Decision Notice - Minor Change - MCU21 0228 01 & OPW21 0364 01 [As Published] · MCU21/0228.01

of 17

Text shows just the words. Original shows the document exactly as it was published.

                                                                              Officer:          Georgina Schramm
                                                                              Direct Telephone: 07 5329 6569
                                                                              Our Reference:    MCU21/0228.01
                                                                                                OPW21/0364.01
                                                                              Your Reference:   M2915P

               21 February 2024


               Altum Property Group
               C/- JFP Urban Consultants Pty Ltd
               T1.209 Kon-Tiki Business Centre
               Tower 1/55 Plaza Parade
               MAROOCHYDORE QLD 4558
               [email protected]



               Dear Sir/Madam,
                                            Decision Notice – Minor Change
                                                         Planning Act 2016

               I refer to your application received on 4 December 2023, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              MCU21/0228.01,OPW21/0364.01

                   Street address:              245 David Low Way, Peregian Beach

                   Real property description:   Lot 22 P 9315

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               The following type of approval was issued on 18 August 2022.
               •       Development Permit for Material Change of Use of Premises – Dual Occupancy, & Office
               •       Development Permit for Operational Works - Roadwork, Drainage Work, Landscaping,
                       Stormwater, Earthworks
               In relation to the request to make a minor change to the existing approval, Council on 19 February
               2024, decided to approve in part the requested changes. The changes are detailed below.
               A.      Approve the change in part;
               B.      Amend conditions 1 and 46;
               C.      Refuse to approve a gate to the site’s rear to link with the Community House at 5-7 Rufous
                       Street for the following reasons:
                       1.     There is no suitable safe access on the Peregian Beach Community House land from
                              the gate to Rufous Street.


               ABN 97.969.214.121                                                             PO Box 141
               noosa.qld.gov.au                                                        Tewantin QLD 4565
               [email protected]                                                        07 5329 6500
                                                                                                       Page 1 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024
Full text of the other 16 pages

Page 2

                      2.      The proposed link through the subject site is also not designed as a public thoroughfare
                              and conflicts with the development’s car parking and driveway areas.
               D.     Advice the applicant that the gate to the site’s rear that currently provides pedestrian access
                      to the Peregian Beach Community House must be removed and this area landscaped.
               3.     CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.     ASSESSMENT MANAGER CONDITIONS

                      When Conditions must be Complied With
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                        Plan No.             Rev.    Plan/Document Name                             Date

                        1622-DA02            08      Floor Plans,     prepared    by   Blackburn 8 August 2022
                                                     Jackson

                        1622-DA03            07      Elevations, prepared by Blackburn Jackson      8 August 2022

                        1622-DA04            07      Section, prepared by Blackburn Jackson         8 August 2022

                        1622-DA05            07      Section, prepared by Blackburn Jackson         8 August 2022

                        1622-DA06            07      Landscape Area Plans,         prepared    by 8 August 2022
                                                     Blackburn Jackson

                        1622-DA07            08      Site Cover & Height, prepared by Blackburn 8 August 2022
                                                     Jackson

                        1622-DA08            07      Materials & Finishes,         prepared    by 8 August 2022
                                                     Blackburn Jackson

                        1622-DA09            07      Perspectives,    prepared    by   Blackburn 8 August 2022
                                                     Jackson

                        1622_L01-01_C        C       Landscape Notes & Schedules, prepared 20   November
                                                     by Blackburn Jackson                  2023
                                                     (Annotated by Council)

                        1622_L03-01_C        C       Landscape Planting Plans, prepared by 20   November
                                                     Blackburn Jackson                     2023
                                                     (Annotated by Council)

                        1622_L07-01_01       01      Landscape Details, prepared by Blackburn 19 May 2022
                                                     Jackson

               2.     Deleted
                      Nature and Extent of Approved Use
               3.     The approved Dual Occupancy is comprised of two (2) small dwellings, and Office, in
                      accordance with the use definitions under Noosa Plan 2020.




