Bligh Tanner Consulting Engineers Page 16
Noosa Flexi Learning Centre Stormwater Management Plan
August 2012
• In the front of the site there is an area of landscape that will be revegetated, and this
area could be easily depressed to create 1 m³ of shallow flood detention (0.1m depth
over 10 m²)
• As additional airspace within rainwater tanks.
Further guidance will be sought from Council at Operational Works to confirm this
requirement. In any case, the proposed development layout is compatible with attenuating
flooding impacts downstream.
5.3 Frequent flow impacts downstream of the site
According to the Girraween Stormwater Management Plan (Ecological Engineering 2006),
the increased frequency of surface runoff is considered to be the primary threat to the wet
heath vegetation of that ecosystem.
The strategy to minimise impervious areas and to harvest and infiltrate stormwater is
consistent with preserving the hydrology of this receiving environment.
Pre and post development flow frequency curves are presented in Figure 7 below. It shows
that the strategy is effective in avoiding any increase in runoff for all rainfall events within the
simulation period (1973 – 1983). Exact replication of pre-developed flows is the ideal
outcome, and the results show modest reduction in flows. The following points are noted:
• The results are generated from MUSIC in the absence of any calibration data to
reflect the sandy soils of the site (nonetheless, the relative impact between pre and
post development would probably not change greatly)
• The reduction is modest (it is only apparent when plotted on a logarithmic scale)
• A reduction is preferable to an increase (the wet heath is at risk from losing its drying
phase), and there is already surplus wetting already occurring from other parts of the
catchment, so a small reduction from this site is desirable.
100
10
Daily flow (m³/day)
1
0.1 pre
post
0.01
0.001
0% 20% 40% 60% 80% 100%
Cumulative frequency
Figure 7: Comparison of pre and post development flow frequency showing that the
proposed development avoids increasing the wetness of the downstream ecosystem.
Print Date: 2 March 2020, 2:19 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Storm Water management plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.