2017-02-13 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 13 FEBRUARY 2017
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following
table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
1620/DA/1.02 C Existing/Demolition Ground Floor Plan 25/01/17
1620/DA/2.01 J Proposed Basement Plan – Stage 4 30/01/17
1620/DA/2.02 G Proposed Ground Floor Plan – Stage 4 30/01/17
1620/DA/2.05 G Proposed Roof Plan – Stage 4 30/01/17
1620/DA/3.01 E Sections – Stage 4 30/01/17
1620/DA/4.01 H Elevations – Stage 4 30/01/17
1620/DA/5.01 E Landscape Concept Strategy – Plan 30/01/17
1620/DA/5.02 C Landscape Concept Strategy 30/01/17
Nature and Extent of Approved Use
3. The proposed development provides for an extension to the Gaming Area (providing
for a maximum of 180 gaming machines), Smokers Terrace, Store, Children’s Lounge,
basement carpark area and other internal modifications as shown on the approved
plans.
4. The proposed Children’s Lounge is to remain an enclosed structure and is not to be
used as an open balcony or break out area in association with the Function Room.
5. The proposed development shall be setback at least 2m from the Pelican Street
frontage and 4m from Doonella Street, with the exception of Stair 3, which is to be
setback not less than 0.85m. The basement carpark area is to remain predominantly
an open structure, where above ground level, with all openings fitted with open timber
battens as shown on the approved plans. The building setback areas to the basement
shall be densely landscaped to screen the basement area from both Doonella and
Pelican Streets.
6. Access and egress to the existing Function Room is to be obtained via the main entry
to the RSL building and is not via the doors providing access to the new service
carpark area at this level. These doors are not to be used in association with an
additional break out area by patrons using the Function Room.
7. All open space areas shown on the Overall Site Plan, prepared by Planit Consulting,
dated September 2016 and Landscape Concept Strategy Plans 1620/DA/5.01 Rev E
and 1620/DA/5.02 Rev C dated 30/01/17, are to be landscaped in accordance with the
Statement of Landscape Intent provided. The applicant is required to provide the
equivalent number of mature trees lost by the development of the site, in the
landscaped open space areas. A number of larger trees are to be provided in the open
space area to the north of the RSL development and behind the existing commercial
buildings on the subject land. The landscaping of the open space areas is to be
undertaken to the reasonable satisfaction of the Manager, Planning and Environment.
8. The length of the car park podium to the Pelican Street frontage must be broken up
through the use of large feature trees at the Pelican Street/Doonella Street corner and
again at the entrance to the car park from Doonella Street as shown on the Landscape
Concept Strategy – Plan 1620/DA/5.01 Rev E dated 30/01/17.
Page 6 of 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.