                                    Site Based Stormwater Management Plan

                                    8th August 2012




      BUILDING STRUCTURES
      LAND AND INFRASTRUCTURE DEVELOPMENT
      ENVIRONMENTAL PLANNING
      INTEGRATED WATER MANAGEMENT
      SPECIAL STRUCTURES




                                                                 Print Date: 2 March 2020, 2:19 PM
Full text of the other 34 pages

Page 2

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                                         Page i
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  DOCUMENT CONTROL SHEET

                  BLIGH TANNER PTY LTD                                        Document:
                  ABN 32 061 537 666                                          Noosa Flexi-Learning Centre Site Based
                                                                              Stormwater Management Plan, 8th August
                  LEVEL 9, 269 WICKHAM STREET
                                                                              2012
                  PO BOX 612
                                                                              Bligh Tanner Job Number:
                  FORTITUDE VALLEY
                                                                              2012.167.600
                  QUEENSLAND 4006 AUSTRALIA
                  TELEPHONE +61 7 3251 8555                                   Project Engineer:

                  FACSIMILE          +61 7 3251 8599                          Alan Hoban

                  [email protected]                              Client:
                  www.blightanner.com.au                                      Fulton Trotter (for the Edmund Rice
                                                                              Foundation)

                                                                              Client Contact:
                                                                              Mark Kalinowski

                  Climate change
                  Unless expressly stated otherwise, historical climate data has been used in, or underpins, the analyses that are
                  presented in this report. The historical climate is not necessarily a valid indicator of future climate, which may
                  contain prolonged periods that are wetter or drier than the historical record used for this analysis. There is
                  significant variability in estimates of how climate, and in particular, rainfall, will be impacted by various levels of
                  greenhouse gas accumulation in the atmosphere. Rainfall has a much greater spatial variability than temperature
                  and some areas are likely to become wetter whilst other areas become drier. Further to this there may be
                  changes in the seasonality and intensity of rainfall. Such changes in climate could affect the conclusions and
                  recommendations of this report.

                  Inherent natural variability in soils and plants
                  Where particular types of soils are recommended, such recommendations are based on information provided by
                  soils suppliers, laboratories and published industry guidelines. There can be inconsistencies in the behaviour of
                  soils under field conditions compared to laboratory conditions, and, for both natural and blended soils, many soils
                  are non-homogenous and properties and behaviour can be vary. Where particular plant species have been
                  recommended, such recommendations are based on botanical knowledge and observations of similar species
                  growing in similar, but not identical conditions. Plants can be sensitive to subtle changes in climate, hydrology,
                  soil and surrounding ecological conditions. Further to this, plant health is often closely linked to the level of
                  maintenance provided. No warranty or guarantee, whether explicit or implied is made with respect to the suitability
                  or performance of soils or plant species recommended in this report.




                  © Bligh Tanner Pty Ltd August 2012

                  Version                 Author                  Reviewed                Approved                 Date

                  Version 1               Alan Hoban              Chris Tanner            Chris Tanner             8/8/2012




                                                                                                                     Print Date: 2 March 2020, 2:19 PM

Page 3

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                                                   Page ii
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  TABLE OF CONTENTS

                  EXECUTIVE SUMMARY ...................................................................................................... IV
                  GLOSSARY .......................................................................................................................... V
                  1 INTRODUCTION ............................................................................................................. 1
                   1.1 Locality Plan ............................................................................................................ 2
                   1.2 Site Characteristics................................................................................................. 2
                   1.3 Proposed Land Uses .............................................................................................. 3
                   1.4 Location Conditions ............................................................................................... 3
                   1.5 Rainfall zone ............................................................................................................ 3
                   1.6 Soil Category ........................................................................................................... 3
                  2 DESIGN OBJECTIVES ................................................................................................... 5
                   2.1 Stormwater Treatment Objectives ......................................................................... 5
                   2.2 Hydrologic Objectives ............................................................................................ 6
                   2.3 Water Savings Targets ........................................................................................... 6
                   2.4 Construction Phase Objectives ............................................................................. 7
                     Erosion Hazard Assessment ........................................................................................... 7
                  3 STRATEGY DESCRIPTION AND PLAN ........................................................................ 8
                   3.1 Erosion and Sediment Control Strategy................................................................ 9
                   3.2 Stormwater Treatment Strategy ............................................................................. 9
                  4 STORMWATER QUALITY ASSESSMENT................................................................... 11
                  5 HYDROLOGIC ASSESSMENT ..................................................................................... 14
                   5.1 Flooding of the site ............................................................................................... 14
                   5.2 Flooding impacts downstream of the site ........................................................... 14
                   5.3 Frequent flow impacts downstream of the site ................................................... 16
                  6 IMPLEMENTATION ...................................................................................................... 17
                   6.1 Construction.......................................................................................................... 17
                  7 CONCLUSION .............................................................................................................. 18
                  8 REFERENCES .............................................................................................................. 19

                  List of Figures
                  Figure 1 Locality Plan showing the site in relation to relevant receiving environments ........... 2
                  Figure 2 Site plan showing relevant features of the stormwater strategy .............................. 10
                  Figure 3 MUSIC model schematic........................................................................................ 12
                  Figure 4: Comparison of runoff volumes and pollutant loads, which shows that the mitigated
                  pollutant loads are close to existing levels and well below a conventional ‘best-practice’
                  approach (note logarithmic scale). Actual values are presented in Table 6. ........................ 12
                  Figure 5 Catchment boundary and overland flow paths ....................................................... 14
                  Figure 6 Comparison of pre and post developed peak flows (without mitigation). The increase
                  in peak flow for the Q100 is about 140 litres per second. ..................................................... 15
                  Figure 7: Comparison of pre and post development flow frequency showing that the
                  proposed development avoids increasing the wetness of the downstream ecosystem......... 16

                  List of Tables
                  Table 1 Key site information.................................................................................................. 1
                  Table 2: Soil Properties estimated using the Atlas of Australian Soils .................................... 3
                  Table 3 How the proposal responds to the Noosa Plan.......................................................... 5
                  Table 4 Values used in erosion hazard estimation ................................................................. 7



                                                                                                                                Print Date: 2 March 2020, 2:19 PM

Page 4

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                                         Page iii
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  Table 5 Estimation of non-potable demands from rainwater tanks ......................................... 9
                  Table 6: Comparison of runoff volumes and pollutant loads ................................................. 13
                  Table 7 Rational method estimates of peak flows ................................................................ 15
                  Table B8 Meteorological and rainfall runoff data reporting table ............................................. 2
                  Table B9 Catchment definition reporting table ....................................................................... 2
                  Table B10 Rainwater tank node reporting table ..................................................................... 2
                  Table B11 Infiltration node reporting table.............................................................................. 3
                  Table B12 Porous pavement node reporting table ................................................................. 3
                  Table B13 Stormwater quality modelling results reporting table ............................................. 4

                  Attachments
                  Attachment A – MUSIC Modelling




                                                                                                                        Print Date: 2 March 2020, 2:19 PM

Page 5

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                 Page iv
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  EXECUTIVE SUMMARY

                  The Noosa Flexi-Learning Centre aims to create a welcoming and distinctly un-institutional
                  learning environment for disenfranchised and disengaged youth in the Noosa Region. The
                  design response is to create a beach-house style environment which minimises its impact on
                  the site, as well as on the planet’s resources.

                  The young people that will use the centre are approaching life with few privileges. By
                  creating a learning environment that embodies great sustainability features, the design team
                  hopes to provide accelerated opportunities for them to understand and interact with the types
                  of environmental knowledge that we believe will be important to the world they are inheriting.
                  Such learning opportunities can help build their pride, self-confidence and a sense of
                  purpose.

                  The stormwater management strategy helps create such a place by:
                     • Preserving the natural hydrology across most of the site by building lightweight
                         structures on piers, and minimizing soil compaction during construction
                     • Harvesting rainwater and using a prominent elevated rainwater tank that both
                         symbolizes the responsible use of water and reduces the electricity needed for
                         pumping.

                  This report complies with the format for site-based stormwater management plans as set out
                  in the Urban Stormwater Planning Guidelines (DERM 2010) as referenced under the State
                  Planning Policy 4/10 Healthy Waters.

                  The site is low risk from an erosion and sediment control perspective, and accordingly a
                  minor erosion and sediment control plan will be provided as part of the operational works
                  application. Moving away from slab-on-ground construction significantly reduces earthworks
                  and hence the risk of sediment moving off the site during construction.

                  The stormwater quality management strategy is compliant with the requirements of the SEQ
                  Regional Plan Implementation Guideline No. 7—as referenced in the Noosa Plan.
                  Significantly, because the ground-level impervious area is kept at 10% of the site area, the
                  stormwater quality objective is satisfied by capturing and managing the first 10 mm of runoff.

                  For major storm events, runoff will continue to discharge across the front boundary of the site
                  as sheet flow. The design of the site, with limited ground level impervious surfaces, has a
                  minor impact on peak flows. A small area of depressed landscape at the front of the lot can
                  provide the 1 m³ of flood detention needed to avoid any increase in peak flows leaving the
                  site.




                                                                                                 Print Date: 2 March 2020, 2:19 PM

Page 6

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                                     Page v
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  GLOSSARY
                  Term                       Definition
                  ARI                        Average Recurrence Interval

                                             A system that collects and infiltrates urban stormwater through a prescribed filter
                  Bioretention system
                                             media covered with vegetation to reduce the concentration of stormwater pollutants

                                             Area of land that collects rainfall and contributes to surface water (streams, rivers,
                  Catchment
                                             wetlands) or to groundwater

                  GPT                        Gross Pollutant Trap

                  groundwater                Sub-surface water in the soil or rock structure

                  Ha                         Hectare

                  Hydraulic conductivity     The rate at which water can move through a permeable medium.