                                                                                                        Page 2 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 3

               4.     The plot ratio of the development must not exceed 0.5:1, in accordance with the
                      administrative definition under Noosa Plan 2020.
                      Currency Period
               5.     This development approval lapses if the use has not happened by 18 August 2028, unless
                      an application to extend the currency period is approved by Council.
                      Building Height
               6.     The maximum height of the development must not exceed 8 metres above the natural ground
                      level, except where shown on Plan 1622-DA07, dated 11 February 2022.
               7.     Certification must be submitted to Council from a Licensed Surveyor which certifies that the
                      building/s do not exceed the maximum height requirement of this Decision Notice.
                      Performance Bond
               8.     Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be
                      submitted to Council, to secure performance of all conditions of this approval, prior to the
                      issue of a Development Permit for Building Works. The cash bond or trading bank guarantee
                      will be returned on performance of the conditions of approval less any costs incurred by
                      Council in respect of enforcing performance of this permit. Council reserves the right to call
                      upon the bond or guaranteed sum to effect compliance with conditions.
                      Street Identification
               9.     The street address of the development must be clearly visible and discernible from the
                      primary frontage of the site by the provision of a street number and, where appropriate, the
                      building name.
                      Water & Sewer Connections
               10.    An underground connection to reticulated water and sewerage must be provided to the
                      development site in accordance with the standards and requirements of Northern SEQ
                      Distributor–Retailer Authority (Unitywater).
               11.    A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to the development site (for MCUs).
                      Nature and Extent of Approved Use
               12.    Non-residential uses on the premises must not operate outside the hours of 7am to 9pm,
                      seven days a week, including public holidays.
                      The requirements of this condition must be included in the Community Management
                      Statement for any body corporate for the subject site.
                      Building Appearance
               13.    All air conditioning units or other mechanical equipment must be located at ground level, or
                      otherwise fully enclosed or screened such that they are not visible from the street frontages
                      nor adjoining properties.
               14.    All deck and balcony areas above ground floor must not be enclosed by permanent fixtures
                      such as shutters, louvres, glass panelling or the like, except where required to satisfy any
                      privacy condition of this Decision Notice.
                      Fencing and Walls
               15.    Any street fencing must be set back an average of at least 1 metre from the front property
                      boundary. Any fencing on the front boundary must not exceed a maximum height of 1.8m.
               16.    The area of land between the fence and the front property boundary must be densely
                      landscaped to obscure any fencing from the street.
               17.    Waste storage areas are to be screened from the roadside and internal areas within the
                      subject site.


                                                                                                      Page 3 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 4

                      Clothes Drying Areas
               18.    Each dwelling unit must be provided with access to an outdoor clothes line which is screened
                      from public view.
                      Protection of Privacy
               19.    The upper level balcony (BAL 1) located on the southern building face of Unit 2 must include
                      either balcony planter boxes, balustrading or fixed external screens, positioned in such a way
                      to obscure direct views into the habitable room windows or private open space areas of the
                      adjoining property.
                      Landscaping Works
               20.    The development site must be landscaped in accordance with PSP3 – Landscaping Plants
                      and Guidelines and generally in accordance with the approved plans.
               21.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
               22.    Deleted
               23.    Deleted
               24.    The existing vegetation in the road reserve is to be retained and managed as per the findings
                      and recommendations of the Arborist Report prepared by Arboriculture Contractors Australia
                      Pty Ltd, dated 27 April 2022. A qualified person* must be present if works are occurring within
                      the Tree Protection Zone.
                      Should one of the mature trees are to be removed, reasonable grounds must be given by the
                      qualified person*, and substituted with additional Baeckea virgata or Banksia integrifolia with
                      a minimum pot size of 100L or greater.
               25.    Deleted
               26.    Deleted
               27.    Deleted
                      External Works
               28.    David Low Way must be upgraded for the length of its frontage to the subject site. The works
                      must include in particular:
                      a.      construction of a pedestrian footpath in accordance with the conditions of this Decision
                              Notice
                      b.      removal of the existing property access and reinstatement of the kerb, footpath and
                              verge area to match the balance of the site frontage, including the provision of topsoil
                              and turf where the existing verge is grassed
                      Condition 28 (a) is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
                      infrastructure identified by Council’s LGIP to service the development.
                      Site Access and Driveways
               29.    A sealed access driveway must be provided from David Low Way to all parking and
                      manoeuvring areas of the development. The works must include in particular:
                      a.      a driveway crossover in accordance with Council’s Standard Drawing RS-051
                      b.      suitable safety measures, including warning signage, to improve driver awareness of
                              pedestrians and enhance pedestrian safety.




