Bligh Tanner Consulting Engineers
Noosa Flexi Learning Centre Stormwater Management Plan
August 2012
Extended detention depth (m) 0m
2
Filter area (m ) 92.5 m²
Unlined filter media perimeter (m) n/a
Saturated hydraulic conductivity (mm/hour). This should 180 mm/hr
be modelled once at 50 mm/hr and once at 200mm/hr.
Report as “50/200”
Filter depth (m) 0.2
Overflow weir width (m) 20 m
Exfiltration rate (mm/hr) 180 mm/hr
If an exfiltration rate has been used, have node water n/a
balance losses been used in calculation of treatment
train effectiveness? (Y / N / N/A)
If exfiltration rate has been used, is the exfiltration rate Y
justified (Y / N / N/A)
Confirmation that K and C* remain default? (Y/N) Y
Table B13 Stormwater quality modelling results reporting table
Catchm Pollutant Inflows Outflow Reduction Reduction Water
ent ID (kg/yr) s (kg/yr) (kg/yr) achieved Quality
(%) Objective
(%)
TOTAL TSS 330 145 185 56% n/a
TP 0.79 0.22 0.58 73% n/a
TN 7.3 1.9 5.5 74% n/a
Print Date: 2 March 2020, 2:19 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Storm Water management plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.