                                             A impermeable surface where the majority of rainfall becomes runoff by limiting the
                  Impervious
                                             infiltration of water into the underlying soils

                  Infiltration               The movement of water from the ground surface into the underlying soil profile

                  kL                         kilolitre (1,000L)

                                             Water quality modelling software; Model for Urban Stormwater Improvement
                  MUSIC
                                             Conceptualisation

                                             An important nutrient found in high concentrations in recycled waters, originating from
                  Nitrogen                   human and domestic wastes. A useful plant nutrient that can also cause off-site
                                             problems of eutrophication in lakes, rivers and estuaries.

                                             An important nutrient found in high concentrations in recycled waters, originating
                  Phosphorus                 principally from detergents but also from other domestic wastes. A useful plant nutrient
                                             that can also cause off-site problems of eutrophication in water bodies

                  Pollutant                  Substance that damages the quality of the environment

                  QUDM                       Queensland Urban Drainage Manual

                                             A water body that may receive runoff from the catchment under consideration, and has
                  Receiving water
                                             some environmental value or beneficial use.

                                             Surface overland flow of water resulting from rainfall or irrigation exceeding the
                  Runoff
                                             infiltration capacity of the soil

                                             Site Based Stormwater Management Plan. A SBSMP shall identify potential on and off
                                             site impacts associated with stormwater for a proposed development. The SBSMP
                  SBSMP
                                             shall also identify a range of stormwater management strategies and actions for water
                                             quality, water quantity, and environmental issues.

                  Stormwater runoff          All surface water runoff from rainfall, predominantly in urban catchments

                                             A series of stormwater treatment measures located in a catchment to provide a staged
                  Treatment train
                                             approach to removal of stormwater pollutants from runoff.

                                             Water Sensitive Urban Design. WSUD Provides a strategy for the conservation and
                  WSUD
                                             management of water resources through better management of stormwater.

                  Water quality              The chemical, physical and biological condition of water

                  Water Quality Modelling    An important technique used to make predictions about the quality of waterways.

                                             Water Quality Objectives. Measurable goals for the quality of receiving waters to
                  WQO
                                             ensure the Environmental Values are upheld.




                                                                                                                    Print Date: 2 March 2020, 2:19 PM

Page 7

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                         Page 1
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  1 INTRODUCTION
                  This stormwater management plan has been prepared in accordance with the requirements
                  for Site Based Stormwater Management Plans as outlined in the Urban Stormwater Planning
                  Guidelines (DERM 2010) as referenced under the State Planning Policy 4/10 Healthy
                  Waters.

                  It described the stormwater strategy for the site and considers erosion and sediment control,
                  stormwater management (water quality and hydrology), and flooding, and has been prepared
                  to support a Development Application for the site. Key details about the site are listed in
                  Table 1 below.

                  The Noosa Flexi-Learning Centre aims to create a welcoming and distinctly un-institutional
                  learning environment for disenfranchised and disengaged youth in the Noosa Region. The
                  design response is to create a beach-house style environment which minimises its impact on
                  the site, as well as on the planet’s resources.

                  The young people that will use the centre are approaching life with few privileges. By
                  creating a learning environment that embodies great sustainability features, the design team
                  hopes to provide accelerated opportunities for them to understand and interact with the types
                  of environmental knowledge that we believe will be important to the world they are inheriting.
                  Such learning opportunities can help build their pride, self-confidence and a sense of
                  purpose.

                  The stormwater management strategy helps create such a place by:
                     • Preserving the natural hydrology across most of the site by building on piers, and
                         minimizing soil compaction during construction.
                     • Harvesting rainwater and using a prominent elevated rainwater tank that both
                         symbolizes the responsible use of water and reduces the electricity needed for
                         pumping.


                  Table 1 Key site information

                  Submission date                                 August 2012
                  Developer’s name                                Edmund Rice Education and the Flexible
                                                                  Learning Centre Network
                  Principal Consultant                            Fulton Trotter Architects
                  Consultant’s name                               Bligh Tanner Consulting Engineers
                  Current and proposed land use of                The site is currently vacant. The
                  development site                                proposed use is for a Flexible Learning
                                                                  Centre.
                  Description of site location                    The site is on Girraween Crt, Sunshine
                                                                  Beach Qld, opposite the Sunshine Beach
                                                                  High School and adjacent to Tennis
                                                                  Noosa. The site has recently been
                                                                  subdivided from the parent Lot 3 on
                                                                  RP887636 (at the time of writing the plan
                                                                  hasn’t been sealed).
                  Coordinates                                     26°24’25”S
                                                                  153°06’06”
                  Reference to associated documents.              Fulton trotter Architectural Drawings
                                                                  DA-01 to DA-06




                                                                                                        Print Date: 2 March 2020, 2:19 PM

Page 8

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                        Page 2
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  1.1 Locality Plan
                  The site location is shown in Figure 1 below.




                                                            Noosa Flexi-
                                                            Learning
                                                            Centre

                             Noosa Heads



                                                                             Sunshine Beach

                                                                                                   Coastal waters and
                                                                                                   the Coral Sea
                                                                                                   Sensitive to
                                                                                                   changes in water
                                                                                                   quality

                                                                           Sunrise Beach

                      Noosa National
                      Park/Girraween
                      Nature Reserve:
                      Environmentally
                      sensitive healthland
                      which is particularly
                      sensitive to increased
                      wetting near
                      stormwater outfalls
                      and high nutrient
                      levels, leading to weed
                      infestations and
                                                  Burgess Creek
                      changes in the
                      vegetation community        Increases in peak
                                                  flows could
                                                  exacerbate erosion
                                                                                           Castaways
                                                                                             Beach




                  Figure 1 Locality Plan showing the site in relation to relevant receiving environments


                  1.2 Site Characteristics
                  The site is approximately 0.5 hectares. It is on free-draining sandy soils (as described in
                  Section 1.6).

                  The rear, northern end of the site is at RL 34.1 m grading to RL 32.5 m at the southern
                  boundary, a grade of about 1.6%. A raised mount to the south east of the site rises to RL35
                  M. The lowest point of the site is at the south western corner, at RL 32.27 m.

                  It is currently vegetated with endemic dunal species, including Banksia spp. and
                  Xanthorrhoea spp.



                                                                                                       Print Date: 2 March 2020, 2:19 PM

Page 9

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                    Page 3
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  Girraween Court has existing stormwater drains and kerb and channel. The stormwater pit in
                  front of the site has an invert at RL 31.27, about 1 metre below the lowest surface level on
                  the site.
                  At the end of the existing stormwater drain is a bioretention/infiltration system which was
                  inspected and had adequate plant coverage and no evidence of impeded infiltration.


                  1.3 Proposed Land Uses
                  The site is proposed to be used as Flexible Learning Centre, which seeks to respond to the
                  needs of young people disenfranchised and disengaged from education.

                  It will consist of a series of small buildings that create a learning environment for about 80
                  young people and about 10 staff.


                  1.4 Location Conditions
                  The site is located upstream of the environmentally sensitive Noosa National Park and the
                  Girraween Nature reserve, which Burgess Creek passes through. The stormwater
                  management priorities for this area are set out in the Girraween Stormwater Management
                  Plan (Ecological Engineering 2006) as follows:
                      1. Reinstate the natural hydrology of the catchment
                      2. Repair channel incision at existing stormwater outfalls and remove invasive aquatic
                         weeds
                      3. Treat urban stormwater to current best practice standards

                  1.5 Rainfall zone
                  The nearest rainfall gauge is Noosaville (Bureau of Meteorology Station ID 040995). This
                  rainfall station commenced in 2009, and so does not provide a sufficient period of record for
                  stormwater quality modelling. Accordingly the Cooroy Composite gauge (ID 40059) has
                  been used for long term simulations in accordance with the MUSIC Modelling Guidelines
                  Version 1.0 (Water by Design 2010).


                  1.6 Soil Category
                  For the purposes of this stormwater management plan, soils have been categorised by a
                  field inspection and from the Atlas of Australian Soils (accessed via the Australian Soil
                  Resource Information System). Full soil tests will be undertaken as part of a geotechnical
                  investigation as part of the detailed design and included with the operational works
                  application.

                  The site is characterised by fine, free draining sands with modest organic material and
                  limited fines (consistent with the dunal vegetation present on site). The Soils are in zone
                  Ca10. The five dominant principle profile forms for this zone, and their typical properties, are
                  outlined in Table 2 below.

                  Table 2: Soil Properties estimated using the Atlas of Australian Soils
                  Principal      Median A horizon Texture      Median A Horizon kSat
                  profile forms (Northcote class)              (log10) (mm/hr)
                  Uc2.2          1 (Uniform Coarse)            9 +/-2
                  Uc2.3          1 (Uniform Coarse)            9 +/-2
                  Uc1.22         1 (Uniform Coarse)            9 +/-2
                  O              3 (Uniform Fine)              9 +/-2
                  Gn2.94         2 (Uniform Medium)            7 +/-2




                                                                                                   Print Date: 2 March 2020, 2:19 PM

Page 10

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                  Page 4
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  Based on this assessment there is a very high likelihood that the site soils do not present a
                  constraint to the propsed stormwater management strategy.




                                                                                                 Print Date: 2 March 2020, 2:19 PM

Page 11

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                              Page 5
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  2 DESIGN OBJECTIVES
                  This chapter outlines the relevant stormwater management design objectives for site.


