCU15/0111 & REC15/0031 Development Application F - Engineering report Email 7 of 8.
CALIBRE CONSULTING
14.143 Effects of Works
Acceptable Solutions (if self-
Specific Outcomes assessable) Proposed Measures
Probable Solutions
(if code assessable)
AND
S1.6 For buildings:
(a) Temporary or permanent
downpipes are connected to the
stormwater system before laying
the roof; OR
(b) Localised erosion is avoided by
directing flow from downpipes
over non-erosive areas.
Stormwater Runoff
O2 S2.1 Diversion drains or bunds are Part of the sediment and erosion
Stormwater is diverted around designed and constructed to drain control mentioned above may require
disturbed areas. upstream runoff around the disturbed the diversion of stormwater around
site; disturbed areas.
AND
S2.2 Discharge from the diversion
drains do not cause runoff impacts to
other properties;
OR
S2.3 Alternative methods, as
described in the Institution of
Engineer’s Australia (Queensland
Division) Soil Erosion and Sediment
Control – Guidelines for Queensland
Construction Sites, are used.
Table 7-4: Division 16: Existing Services Code
Table 14-51 Existing Services
Specific Outcomes Probable Solutions Proposed Measures
(if code assessable)
Setbacks and Easements
O1 S1.1
Development near a sewer, water The footing of any structure or building Due consideration for all infrastructure
main, stormwater drain, overland is located clear of the zone of influence and existing flow paths will occur
flow path or associated structure but no closer than 15.m (measured throughout the detailed design
does not: horizontally) from infrastructure process.
(a) adversely affect the function of including sewers, water mains and
the service; stormwater structures; Preliminary consideration of these
(b) place an additional load on the AND items have been provided in the
service; and Drawings provided in this Report (No.
(c) unduly increase future B14158.W-02A dated December
maintenance costs. 2014).
S1.2 No building of structure
overhangs the zone of influence;
AND
S1.3 Finished surface levels maintain
a minimum of 600mm of cover, but not
B14158.W | COOROY RETIREMENT COMMUNITY | PALM LAKE RESORTS CIVIL ENGINEERING REPORT | 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.