                                                                                                        Page 4 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 5

                      Car Parking
               30.    A minimum of eight (8) car parking spaces must be provided and marked on the site and
                      made available and accessible at all times while the use is open for business. The works
                      must include in particular:
                      a.      The small dwellings component of the development is to have available three (3)
                              parking spaces, one (1) space is to be available for visitors of the residential use, which
                              are clearly marked for that purpose and accessible at all times for visitor use.
                      b.      The office is to have available five (5) parking spaces, which are clearly marked for that
                              purpose.
                      c.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities.
               31.    All car parking areas and access driveways must be maintained exclusively for vehicle
                      parking and manoeuvring and kept in a tidy and safe condition at all times.
               32.    Directional signage must be provided to direct visitors and customers to the car parking
                      spaces provided on site.
                      Pedestrian and Bicycle Facilities
               33.    Pedestrian and bicycle facilities must be provided for the development. The works must
                      include in particular a 2.0 metre wide footpath within the road verge for the entire length of
                      the site’s frontage to David Low Way.
                      Condition 33 is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
                      infrastructure identified by Council’s LGIP to service the development.
               34.    A minimum of two (2) bicycle spaces are to be provided and dedicated for use by those
                      associated with the Office.
                      Stormwater Drainage
               35.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken generally in accordance with the “Site Based
                      Stormwater Management Plan” – Reference number 188-002-001, Revision A prepared by
                      BAX Engineering dated 3 February 2022 and must include:
                      a.      the deletion of the connection from the proposed infiltration pit to the existing infiltration
                              pit in the adjoining property, and
                      b.      any modifications to the proposed infiltration pit necessary due to the deletion of the
                              abovementioned connection
                      The amended plans must be submitted to Council at least 5 business days prior to the pre-
                      start meeting.
                      Condition 35 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                      infrastructure.
               36.    Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property.
                      Services
               37.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               38.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.




                                                                                                             Page 5 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 6

                      Easements
               39.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               40.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               41.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               42.    All earthworks and associated retaining structures/batters must be contained entirely within
                      the subject site unless written permission from the respective landowner(s) is provided to
                      Council. All earthworks must be undertaken in accordance with the provisions of Australian
                      Standard AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
               43.    Where the development involves excavation or filling over, or adjacent to, drainage, water
                      supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
                      provide a freeboard of 100mm above the finished ground surface level.
               44.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               45.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               Operational Works
               APPROVED PLANS
                      When conditions must be complied with
               46.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions, where there is conflict between the approved plans
                      and conditions of approval, the condition prevails.

                        Plan No.          Rev.   Plan/Document Name                             Date

                        188-002-002-B     B      General Notes prepared by Bax                  7 February 2022
                                                 Engineering

                        188- 002-100      B      Site Layout Plan prepared by Bax               7 February 2022
                                                 Engineering

                        188-002-200       B      Earthworks Layout Plan prepared by Bax         7 February 2022
                                                 Engineering




                                                                                                       Page 6 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 7

                        188-002-201        B      Earthworks Sections prepared by Bax           7 February 2022
                                                  Engineering

                        188-002-300        B      Grading & Drainage Layout Plan (as            7 February 2022
                                                  annotated by Council) prepared by Bax
                                                  Engineering

                        188-002-301        B      Pavement Layout Plan prepared by Bax          7 February 2022
                                                  Engineering

                        188-002-302        B      Sign & Line Marking Layout Plan prepared      7 February 2022
                                                  by Bax Engineering

                        188-002-401        B      Drainage Longitudinal Section prepared by     7 February 2022
                                                  Bax Engineering

                        -                  -      Arborist Tree Assessment Report by            27 April 2022
                                                  Arboriculture Contractors Australia Pty Ltd

                        1622_L01-          C      Landscape Notes & Schedules prepared by       20 November
                        01_C                      Blackburn Jackson                             2023
                                                  (Annotated by Council)

                        1622_L03-          C      Landscape Planting Plans prepared by          20 November
                        01_C                      Blackburn Jackson                             2023
                                                  (Annotated by Council)