                  2.1 Stormwater Treatment Objectives
                  Stormwater quality is to be managed in accordance with the Noosa Plan Water Sensitive
                  Urban Design Code (Table 14-61).

                  Table 3 How the proposal responds to the Noosa Plan
                  Specific Outcome                       Probable Solutions                   Proposed Approach
                  Water reuse                            S1.1 Development complies            Minimise ground-level
                  O1 Development uses a                  with the water quality standards     impervious areas (i.e. slab on
                  combination of detention and           in Table 2 of the SEQ Regional       ground construction) to less
                  retention systems to capture           Plan Implementation Guideline        than 25% of the site area.
                  run-off from areas on the site;        No. 7 for Water Sensitive Urban
                  AND                                    Design;                              Capture and manage the first 10
                  O2 Water storage devices must          S2.1 No solution provided            mm of runoff from impervious
                  have sufficient capacity having        S3.1 Captured water is plumbed       areas, including:
                  regard to local rainfall pattern       to be available for all external     • capturing roofwater for non-
                  and the catchment area of roof         uses including gardening,               potable uses
                  or other hard standing surface;        irrigation, ponds, filling           • infiltrating excess water into
                  AND                                    swimming pools and outdoor
                  O3 Captured water is utilised for      cleaning, as well as all ground         the soils to preserve the
                  all non-potable uses on site;          floor toilet cisterns and washing       regional hydrology.
                  AND                                    machine cold taps;
                  O4 On-site detention does not          S3.2 Where the captured water
                  adversely impact on water              is used for toilet flushing and/or
                  requirements downstream of the         laundry use, an automatic or
                  site where the water is required       manual interchange device that
                  to sustain the ecology and             allows alternate use of captured
                  hydrology of downstream                water or the reticulated water
                  systems (environmental flows);         supply is installed to ensure that
                  AND                                    there is a continual supply of
                  O5 Within the Shire Business           water for sanitary flushing and
                  Centre site, as shown on Map           laundry use.
                  SBC, on-site detention                 S4.1 No solution provided
                  measures are contained within          S5.1 No solution provided
                  the developed areas of the site,
                  clear of drainage lines and
                  Open Space Precincts.
                  Run-off treatment                      S6.1 & S7.1 Development              Capture and manage first 10
                  O6 Run-off that leaves the site        complies with the water quality      mm of runoff from impervious
                  is treated so as not to adversely      standards in Table 2 of the SEQ      surfaces as per Table 2 of the
                  impact on the ecology and              Regional Plan Implementation         SEQ Regional Plan
                  hydrology of downstream                Guideline No. 7 for Water            Implementation Guideline No. 7
                  environmental flows;                   Sensitive Urban Design.              for Water Sensitive Urban
                  AND                                                                         Design
                  O7 Within the Shire Business
                  Centre site, as shown on Map
                  SBC—
                  a) run-off treatment occurs
                  within the site ; and b) drainage
                  lines are only used for final
                  polishing of run-off.

                  Town water supply                      S8.1 A suitable backflow
                  connections                            prevention device is installed to
                  O8 Backflow devices or similar         protect the potable water within




                                                                                                             Print Date: 2 March 2020, 2:19 PM

Page 12

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                           Page 6
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  systems ensure water reuse             the reticulated water supply in
                  facilities have no impact on the       accordance with AS/NZS
                  quality of the town mains water.       3500:2003 Plumbing and
                                                         Drainage.
                  Use of natural treatments and          S9.1 & S10.1 Development          The need for natural treatment
                  systems                                complies with the water quality   systems will be minimised by
                  O9 Natural treatment strategies,       standards in Table 2 of the SEQ   preserving the natural hydrology
                  including grass swales and bio-        Regional Plan Implementation      of the site, thereby minimising
                  retention systems, vegetated           Guideline No. 7                   any increase in surface runoff.
                  filtration strips and gross
                  pollutant traps, are used
                  wherever practicable;
                  AND
                  O10 Within the Shire Business
                  Centre, as shown on Map
                  SBC— where necessary,
                  drainage lines are ecologically
                  enhanced to ensure that the
                  water quality polishing functions
                  are of high standard.




                  As per Table 2 of the SEQ Regional Plan Implementation Guideline No. 7, development that
                  is less than 25% impervious is excluded from load-based objectives but is required to
                  capture and manage the first 10 mm of runoff per day from impervious areas.

                  The rationale for this, according to the SEQ Regional Plan Implementation Guideline No. 7 is

                           “Since the load-based reductions are relative to the average pollutant loads in
                           untreated runoff, a higher standard is effectively imposed on low-pollutant-generating
                           development, by requiring pollutants to be removed to unachievable levels.
                           Accordingly, development resulting in no more than six dwellings or 25%
                           imperviousness or less can be addressed through simpler ‘deemed to comply’
                           solutions


                  2.2 Hydrologic Objectives
                  The hydrologic objective for this site is to preserve the natural hydrologic regime of the
                  catchment by avoiding any increase in the volume of surface runoff leaving the site.

                  This would thereby satisfy the Frequent Flow Management Objective outlined in Table 4 of
                  the SEQ Regional Plan Implementation Guideline No. 7, which states that the first 10 m of
                  runoff should be captured and managed (where the total impervious surface is 0% to 40%)
                  management of captured stormwater may include infiltration to native soils (where adverse
                  impacts will not arise).


                  2.3 Water Savings Targets
                  The proposed centre is a Class 9 Commercial Building (under the Building Code of
                  Australia), and therefore the Queensland Development Code Mandatory Part 4.3 Alternative
                  Water Sources – Commercial Buildings applies.

                  Accordingly, the centre must have an alternate water source which provides water for
                  suitable uses.




                                                                                                          Print Date: 2 March 2020, 2:19 PM

Page 13

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                 Page 7
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  The most appropriate acceptable solution for this site is to have rainwater tanks, sized at
                  1500L per required pedestal (Acceptable Solution A3), which is connected to each required
                  pedestal, external use, and washing machine cold water taps (Acceptable Solution A2).


                  2.4 Construction Phase Objectives
                  Stormwater run-off from land development and infrastructure development sites has a high
                  potential to cause water contamination and/or environmental harm. This is regulated under
                  the EP Act 1994.

                  Under S440ZG it is an offence to unlawfully deposit a prescribed water contaminant to
                  waters. Prescribed contaminants are listed in Schedule 9 of the Environmental Protection
                  Regulation 2008 (EP Reg), and include: ashes, clay, gravel, sediment, stones and similar
                  organic or inorganic matter, as well as building and construction materials and waste.

                  Under S 319 persons in Queensland carrying out activities which may cause environmental
                  harm must comply with the ’general environmental duty’ (GED). This requires that all
                  reasonable and practicable measures must be adopted to prevent and minimise
                  environmental harm. Although not being able to demonstrate compliance against GED is not
                  an offence, demonstrating that all reasonable and practicable measures have been adopted
                  is a defence for offences such as water contamination. For instance, under chapter 10,
                  s493A of the EP Act, where a person deposits a prescribed water contaminant to waters or
                  causes unlawful environmental harm, it is a defence to demonstrate compliance with the
                  GED. Demonstrating that all reasonable and practicable measures have been conceived and
                  implemented should encompass:
                      • thorough and ongoing site assessments
                      • consideration of, and adaptation for site specific erosion risk factors including
                          topography, soil type, climate and season
                      • design, installation, operation, management, maintenance and monitoring of control
                          measures as identified in the erosion and sediment control plan.

                  Erosion Hazard Assessment
                  This site is considered low risk based on the following erosion hazard assessment:
                     • Predicted Annual Soil loss (tonnes) = A x B x T
                     • Where A = R.K.LS.C.P (as per the Revised Universal Soil Loss Equation).

                  Table 4 Values used in erosion hazard estimation
                  Factor    Description                  Adopted value
                  R         Rainfall erosivity factor    5700 (i 2y 6hr = 15.8 mm/hr)
                  K         Soil erodibility factor      0.04 (loam)
                  LS        Topographic factor           0.2 (100 m @ 1%)
                  C         Cover and management         1 (no cover)
                  P         Practice                     1.3 (no management)
                  B         Area of disturbance          0.5 ha
                  T         Predicted duration           0.5 yrs

                  Predicted unmitigated soil loss = 59 t/ha/yr x 0.5 ha x 0.5 yrs = 15 tonnes

                  As this is significantly less than 150 tonnes, this development is considered low risk,
                  and accordingly a minor erosion and sediment control plan will be provided as part of
                  the operational works application, as per Sunshine Coast Regional Council’s Manual
                  for Erosion and Sediment Control V1.2 (Nov 2008).




                                                                                                Print Date: 2 March 2020, 2:19 PM

Page 14

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                      Page 8
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  3 STRATEGY DESCRIPTION AND PLAN
                  The overall intent of the stormwater strategy is to mimic the natural hydrology of the site by
                  minimising the level of disturbance to the existing ground conditions.

                  Key features of the strategy include:
                     1. Maintaining ground-level permeability across 90% of the site:
                              a. Only 3% of the site (177 m²) will be slab-on-ground construction (for the Music
                                   building (due to soundproofing needs) and part of the Create building (due to
                                   the raised ground levels in that area). The majority of structures will be built on
                                   raised piers (consistent with a Noosa beach-house feel) to largely preserve
                                   ground level infiltration characteristics. The pier-construction technique will
                                   preserve large areas of shallow tree roots, which will assist in maintaining the
                                   natural infiltration rate of the soils and retaining natural biological nutrient
                                   removal capacity.
                              b. 7% of the site is carpark, and this will use permeable pavement to reduce
                                   runoff from small rainfall events.
                     2. 68% of the site free is free of structures (buildings/carparks) which will minimise
                         change to pollutant generation or infiltration properties. This area includes significant
                         retention of existing vegetation, as well as revegetation with existing species.
                     3. Roof runoff will be captured in rainwater tanks that are designed to suit the non-
                         potable water demands at the Flexi-Learning Centre. 25% of the site is covered in
                         roofs and about 60% of roof areas will drain to rainwater tanks, and about 60% of this
                         water is able to be reused. The overflow from these tanks will be diverted to
                         infiltration trenches. The balance of roof areas will drain directly infiltration trenches,
                         rather to via rainwater tanks, because the relatively low non-potable water demands
                         at the Centre do not justify harvesting water from every roof.
                     4. The mean annual volume of surface runoff leaving the site is expected to be about
                         20% less than existing levels (due to rainwater harvesting and infiltration).
                     5. Runoff from the site will enter the stormwater drainage system along Girraween Crt,
                         which drains through an existing bioretention/infiltration system at the end of the court
                         before reaching the Noosa National Park/Girraween Nature Reserve and Burgess
                         Creek. Whilst this existing bioretention system is not specifically needed to treat
                         runoff from the site (and probably isn’t designed to do so), it does provide an
                         additional layer of protection to the receiving environment (given the nature of the
                         intended use, there are unlikely to be any activities on the site that would generate
                         atypical pollutant loads).
                     6. The small increase in impervious areas means there is only a small increase in peak
                         flows under major storm conditions. The very small amount of flood detention
                         required (about 1 m3) will be easily accommodated within the site design at the
                         detailed design stage (as part of infiltration systems, additional landscape
                         depressions or additional airspace in rainwater tanks).
                     7. Overland flow paths will be similar to existing conditions, and under major storm
                         events water will sheet flow across the south-western boundary of the site on to
                         Girraween Crt and then flow west towards Burgess Creek.




                                                                                                     Print Date: 2 March 2020, 2:19 PM

Page 15

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                   Page 9
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  3.1 Erosion and Sediment Control Strategy
                  Due to the site having a low erosion risk, a minor erosion and sediment control plan will be
                  submitted as part of the operational works application. A preliminary erosion and sediment
                  control strategy is outlined below:

                  Given the flat sandy nature of the site, and that soil disturbance will be minimised because
                  most structures will be built on raised stumps rather than slab-on-ground, the erosion and
                  sediment control strategy is expected to be quite straightforward and involve a combination
                  of:
                      • Careful staging of works and tightly controlled work-methods to minimize soil
                         disturbance (this is critical as the permeability of the soils needs to be maintained
                         post-construction)
                      • Temporary downpipes to minimize erosion
                      • Sediment fences
                      • Controlled vehicle access points

                  No sediment basins are planned.
                  3.2 Stormwater Treatment Strategy
                  The stormwater treatment strategy is closely linked to the architectural design for the site, in
                  particular, keeping the building footprints small and retaining large areas of greenspace, and
                  building on piers to maintain the ground level permeability of the site.

                  Roofwater will be harvested and used all non-potable uses. Estimating demands for a centre
                  of this nature is difficult, as attendance is highly variable, and there are atypical water uses
                  compared to conventional schools. For example clothes washing facilities are provided for
                  young people who may be homeless, and some of the learning activities could, from time to
                  time, be high water users.

                  Non potable demands estimates are outlined in Table 5 below.

                  Table 5 Estimation of non-potable demands from rainwater tanks
                    Use               Rate              Comment/Source
                    Toilets           10.5 l/p/day      50% of the demand for a high efficiency
                                                        toilet or houses (Water y Design 2010)
                    Washing           2.6 l/p/day       10% of the demand for a high efficiency
                    Machine                             washing machine (Water by Design 2010)
                    Occupancy         80 people
                    Total internal    0.94 kL/day
                    use
                    Irrigation rate   700 mm/yr for the Water by Design 2010
                                      turfed area
                    Irrigation Area   640 m²            Turfed area as per site plan
                    Total external    384 kL/yr
                    use




                                                                                                  Print Date: 2 March 2020, 2:19 PM

Page 16

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                               Page 10
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                                                                                       CARPARK WITH   CONTINGENCY LOCATION
                    AREAS TO BE PROTECTED                  REVEGETATED AREAS USING
                                                                                       PERMEABLE      WHERE THE LANDSCAPE
                    DURING CONSTRUCTION                    EXISTING/RELOCATED PLANTS
                                                                                       PAVEMENT       COULD BE DEPRESSED FOR
                    (INCLUDING UNDERSTOREY                                                            FLOOD DETENTION (1 M3) OR
                    PLANTING)                                                                         BIORETENTION




                    ROOF AREA
                    DRAINING
                                                                                       `
                    DIRECTLY TO
                    INFILTRATION




                        ROOF AREA
                      DRAINING TO
                       RAINWATER
                       TANKS, WITH
                      OVERFLOW TO
                      INFILTRATION




                           CATCHMENT
                           EXTENT FOR                   SLAB-ON-GROUND
                           OVERLAND FLOWS               CONSTRUCTION

                  Figure 2 Site plan showing relevant features of the stormwater strategy




                                                                                                        Print Date: 2 March 2020, 2:19 PM

Page 17

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                     Page 11
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  4 STORMWATER QUALITY ASSESSMENT

                  Modelling has been undertaken in accordance with Water by Design (2010) MUSIC
                  Modelling Guidelines Version 1.0 with the exception of the following:
                    • Forested parameters have been used to reflect the landscape areas—apart from the
                         turfed areas—in the post-development case, as there is no significant change to pre-
                         developed conditions.

                  Whilst the design objectives for the site (as outlined in Section 2.1) allow for the infiltration of
                  stormwater and do not explicitly require stormwater quality to be managed, given the
                  sensitivity of the receiving environment it is prudent to consider these impacts.

                  It is difficult to accurately estimate the impacts of the development on groundwater quality for
                  several reasons:
                       • The capacity of the in-situ soils to process stormwater pollutants, particularly the
                            denitrifying capacity of the soils and root zone, is difficult to estimate, and MUSIC
                            does not account for the potential retention or transformation of nutrients in natural
                            soils.
                       • The site’s sandy soils are far more permeable than the soils used to develop the
                            recommended rainfall runoff parameters outlined in the SEQ MUSIC Modeling
                            Guidelines (Water by Design 2010), and local calibration data are not available.
                            Permeable area parameters have a significant bearing on model results when
                            impervious areas are low (Water by Design 2010). For example, using a
                            recommended rainfall runoff parameters for a forested site results in an annual
                            volumetric runoff coefficient of 32% which is well above what would be reasonably
                            expected for this site a value of . Adjustments to these parameters in the absence of
                            calibration data would be somewhat arbitrary as they are calibration parameters and
                            not directly related to physical soil characteristics.

                  Notwithstanding the above limitations, using MUSIC in accordance with the recommended
                  guidelines produces the results shown in Figure 4 and Table 6 below.

                  A schematic of the MUSIC model configuration is presented in Figure 3.
                  Note that the architectural design of the site plays a key role in mitigating stormwater
                  impacts. If the site were to be developed as a conventional commercial development, and
                  the stormwater runoff was treated to current best practice standards using bioretention
                  systems, the runoff volumes and pollutant loads would be higher than those from the Noosa
                  Flexi Learning Centre even if there were no rainwater tanks or infiltration systems. In other
                  words the site, by virtue of the low impact design of the site, it will likely perform better than a
                  conventional ‘best-practice’ development.

                  This result highlights the logic of exempting development with low levels of imperviousness
                  from the stormwater quality load-based objectives.




                                                                                                      Print Date: 2 March 2020, 2:19 PM

Page 18

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                        Page 12
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  Figure 3 MUSIC model schematic

                    10000


                     1000                                                             Existing


                                                                                      Conventional commercial
                          100                                                         development
                                                                                      Conventional commercial with
                                                                                      best practice bioretention
                           10
                                                                                      Noosa Flexi


                           1                                                          Noosa Flexi with tanks


                                                                                      Noosa Flexi with tanks +
                          0.1                                                         infiltration
                                Flow (ML/yr)       Total       Total         Total
                                                Suspended Phosphorus       Nitrogen
                                               Solids (kg/yr) (kg/yr)       (kg/yr)

                  Figure 4: Comparison of runoff volumes and pollutant loads, which shows that the mitigated
                  pollutant loads are close to existing levels and well below a conventional ‘best-practice’
                  approach (note logarithmic scale). Actual values are presented in Table 6.




                                                                                                         Print Date: 2 March 2020, 2:19 PM

Page 19

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                                       Page 13
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  Table 6: Comparison of runoff volumes and pollutant loads
                                                                                         Conventional                 Noosa
                                                                                         commercial                   Flexi       Noosa Flexi
                                                                    Conventional         with best        Noosa       School      School with
                                                                    commercial           practice*        Flexi       with        tanks +
                                                       Existing     development          bioretention     School      tanks       infiltration
                   Flow (ML/yr)                               2.9             7.8                   7.6         4.6         3.9             2.0
                   Total Suspended Solids (kg/yr)            160               1300                270        330         300             150
                   Total Phosphorus (kg/yr)                  0.19                3.0                1.2        0.8       0.65             0.22
                   Total Nitrogen (kg/yr)                     2.1                 25                14         7.3         5.5             1.9
                  * sized to reduce pollutant loads by 80% (TSS) 60% (TP) and 45% (TN)




                                                                                                                      Print Date: 2 March 2020, 2:19 PM

Page 20

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                            Page 14
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  5 HYDROLOGIC ASSESSMENT
                  5.1 Flooding of the site
                  The site is located at the top of a dune system with a very small external catchment (0.3 ha)
                  and on sandy, free draining soils. The site is therefore not prone to flooding. The site is well
                  clear of Council’s estimated food extent for the 100 year average recurrence interval (ARI)
                  flood1.