                        1622_L07-          01     Landscape Details, prepared by Blackburn      19 May 2022
                        01_01                     Jackson

               CURRENCY PERIOD
               46.    Deleted
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               47.    All necessary approvals from external service providers (eg Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               48.    A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
               49.    Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               50.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Erosion and sediment control works;
                      d.      Other relevant parties




                                                                                                      Page 7 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 8

               51.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               52.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               53.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               54.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               55.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice
                      b.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines
                      c.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site
                      Pavement Design and Construction
               56.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               57.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               58.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               59.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Pathways
               60.    All pathways must be constructed in accordance with the following requirements:
                      a.      All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
                      b.      Provision must be made for disabled access at all kerb crossings associated with
                              pathways, in accordance with Council's current standards.
                      c.      All paths must have a slip resistant surface




                                                                                                     Page 8 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 9

                      d.      Expansion and contraction joints must provide a flush finish. Installation of joints by
                              saw cutting is preferred to ensure a smooth ride for cyclists
                      e.      The required work includes any modifications to ensure the footpath finishes flush with
                              all existing service covers and the like, or alternatively these services are raised or
                              altered, so as not to create a pedestrian safety hazard
               61.    Pathways must:
                      a.      terminate in a manner that ensures smooth transition to existing surfaces for public
                              safety
                      b.      be designed and constructed to comply with the Disability Discrimination Act (DDA),
                              Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
                              access and mobility
                      Site Access and Driveways
               62.    The driveway crossover must be constructed generally in accordance with Council’s
                      Standard Drawing RS-051 and any associated addendum.
               63.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               64.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete.
                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties
                      c.      Underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway
                      d.      Where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path
                      e.      The property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage. The developer is responsible for any necessary relocation
                              of existing services to provide this clearance and must contact the relevant service
                              authorities and comply with their requirements in relation to these works.
                      Stormwater Drainage
               65.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               66.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (eg by blocking or interfering with natural overland flows).
               67.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Erosion and Sediment Control
               68.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination. These
                      measures must be designed, implemented and maintained in accordance with “Best Practice
                      Erosion and Sediment Control” published by the International Erosion Control Association
                      (Australasian Chapter) (IECA, 2008), to the extent that such measures and practices are also
                      consistent with the following:


                                                                                                        Page 9 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 10

                      a.      Minimise Erosion
                              i.       For areas of the site which drain to a sediment basin, implement drainage and
                                       erosion control measures prior to rainfall which prevent or minimise rill erosion
                                       and gully erosion
                              ii.      For areas of the site which do not drain to a sediment basin, implement drainage
                                       and erosion control measures prior to rainfall (including contingency measures)
                                       which prevent or minimise erosion, including rain drop erosion, chemical erosion,
                                       rill erosion and gully erosion
                              iii.     Prior to the final inspection for the development, all site surfaces must be
                                       effectively stabilised using methods which have achieved effective short-term
                                       stabilisation and which will continue to achieve effective stabilisation in the
                                       medium to long-term. For the purpose of this condition, an effectively stabilised
                                       surface is defined as one that does not, or is not likely to result in visible evidence
                                       of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead
                                       to water contamination.
                      b.      Manage concentrated stormwater flows
                              i.       Prior to each rainfall event ensure concentrated stormwater flow paths are
                                       provided with capacity in accordance with IECA (2008) Table 4.3.1 and are
                                       structurally stable in all rainfall events for the following sources:
                                       (a)        From stormwater catchments upslope of the area of disturbance
                                             which are either stable or external to the site, ensure stormwater is diverted
                                             or managed either:
                                             i.    around the site or through the site without causing erosion and
                                                   without contaminating the flow; or
                                             ii.   if it is impractical to convey the flows around or through the site,
                                                   convey the flows into appropriately sized sediment basins without
                                                   causing erosion
                                       (b)   From all disturbed areas of the site to sediment basin(s) without causing
                                             erosion
                      c.      Minimise sediment released from the site
                              i.       Install and maintain additional sediment control measures within the site, as
                                       necessary to maximise sediment capture.
                              ii.      Minimise the tracking of material from the site onto roadways. Ensure that all
                                       material on roadways caused by vehicles leaving the site is removed without
                                       causing water contamination, prior to rainfall and at least at the end of each work
                                       day.
               69.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      c.      Been revised to address predicted rainfall events, and
                      d.      Achieve the desired environmental outcomes.