                  Under major storm events, runoff will flow across the site as sheet flow, as shown in Figure 5
                  below.

                  The central turfed area is intended for active recreation, and so it will be slightly raised to
                  assist with drainage so that the students can use this area sooner after it rains.




                             CATCHMENT
                             BOUNDARY




                                                                                       OVERLAND FLOW




                  Figure 5 Catchment boundary and overland flow paths


                  5.2 Flooding impacts downstream of the site

                  For the purposes of flood assessments, a 0.3 ha external catchment has been included (from
                  land immediately to the north of the site, and part of the adjoining lot to the east of the site,
                  refer Figure 5).

                  An initial sizing of flood detention has been undertaken using the initial sizing method
                  outlined in QUDM (2007) Section 5.05.1. For the developed case, the ground level fraction



                  1
                   Sunshine Coast Regional Council Estimated Flood Extent – 100 Year Average Recurrence Interval: Freshwater
                  Flooding And Storm Tide, Current Climate Conditions
                  http://www.sunshinecoast.qld.gov.au/addfiles/documents/floodmaps/ari_map_north.pdf last printed 24/03/2011



                                                                                                           Print Date: 2 March 2020, 2:19 PM

Page 21

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                           Page 15
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  impervious has been conservatively adopted at 20% (the actual ground level impervious
                  area, including the full area of the carpark, is about 10%).

                  Table 7 Rational method estimates of peak flows
                                               Predeveloped                                   Developed
                  Area                         0.8 ha                                         0.8 ha
                  Frequency factor (Fy)        1.2                                            1.2
                  Fraction Impervious (Fi)     0%                                             20%*
                  C10                          0.53                                           0.74
                  Time of concentration                            10 minutes                 10 minutes
                  I (mm/hr)                                        250                        250
                  Peak Flows
                  Q2 (m3/s)                                           0.1                     0.2
                  Q10 (m3/s)                                          0.2                     0.3
                  Q100 (m3/s)                                         0.4                     0.5
                  *
                                              0.60

                                                     Predevelopment
                                              0.50
                                                     Post-development
                      Peak discharge (m³/s)




                                              0.40


                                              0.30


                                              0.20


                                              0.10


                                                -
                                                         2                      10                    100
                                                                 Average Recurrence Interval (yrs)

                  Figure 6 Comparison of pre and post developed peak flows (without mitigation). The
                  increase in peak flow for the Q100 is about 140 litres per second.

                  The increase in the Q100 flow as a result of the development, in absolute terms, is about 140
                  litres per second.

                  The detention size, in accordance with initial sizing method outlined in chapter 5.05 of
                  QUDM, has been estimated at 1 m³ (being the average of QUDM equations 5.01, 5.02, 5.03
                  and 5.04).

                  This flood detention is particularly small and could be considered immaterial particularly in
                  light of
                      • the limited infrastructure between the site and the receiving environment (being
                           raised classrooms and sporting facilities)
                      • the small increase in peak flow is unlikely to have a significant impact on the erosivity
                           of flows in Burgess Creek given it has a far larger catchment

                  Nonetheless the small volume will be easily provided for as follows (in order of preference):
                     • in the infiltration depressions beneath the buildings



                                                                                                            Print Date: 2 March 2020, 2:19 PM

Page 22

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                                         Page 16
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                                           •     In the front of the site there is an area of landscape that will be revegetated, and this
                                                 area could be easily depressed to create 1 m³ of shallow flood detention (0.1m depth
                                                 over 10 m²)
                                           •     As additional airspace within rainwater tanks.

                  Further guidance will be sought from Council at Operational Works to confirm this
                  requirement. In any case, the proposed development layout is compatible with attenuating
                  flooding impacts downstream.


                  5.3 Frequent flow impacts downstream of the site
                  According to the Girraween Stormwater Management Plan (Ecological Engineering 2006),
                  the increased frequency of surface runoff is considered to be the primary threat to the wet
                  heath vegetation of that ecosystem.

                  The strategy to minimise impervious areas and to harvest and infiltrate stormwater is
                  consistent with preserving the hydrology of this receiving environment.

                  Pre and post development flow frequency curves are presented in Figure 7 below. It shows
                  that the strategy is effective in avoiding any increase in runoff for all rainfall events within the
                  simulation period (1973 – 1983). Exact replication of pre-developed flows is the ideal
                  outcome, and the results show modest reduction in flows. The following points are noted:
                       • The results are generated from MUSIC in the absence of any calibration data to
                           reflect the sandy soils of the site (nonetheless, the relative impact between pre and
                           post development would probably not change greatly)
                       • The reduction is modest (it is only apparent when plotted on a logarithmic scale)
                       • A reduction is preferable to an increase (the wet heath is at risk from losing its drying
                           phase), and there is already surplus wetting already occurring from other parts of the
                           catchment, so a small reduction from this site is desirable.


                                                100


                                                 10
                     Daily flow (m³/day)




                                                  1


                                                 0.1                                                   pre
                                                                                                       post
                                                0.01


                                               0.001
                                                       0%         20%           40%           60%             80%        100%
                                                                              Cumulative frequency

                  Figure 7: Comparison of pre and post development flow frequency showing that the
                  proposed development avoids increasing the wetness of the downstream ecosystem.




                                                                                                                          Print Date: 2 March 2020, 2:19 PM

Page 23

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                             Page 17
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  6 IMPLEMENTATION

                  The strategy avoids the creation of vegetated stormwater assets which makes it easier to
                  implement (i.e. it removes the need for detailed staging of works, construction hold points,
                  coordination of erosion and sediment control measures, and establishment periods), and
                  there are no assets being created that will be handed over to Council. The implementation of
                  this stormwater strategy is therefore relatively straightforward. The key implementation
                  challenge is managing construction activities as outlined below.


                  6.1 Construction
                  Construction activities will need to be carefully managed as follows:
                     • Retain as much natural vegetation as possible using appropriate fencing
                     • Minimise disturbance and compaction of soils by having dedicated access routes
                         through the site for construction vehicles
                     • Minimise the generation of fines from construction activites that may impede
                         infiltration (eg cement, sanding).

                  Specific management approaches will include pre-start meetings, hold points, and the use of
                  detailed work-method statements to ensure construction methods are compatible with
                  maintaining the natural hydrology of the site. These approaches will be integrated with the
                  erosion and sediment control plan.




                                                                                              Print Date: 2 March 2020, 2:19 PM

Page 24

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                                 Page 18
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  7 CONCLUSION
                  The proposed stormwater management strategy for the Noosa Flexi Learning Centre will
                  satisfy the requirements for the site for:
                      • Stormwater quality
                      • Hydrology (frequent flows)
                      • Flood mitigation
                      • Erosion and sediment control.

                  The strategy is simple and feasible, and is closely linked to the architectural design of the
                  site.

                  It addresses the specific environmental requirements of the high value receiving
                  environment, and is consistent with the aspiration to create a special place for
                  disenfranchised young people.




                                                                                                  Print Date: 2 March 2020, 2:19 PM

Page 25

Noosa Council documents


                  Bligh Tanner Consulting Engineers                                                              Page 19
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  8 REFERENCES

                  CSIRO (2000) Estimation of Soil Properties Using the Atlas of Australian Soils. Technical
                  report 11/00, February 2000.

                  Department of Environment and Resource Management (2007), Queensland Urban
                  Drainage Manual

                  Department of Environment and Resource Management (2010) Urban Stormwater Quality
                  Planning Guidelines Dec 2010

                  Department of Infrastructure and Planning (2009) South East Queensland Regional Plan
                  2009 – 2031 Implementation Guideline No. 7 Water Sensitive Urban Design.

                  Ecological Engineering (2006) Girraween Stormwater Management Plan, Version 1, 22nd Dec
                  2006. Report prepared for Noosa Council.

                  Sunshine Coast Regional Council (2008) Manual for Erosion and Sediment Control V1.2 Nov
                  2008.

                  Water by Design (2010) MUSIC Modelling Guidelines Version 1.0 - Healthy Waterways
                  Limited.




                                                                                               Print Date: 2 March 2020, 2:19 PM

Page 26

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012




                  ATTACHMENTS




                                                                           Print Date: 2 March 2020, 2:19 PM

Page 27

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  Attachment A – MUSIC Modelling
                  The following reporting tables outline the key parameters used in the MUSIC Modelling for
                  this project. The table format is adopted from the Water by Design (2010) MUSIC Modelling
                  Guidelines V1.0. In accordance with that guideline, where recommended rainfall-runoff and
                  pollutant generation parameters are adopted, they aren’t reported.

                  Interested parties can review the model files to verify model parameters.

                  Table B8 Meteorological and rainfall runoff data reporting table
                            Input                                  Data used in modelling
                            Rainfall station                       Cooroy Composite 40059
                            Time step                              6 minute
                            Modelling period                       1/1/1973 – 13/12/1983 (11 years)
                            Mean annual rainfall (mm/yr)           1595 mm
                            Evapotranspiration (mm/yr)             1627 mm
                            Rainfall runoff parameters             Predevelopment: Forested
                                                                   Post development: Urban Residential (except for natural
                                                                   landscaped areas which use Forested parameters)

                            Pollutant export parameters            Predevelopment: Forested
                                                                   Post Development: Urban Residential (except for natural
                                                                   landscaped areas which use Forested parameters)


                  Table B9 Catchment definition reporting table
                            Catchment ID                   Area (m²)              Land use          Total impervious (%)
                            1 (reference to catchment      Total area of sub-     Residential,      Total impervious portion of
                            plan)                          catchment              commercial,       catchment as measured
                                                                                  industrial etc.   off development plans
                            Carpark                        370                    Residential       100%
                            Buildings                                             Residential
                              Knowledge                    170                    Residential       100%*
                              Amenities                    70                     Residential       100%*
                              Create                       318                    Residential       100%*
                              Retreat                      210                    Residential       100%*
                              Sound                        139                    Residential       100%*
                              Allied/Support/Eat/Gather    497                    Residential       100%*
                            Landscape                      3226                   Forest            0%
                            Turf                           600                                      0%

                            TOTAL                            5600
                           *Note this is roof area, not ground level impervious area


                  Table B10 Rainwater tank node reporting table
                            Rainwater tanks
                            Catchment ID                                                  Treatment node 1
                            Volume below overflow pipe (kL). If greater than 1 tank      20 kL
                            specify number of tanks, volume per tank and total e.g.
                            10 tanks x 5 kL = 50 kL
                            Depth above overflow (m)                                     0.1
                            If tanks are lumped, is depth below overflow the same as     n/a
                            a single tank and overflow pipe scaled accordingly
                                             2
                            Surface area (m ).                                           10
                            Overflow pipe diameter (mm). For lumped tanks this           150
                            must be equivalent to the diameter of the overflow pipe
                            of a single tank multiplied by the square root of the
                            number of tanks



                                                                                                               Print Date: 2 March 2020, 2:19 PM

Page 28

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                            Stored water used for irrigation and other purposes (Y/N)                  Y
                            PET
                            PET – Rain
                            Indoor connections e.g. toilet, laundry etc.                               0.94
                            Indoor demand (kL/day)                                                     0.94
                            Outdoor demand (kL/yr)                                                     384
                            Daily demand (kL/day)                                                      0.94
                            Monthly distribution of annual demand (kL/day)
                            Confirmation that K and C* remain default? (Y/N)                                    Y


                  Table B11 Infiltration node reporting table
                            Infiltration System
                            Catchment ID                                                               Treatment node 1       Treatment node 2
                                                                                                                              (etc.)
                            Water quality objectives (WQO’s) must be achieved prior                    (note the discussion on design objectives in
                            to stormwater entering an infiltration system i.e.                         Chapter 2)
                            infiltration systems cannot be use to demonstrate
                            compliance with WQO’s. Has compliance been achieved
                            prior to using this node? (Y/N)
                            Is the exfiltration rate justified                                         Yes
                                                                                                       Notwithstanding construction controls, the
                            Can the hydraulic conductivity of the in-situ soils be guaranteed even
                                                                                                       hydraulic conductivity of sand is relatively
                            during earthworks?
                                                                                                       insensitive to compaction.
                            If “no” was answered to any of the above questions this node cannot be used.
                                                          2
                            Pond surface area (m )                                                     200                    200
                            Extended detention depth (m)                                               0.1                    0.1
                                               2
                            Filter area (m )                                                           200                    200
                            Unlined filter media perimeter (m)                                         400                    400
                            Depth of infiltration media (m)                                            0.3                    0.3
                            Exfiltration rate (mm/hr)                                                  180                    180
                            Overflow weir width (m)                                                    50                     50
                            Evaporative loss as % of PET                                               25                     25
                            Confirmation that K and C* remain default? (Y/N)                           y                      y


                  Table B12 Porous pavement node reporting table
                             Porous Pavements
                            Catchment ID                                                               Treatment node 1
                            Is direct rainfall modelled as a separate source node with                 Y
                            a 100% impervious fraction? (Y/N)?
                            Is the biofilter filter area set to represent the opening                  It is assumed at
                            area of the permeable paving or void ratio of porous                       25% of total
                            pavement (not the total surface area)? (Y/N). This should                  carpark area
                            be estimated from the product specifications.
                            Is the extended detention depth set to 0 m?                                Y
                            Is the filter depth set to represent the treatment area only (should not   Y
                            include the depth of the drainage layer)
                            Is the vegetation property set to “unvegetated”?                           n/a
                                                   2
                            Surface area (m )                                                          92.5
                            Has the filter area been calculated appropriately (Y / N /                 Y
                            N/A)




                                                                                                                                  Print Date: 2 March 2020, 2:19 PM

Page 29

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                             Extended detention depth (m)                                     0m
                                           2
                             Filter area (m )                                                 92.5 m²
                             Unlined filter media perimeter (m)                               n/a
                             Saturated hydraulic conductivity (mm/hour). This should          180 mm/hr
                             be modelled once at 50 mm/hr and once at 200mm/hr.
                             Report as “50/200”
                             Filter depth (m)                                                 0.2
                             Overflow weir width (m)                                          20 m
                             Exfiltration rate (mm/hr)                                        180 mm/hr
                             If an exfiltration rate has been used, have node water           n/a
                             balance losses been used in calculation of treatment
                             train effectiveness? (Y / N / N/A)
                             If exfiltration rate has been used, is the exfiltration rate     Y
                             justified (Y / N / N/A)
                             Confirmation that K and C* remain default? (Y/N)                 Y




                  Table B13 Stormwater quality modelling results reporting table
                          Catchm         Pollutant           Inflows        Outflow         Reduction     Reduction       Water
                           ent ID                             (kg/yr)       s (kg/yr)        (kg/yr)      achieved       Quality
                                                                                                             (%)        Objective
                                                                                                                           (%)
                          TOTAL             TSS             330             145             185           56%          n/a
                                             TP             0.79            0.22            0.58          73%          n/a
                                             TN             7.3             1.9             5.5           74%          n/a




                                                                                                                Print Date: 2 March 2020, 2:19 PM

Page 30

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  MUSIC MRT File

                  Source nodes
                  Location,Ground Level
                  (Forest),Support/Eat/Gather/Allied,Knowledge,Sound,Retreat,Create,Amenities,Landscape
                  (forest),Turf,Direct rainfall on carpark
                  ID,1,3,4,8,9,10,11,13,14,15
                  Node
                  Type,UrbanSourceNode,UrbanSourceNode,UrbanSourceNode,UrbanSourceNode,UrbanSo
                  urceNode,UrbanSourceNode,UrbanSourceNode,UrbanSourceNode,UrbanSourceNode,Urba
                  nSourceNode
                  Total Area (ha),0.56,0.05,0.017,0.014,0.021,0.032,0.007,0.323,0.06,0.037
                  Area Impervious (ha),0,0.05,0.017,0.014,0.021,0.032,0.007,0,0,0.037
                  Area Pervious (ha),0.56,0,0,0,0,0,0,0.323,0.06,0
                  Field Capacity (mm),80,200,200,200,200,200,200,80,200,200
                  Pervious Area Infiltration Capacity coefficient - a,200,211,211,211,211,211,211,200,211,211
                  Pervious Area Infiltration Capacity exponent - b,1,5,5,5,5,5,5,1,5,5
                  Impervious Area Rainfall Threshold (mm/day),1,1,1,1,1,1,1,1,1,1
                  Pervious Area Soil Storage Capacity (mm),120,500,500,500,500,500,500,120,500,500
                  Pervious Area Soil Initial Storage (% of Capacity),10,10,10,10,10,10,10,10,10,10
                  Groundwater Initial Depth (mm),50,50,50,50,50,50,50,50,50,50
                  Groundwater Daily Recharge Rate (%),25,28,28,28,28,28,28,25,28,28
                  Groundwater Daily Baseflow Rate (%),3,27,27,27,27,27,27,3,27,27
                  Groundwater Daily Deep Seepage Rate (%),0,0,0,0,0,0,0,0,0,0
                  Stormflow Total Suspended Solids Mean (log mg/L),1.9,1.3,1.3,1.3,1.3,1.3,1.3,1.9,2.18,2.18
                  Stormflow Total Suspended Solids Standard Deviation (log
                  mg/L),0.2,0.39,0.39,0.39,0.39,0.39,0.39,0.2,0.39,0.39
                  Stormflow Total Suspended Solids Estimation
                  Method,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stocha
                  stic,Stochastic,Stochastic
                  Stormflow Total Suspended Solids Serial Correlation,0,0,0,0,0,0,0,0,0,0
                  Stormflow Total Phosphorus Mean (log mg/L),-1.1,-0.89,-0.89,-0.89,-0.89,-0.89,-0.89,-1.1,-
                  0.47,-0.47
                  Stormflow Total Phosphorus Standard Deviation (log
                  mg/L),0.22,0.31,0.31,0.31,0.31,0.31,0.31,0.22,0.31,0.31
                  Stormflow Total Phosphorus Estimation
                  Method,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stocha
                  stic,Stochastic,Stochastic
                  Stormflow Total Phosphorus Serial Correlation,0,0,0,0,0,0,0,0,0,0
                  Stormflow Total Nitrogen Mean (log mg/L),-0.075,0.26,0.26,0.26,0.26,0.26,0.26,-
                  0.075,0.26,0.26
                  Stormflow Total Nitrogen Standard Deviation (log
                  mg/L),0.24,0.23,0.23,0.23,0.23,0.23,0.23,0.24,0.23,0.23
                  Stormflow Total Nitrogen Estimation
                  Method,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stocha
                  stic,Stochastic,Stochastic
                  Stormflow Total Nitrogen Serial Correlation,0,0,0,0,0,0,0,0,0,0
                  Baseflow Total Suspended Solids Mean (log mg/L),0.51,0,0,0,0,0,0,0.51,1,1
                  Baseflow Total Suspended Solids Standard Deviation (log
                  mg/L),0.28,0,0,0,0,0,0,0.28,0.34,0.34
                  Baseflow Total Suspended Solids Estimation
                  Method,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stocha
                  stic,Stochastic,Stochastic
                  Baseflow Total Suspended Solids Serial Correlation,0,0,0,0,0,0,0,0,0,0
                  Baseflow Total Phosphorus Mean (log mg/L),-1.79,0,0,0,0,0,0,-1.79,-0.97,-0.97
                  Baseflow Total Phosphorus Standard Deviation (log mg/L),0.28,0,0,0,0,0,0,0.28,0.31,0.31