                                                                                                              Page 10 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 11

                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               70.    Drainage paths must be regularly inspected to ensure the sediment fences/measures are not
                      being bypassed as a result of sediment build up. Sediment laden runoff must be prevented
                      from leaving the subject site and entering neighbouring properties and/or stormwater
                      systems.
               71.    Soil exposure must be limited on the site to a distance of no more than 2m beyond the extent
                      of earthworks shown on the approved plans except where the exposed soil is effectively
                      stabilised without delay and prior to rainfall occurring.
               72.    A log book for the Erosion and Sediment Control measures and inspections must be
                      maintained by the site manager and made readily available to Council when requested. The
                      supervising engineer must verify and endorsed the E&SC measures upon their installation,
                      and periodically check these measures and the log book during construction and the
                      stabilisation stages. Any defects in erosion and sediment control devices, such as sediment
                      fences, are to be inspected and documented. Upon Inspection, the contractor is to determine
                      whether the device should be replaced or repaired. Documentation is to include how the
                      damage was caused and what measures can be implemented to reduce the possibility of
                      repeat occurrences. Any damage to either permanent or temporary water quality control
                      structures or devices is to be immediately rectified at the contractor’s expense.
                      The effectiveness of the erosion and sediment control devices must be monitored. All ESC
                      measures are to be inspected:
                      a.      at least daily (when work is occurring on site) or weekly (when work is not occurring on
                              site); or
                      b.      within 24 hours of expected rain; or
                      c.      within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
                              mobilise sediment on site).
                      Landscape
               73.    Landscape works must be undertaken in accordance with this Decision Notice.
               74.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
                      Damage to Services and Assets
               75.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION / PRIOR TO THE COMMENCMENT OF THE USE
                      Certification
               76.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
                      Bonds
               77.    Bonds must:




                                                                                                        Page 11 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 12

                      a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works.
                      b.      be calculated using a schedule of works and relevant bond equation
                      c.      have approval of the bond calculations and amount from Council prior to lodgement
                      d.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
               As Constructed Plans and ADAC XML Files (Council)
               79. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                    “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                    information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                                       Please Note: Further information and advice relating to the as-constructed
                                       drawing presentation, as-constructed survey capture and associated guidelines
                                       for preparation of a compliant ADAC XML digital file are available on the webpage
                                       titled “As Constructed Guidelines” and accessible at the Noosa Council Website:
                                       Planning & Development / Development Tools & Guidelines / As-Constructed
                                       Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.       Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                       conformance with applicable standards and specifications, along with the
                                       relevant descriptions of assets, services and structures and;
                              ii.      Licensed Surveyor in regard to the cadastral and locational information, levels
                                       and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.
                      On Maintenance
               80.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance
                      with Council’s relevant Planning Scheme Policy prior to the commencement of the
                      use. To achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy
                      c.      maintenance and operational manuals for all proprietary or site specific devices
                      Off Maintenance
               81.    Prior to requesting an Off Maintenance inspection the developer must provide a written
                      request for the Off Maintenance inspection.
               82.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements



                                                                                                         Page 12 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 13

                      b.      submitted certification falsely states works comply with approval requirements.
               83.    A final inspection and approval of the new works and any completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
               5.     REFERRAL AGENCIES

               The referral agencies applicable to this application are:

                Referral Status          Referral Agency and Referral Trigger                  Response
                                         Address
                Concurrence              SARA at DILGP SARA        Schedule 10, Part 4,        The agency provided its
                                         at DILGP Via MyDAS2       Division 3, Table 1, Item   response on 20
                                         at http://prod2.dev-      1 (10.4.3.1.1) -            January 2022
                                         assess.qld.gov.au/suite   Contaminated land           (Reference No. 2201-
                                         / (for assistance,        (unexploded ordnance)       26787 SRA). A copy of
                                         contact DILGP at 5352     (Planning Regulation        the response is
                                         9702 or                   2017)                       attached
                                         email:[email protected] )