                                                                                             Print Date: 2 March 2020, 2:19 PM

Page 31

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  Baseflow Total Phosphorus Estimation
                  Method,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stocha
                  stic,Stochastic,Stochastic
                  Baseflow Total Phosphorus Serial Correlation,0,0,0,0,0,0,0,0,0,0
                  Baseflow Total Nitrogen Mean (log mg/L),-0.59,0,0,0,0,0,0,-0.59,0.2,0.2
                  Baseflow Total Nitrogen Standard Deviation (log mg/L),0.22,0,0,0,0,0,0,0.22,0.2,0.2
                  Baseflow Total Nitrogen Estimation
                  Method,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stochastic,Stocha
                  stic,Stochastic,Stochastic
                  Baseflow Total Nitrogen Serial Correlation,0,0,0,0,0,0,0,0,0,0
                  OUT - Mean Annual Flow
                  (ML/yr),2.90,0.733,0.249,0.205,0.308,0.469,0.103,1.67,0.339,0.542
                  OUT - TSS Mean Annual Load (kg/yr),164,22.2,7.51,6.15,9.12,13.8,3.07,95.1,51.3,123
                  OUT - TP Mean Annual Load (kg/yr),0.188,0.121,41.5E-3,34.3E-3,51.8E-3,76.2E-3,16.8E-
                  3,0.107,0.111,0.236
                  OUT - TN Mean Annual Load
                  (kg/yr),2.09,1.54,0.522,0.432,0.642,0.985,0.213,1.22,0.661,1.14
                  OUT - Gross Pollutant Mean Annual Load
                  (kg/yr),0.00,16.9,5.76,4.75,7.12,10.8,2.37,0.00,0.00,12.5
                  Rain In
                  (ML/yr),8.91062,0.79559,0.270501,0.222765,0.334148,0.509179,0.111383,5.13951,0.95470
                  8,0.588737
                  ET Loss
                  (ML/yr),5.96828,0.0629535,0.0214045,0.0176266,0.0264403,0.0402895,0.00881327,3.4424
                  3,0.613075,0.046585
                  Deep Seepage Loss (ML/yr),0,0,0,0,0,0,0,0,0,0
                  Baseflow Out (ML/yr),1.09342,0,0,0,0,0,0,0.630668,0.127057,0
                  Imp. Stormflow Out
                  (ML/yr),0,0.732638,0.249097,0.205139,0.307708,0.468889,0.102569,0,0,0.542153
                  Perv. Stormflow Out (ML/yr),1.80969,0,0,0,0,0,0,1.0438,0.211814,0
                  Total Stormflow Out
                  (ML/yr),1.80969,0.732638,0.249097,0.205139,0.307708,0.468889,0.102569,1.0438,0.21181
                  4,0.542153
                  Total Outflow
                  (ML/yr),2.90311,0.732638,0.249097,0.205139,0.307708,0.468889,0.102569,1.67447,0.3388
                  71,0.542153
                  Change in Soil Storage (ML/yr),0.0392376,0,0,0,0,0,0,0.0226317,0.00276027,0
                  TSS Baseflow Out (ML/yr),4.34491,0,0,0,0,0,0,2.50974,1.72122,0
                  TSS Total Stormflow Out
                  (ML/yr),159.931,22.1814,7.50561,6.15266,9.12086,13.7974,3.0686,92.5662,49.5435,122.60
                  3
                  TSS Total Outflow
                  (ML/yr),164.276,22.1814,7.50561,6.15266,9.12086,13.7974,3.0686,95.076,51.2648,122.603
                  TP Baseflow Out (ML/yr),0.0218037,0,0,0,0,0,0,0.0125755,0.0175416,0
                  TP Total Stormflow Out
                  (ML/yr),0.166549,0.120962,0.0415425,0.0343147,0.0518497,0.0761971,0.0167506,0.09443
                  63,0.0933642,0.235955
                  TP Total Outflow
                  (ML/yr),0.188353,0.120962,0.0415425,0.0343147,0.0518497,0.0761971,0.0167506,0.10701
                  2,0.110906,0.235955
                  TN Baseflow Out (ML/yr),0.320177,0,0,0,0,0,0,0.184142,0.223599,0
                  TN Total Stormflow Out
                  (ML/yr),1.76716,1.54178,0.521941,0.431928,0.641761,0.985447,0.213405,1.03847,0.43762
                  4,1.135




                                                                                             Print Date: 2 March 2020, 2:19 PM

Page 32

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  TN Total Outflow
                  (ML/yr),2.08733,1.54178,0.521941,0.431928,0.641761,0.985447,0.213405,1.22261,0.66122
                  3,1.135
                  GP Total Outflow (ML/yr),0,16.9487,5.76257,4.74564,7.11847,10.8472,2.37282,0,0,12.5421

                  No Imported Data Source nodes

                  USTM treatment nodes
                  Location,Tanks,Infiltration,Infiltration,Permeable Paving
                  ID,5,6,7,16
                  Node
                  Type,RainWaterTankNode,InfiltrationSystemNodeV4,InfiltrationSystemNodeV4,MediaFiltrati
                  onNode
                  Lo-flow bypass rate (cum/sec),0,0,0,0
                  Hi-flow bypass rate (cum/sec),100,100,100,100
                  Inlet pond volume,0, , ,
                  Area (sqm),10,200,200,92.5
                  Extended detention depth (m),0.1,0.1,0.1,0
                  Permanent Pool Volume (cubic metres),20, , ,
                  Proportion vegetated,0, , ,
                  Equivalent Pipe Diameter (mm),150, , ,
                  Overflow weir width (m),10,50,50,20
                  Notional Detention Time (hrs),16.8E-3, , ,
                  Orifice Discharge Coefficient,0.6, , ,
                  Weir Coefficient,1.7,1.7,1.7,1.7
                  Number of CSTR Cells,2,1,1,3
                  Total Suspended Solids - k (m/yr),400,400,400,8000
                  Total Suspended Solids - C* (mg/L),12,12,12,20
                  Total Suspended Solids - C** (mg/L),12,12,12,
                  Total Phosphorus - k (m/yr),300,300,300,6000
                  Total Phosphorus - C* (mg/L),0.13,0.09,0.09,0.13
                  Total Phosphorus - C** (mg/L),0.13,0.09,0.09,
                  Total Nitrogen - k (m/yr),40,40,40,500
                  Total Nitrogen - C* (mg/L),1.4,1,1,1.4
                  Total Nitrogen - C** (mg/L),1.4,1,1,
                  Threshold Hydraulic Loading for C** (m/yr),3500,3500,3500,
                  Horizontal Flow Coefficient, ,3,3,
                  Extraction for Re-use,On,Off,Off,Off
                  Annual Re-use Demand - scaled by daily PET (ML),0, , ,
                  Annual Re-use Demand - scaled by daily PET - Rain (ML),0.384, , ,
                  Constant Daily Re-use Demand (kL),0.94, , ,
                  User-defined Annual Re-use Demand (ML),0, , ,
                  Percentage of User-defined Annual Re-use Demand Jan,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Feb,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Mar,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Apr,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand May,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Jun,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Jul,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Aug,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Sep,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Oct,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Nov,8.33333333333333, , ,
                  Percentage of User-defined Annual Re-use Demand Dec,8.33333333333333, , ,
                  User-defined Re-use File, , , ,
                  Filter area (sqm), ,200,200,92.5



                                                                                          Print Date: 2 March 2020, 2:19 PM

Page 33

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  Filter perimeter (m), ,400,400,
                  Filter depth (m), ,0.3,0.3,0.2
                  Filter Median Particle Diameter (mm), , , ,1
                  Saturated Hydraulic Conductivity (mm/hr), , , ,180
                  Infiltration Media Porosity, ,0.35,0.35,0.3
                  Length (m), , , ,
                  Bed slope, , , ,
                  Base Width (m), , , ,
                  Top width (m), , , ,
                  Vegetation height (m), , , ,
                  Vegetation Type, , , ,
                  Total Nitrogen Content in Filter (mg/kg), , , ,
                  Orthophosphate Content in Filter (mg/kg), , , ,
                  Is Base Lined?, , , ,
                  Is Underdrain Present?, , , ,
                  Is Submerged Zone Present?, , , ,
                  Submerged Zone Depth (m), , , ,
                  B for Media Soil Texture,-9999,-9999,-9999,-9999
                  Proportion of upstream impervious area treated, , , ,
                  Exfiltration Rate (mm/hr),0,180,180,180
                  Evap Loss as proportion of PET,0,0.25,0.25,
                  Depth in metres below the drain pipe, , , ,0
                  TSS A Coefficient, , , ,0.52
                  TSS B Coefficient, , , ,-0.39
                  TP A Coefficient, , , ,1.28
                  TP B Coefficient, , , ,-0.19
                  TN A Coefficient, , , ,1.67
                  TN B Coefficient, , , ,-0.09
                  Sfc, , , ,
                  S*, , , ,
                  Sw, , , ,
                  Sh, , , ,
                  Emax (m/day), , , ,
                  Ew (m/day), , , ,
                  IN - Mean Annual Flow (ML/yr),1.25,0.821,0.801,0.542
                  IN - TSS Mean Annual Load (kg/yr),37.5,24.4,19.9,123
                  IN - TP Mean Annual Load (kg/yr),0.207,0.134,0.126,0.236
                  IN - TN Mean Annual Load (kg/yr),2.62,1.72,1.65,1.14
                  IN - Gross Pollutant Mean Annual Load (kg/yr),28.8,19.0,0.00,12.5
                  OUT - Mean Annual Flow (ML/yr),0.801,0.00,0.00,6.59E-3
                  OUT - TSS Mean Annual Load (kg/yr),19.9,0.00,0.00,0.251
                  OUT - TP Mean Annual Load (kg/yr),0.126,0.00,0.00,1.02E-3
                  OUT - TN Mean Annual Load (kg/yr),1.65,0.00,0.00,9.44E-3
                  OUT - Gross Pollutant Mean Annual Load (kg/yr),0.00,0.00,0.00,0.00
                  Flow In (ML/yr),1.24558,0.820557,0.800885,0.542229
                  ET Loss (ML/yr),0,0,0,0
                  Infiltration Loss (ML/yr),0,0.820545,0.800875,0.535277
                  Low Flow Bypass Out (ML/yr),0,0,0,0
                  High Flow Bypass Out (ML/yr),0,0,0,0
                  Orifice / Filter Out (ML/yr),0.788226,0,0,0.00644382
                  Weir Out (ML/yr),0.0126625,0,0,0.000146364
                  Transfer Function Out (ML/yr),0,0,0,0
                  Reuse Supplied (ML/yr),0.443419,0,0,0
                  Reuse Requested (ML/yr),0.724222,0,0,0
                  % Reuse Demand Met,61.227,0,0,0
                  % Load Reduction,35.7014,100,100,98.7846



                                                                                       Print Date: 2 March 2020, 2:19 PM

Page 34

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  TSS Flow In (kg/yr),37.4551,24.3717,19.9417,122.603
                  TSS ET Loss (kg/yr),0,0,0,0
                  TSS Infiltration Loss (kg/yr),0,12.6527,13.0389,10.7399
                  TSS Low Flow Bypass Out (kg/yr),0,0,0,0
                  TSS High Flow Bypass Out (kg/yr),0,0,0,0
                  TSS Orifice / Filter Out (kg/yr),19.606,0,0,0.244347
                  TSS Weir Out (kg/yr),0.335678,0,0,0.006478
                  TSS Transfer Function Out (kg/yr),0,0,0,0
                  TSS Reuse Supplied (kg/yr),6.52001,0,0,0
                  TSS Reuse Requested (kg/yr),0,0,0,0
                  TSS % Reuse Demand Met,0,0,0,0
                  TSS % Load Reduction,46.7584,100,100,99.7954
                  TP Flow In (kg/yr),0.207126,0.13449,0.125607,0.235956
                  TP ET Loss (kg/yr),0,0,0,0
                  TP Infiltration Loss (kg/yr),0,0.0878825,0.0923026,0.0696649
                  TP Low Flow Bypass Out (kg/yr),0,0,0,0
                  TP High Flow Bypass Out (kg/yr),0,0,0,0
                  TP Orifice / Filter Out (kg/yr),0.123547,0,0,0.000999727
                  TP Weir Out (kg/yr),0.00206,0,0,2.11818E-5
                  TP Transfer Function Out (kg/yr),0,0,0,0
                  TP Reuse Supplied (kg/yr),0.0609768,0,0,0
                  TP Reuse Requested (kg/yr),0,0,0,0
                  TP % Reuse Demand Met,0,0,0,0
                  TP % Load Reduction,39.3571,100,100,99.5673
                  TN Flow In (kg/yr),2.61547,1.7208,1.64523,1.135
                  TN ET Loss (kg/yr),0,0,0,0
                  TN Infiltration Loss (kg/yr),0,1.40174,1.44888,0.790341
                  TN Low Flow Bypass Out (kg/yr),0,0,0,0
                  TN High Flow Bypass Out (kg/yr),0,0,0,0
                  TN Orifice / Filter Out (kg/yr),1.61898,0,0,0.00909755
                  TN Weir Out (kg/yr),0.0262464,0,0,0.000343
                  TN Transfer Function Out (kg/yr),0,0,0,0
                  TN Reuse Supplied (kg/yr),0.833146,0,0,0
                  TN Reuse Requested (kg/yr),0,0,0,0
                  TN % Reuse Demand Met,0,0,0,0
                  TN % Load Reduction,37.0962,100,100,99.1682
                  GP Flow In (kg/yr),28.8132,18.9831,0,12.5424
                  GP ET Loss (kg/yr),0,0,0,0
                  GP Infiltration Loss (kg/yr),0,0,0,0
                  GP Low Flow Bypass Out (kg/yr),0,0,0,0
                  GP High Flow Bypass Out (kg/yr),0,0,0,0
                  GP Orifice / Filter Out (kg/yr),0,0,0,0
                  GP Weir Out (kg/yr),0,0,0,0
                  GP Transfer Function Out (kg/yr),0,0,0,0
                  GP Reuse Supplied (kg/yr),0,0,0,0
                  GP Reuse Requested (kg/yr),0,0,0,0
                  GP % Reuse Demand Met,0,0,0,0
                  GP % Load Reduction,100,100,100,100

                  No Generic treatment nodes

                  Other nodes
                  Location,Pre-Development Node,Post-Development Node
                  ID,2,12
                  Node Type,PreDevelopmentNode,PostDevelopmentNode
                  IN - Mean Annual Flow (ML/yr),2.90,2.02



                                                                                 Print Date: 2 March 2020, 2:19 PM

Page 35

Noosa Council documents


                  Bligh Tanner Consulting Engineers
                  Noosa Flexi Learning Centre Stormwater Management Plan
                  August 2012



                  IN - TSS Mean Annual Load (kg/yr),164,147
                  IN - TP Mean Annual Load (kg/yr),0.188,0.219
                  IN - TN Mean Annual Load (kg/yr),2.09,1.89
                  IN - Gross Pollutant Mean Annual Load (kg/yr),0.00,0.00
                  OUT - Mean Annual Flow (ML/yr),0.00,0.00
                  OUT - TSS Mean Annual Load (kg/yr),0.00,0.00
                  OUT - TP Mean Annual Load (kg/yr),0.00,0.00
                  OUT - TN Mean Annual Load (kg/yr),0.00,0.00
                  OUT - Gross Pollutant Mean Annual Load (kg/yr),0.00,0.00

                  Links
                  Location,Drainage Link,Drainage Link,Drainage Link,Drainage Link,Drainage Link,Drainage
                  Link,Drainage Link,Drainage Link,Drainage Link,Drainage Link,Drainage Link,Drainage
                  Link,Drainage Link,Drainage Link
                  Source node ID,1,3,4,5,10,9,8,11,7,6,13,14,15,16
                  Target node ID,2,5,6,7,6,5,5,6,12,12,12,12,16,12
                  Muskingum-Cunge Routing,Not Routed,Not Routed,Not Routed,Not Routed,Not Routed,Not
                  Routed,Not Routed,Not Routed,Not Routed,Not Routed,Not Routed,Not Routed,Not
                  Routed,Not Routed
                  Muskingum K, , , , , , , , , , , , , ,
                  Muskingum theta, , , , , , , , , , , , , ,
                  IN - Mean Annual Flow
                  (ML/yr),2.90,0.733,0.249,0.801,0.469,0.308,0.205,0.103,0.00,0.00,1.67,0.339,0.542,6.59E-3
                  IN - TSS Mean Annual Load
                  (kg/yr),164,22.2,7.51,19.9,13.8,9.12,6.15,3.07,0.00,0.00,95.1,51.3,123,0.251
                  IN - TP Mean Annual Load (kg/yr),0.188,0.121,41.5E-3,0.126,76.2E-3,51.8E-3,34.3E-
                  3,16.8E-3,0.00,0.00,0.107,0.111,0.236,1.02E-3
                  IN - TN Mean Annual Load
                  (kg/yr),2.09,1.54,0.522,1.65,0.985,0.642,0.432,0.213,0.00,0.00,1.22,0.661,1.14,9.44E-3
                  IN - Gross Pollutant Mean Annual Load
                  (kg/yr),0.00,16.9,5.76,0.00,10.8,7.12,4.75,2.37,0.00,0.00,0.00,0.00,12.5,0.00
                  OUT - Mean Annual Flow
                  (ML/yr),2.90,0.733,0.249,0.801,0.469,0.308,0.205,0.103,0.00,0.00,1.67,0.339,0.542,6.59E-3
                  OUT - TSS Mean Annual Load
                  (kg/yr),164,22.2,7.51,19.9,13.8,9.12,6.15,3.07,0.00,0.00,95.1,51.3,123,0.251
                  OUT - TP Mean Annual Load (kg/yr),0.188,0.121,41.5E-3,0.126,76.2E-3,51.8E-3,34.3E-
                  3,16.8E-3,0.00,0.00,0.107,0.111,0.236,1.02E-3
                  OUT - TN Mean Annual Load
                  (kg/yr),2.09,1.54,0.522,1.65,0.985,0.642,0.432,0.213,0.00,0.00,1.22,0.661,1.14,9.44E-3
                  OUT - Gross Pollutant Mean Annual Load
                  (kg/yr),0.00,16.9,5.76,0.00,10.8,7.12,4.75,2.37,0.00,0.00,0.00,0.00,12.5,0.00




                                                                                            Print Date: 2 March 2020, 2:19 PM

Used in these records

About this file

File size
1.1 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Storm Water management plan.pdf · 1.1 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.