               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               2.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               3.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Building and Construction Industry (Portable Long Service Leave) Levy
               4.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Preparation of a Preliminary Construction Management Plan
               5.     A Construction Management Plan must be submitted to Council at least 5 business days
                      prior to the pre-start meeting. The plan must address the following:
                      c.      traffic management during all aspects of the construction phase including:
                              iii.     a Traffic Management Control Plan in accordance with the Manual of Uniform
                                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                                       control measures prior to construction




                                                                                                       Page 13 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 14

                              iv.      maintenance of safe pedestrian access for the areas affected by the works during
                                       and after daily construction has ceased
                              v.       proposed fencing to the site during the construction phase of the development
                              vi.      approval of the Traffic Management Control Plan by the Department of Transport
                                       and Main Roads (DTMR) for any works on State controlled roads
                              vii.     provision for worker car parking
                      d.      maintenance and protection of water quality and existing drainage lines through the
                              construction site, through the implementation of appropriate erosion and sediment
                              control measures
                      e.      works programme identifying key components of the works and their respective
                              durations
                      f.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic, services and other relevant issues.
                      g.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details.
                      h.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      i.      identification of complaint management procedures including:
                              viii.    contact details for the on-site manager
                              ix.      dispute resolution procedures
                      j.      details on the location of external fill/dump sites/sources, the haulage route, type of
                              vehicle to be utilised during filling operations and frequency of usage. NB any damage
                              to the existing road system as a result of haulage operations shall be fully repaired at
                              the applicant’s expense
                      Private Infrastructure
               6.     All private infrastructure for the development must be designed to meet the planning scheme
                      requirements unless otherwise agreed by the relevant authority
                      Prestart, On and Off Maintenance Inspections Request
               7.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days notice of preferred inspection time.
               8.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               9.     A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise
                      Environmental Advisory Notes
               10.    The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               11.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control


                                                                                                        Page 14 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 15

               12.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               13.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the final inspection:
                      k.      Methods of stabilisation are:
                              •        appropriate for slopes and slope lengths; and
                              •        are consistent with best practice environmental management practices such as
                                       in the Manual for Erosion and Sediment Control or the IECA Manual; and
                      l.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                      Landscaping
               14.    For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
                      landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
                      current experience in the field of landscape design.
               15.    Public amenity trees are defined as any tree located within public streets, parks or areas that
                      will become publically owned as a result of this development.
                      Aboriginal Cultural Heritage Act 2003
               16.    There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                      approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                      The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                      carries out an activity must take all reasonable and practicable measures to ensure the
                      activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                      duty of care. Substantial monetary penalties may apply to individuals or corporations
                      breaching this duty of care. Injunctions may also be issued by the Land and Resources
                      Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
                      that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                      of Aboriginal cultural heritage.
                      You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
                      Equitable Access and Facilities
               17.    The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      m.      the Disability Discrimination Act 1992 (Commonwealth);
                      n.      the Anti-Discrimination Act 1991 (Queensland); and
                      o.      the Disability (Access to Premises – Buildings) Standards.
                      Advertising Devices
               18.    All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
                      (Administration) 2015 including both temporary and permanent signage. All freestanding,
                      pylon or pole signs or signage that is illuminated requires approval from Council prior to being
                      installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is
                      prohibited from being erected in the Shire.
                      Development Compliance Inspection
               19.    Prior to the commencement of the use, please contact Council's Development Assessment
                      Branch to arrange a Development Compliance Inspection.


                                                                                                           Page 15 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 16

                        Resubmission of Amended Plans Required
               20.      The conditions of this Decision Notice require resubmission of plan/s to Council with
                        amendments. Please address the amended plan/s to Council’s Development Assessment
                        Branch with the Reference No. MCU21/0228 and OPW21/0364.
                        Infrastructure Charges
               21.      All developments and/or changes to existing developments may require payment of
                        “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                        made pursuant to the planning legislation and regulations current at the time of issue. For
                        further information, please refer to https://www.noosa.qld.gov.au/planning-
                        development/development-tools-guidelines/infrastructure-charges
               7.       PROPERTY NOTES

               Not applicable.
               8.       VARIATION APPROVAL DETAILS

                   Type of Development Permit Required                           Subject of the required Development Permit

                   Development Permit for Building Works                         All building work.

               9.       FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               10.      SUBMISSIONS

               Not applicable.
               11.      RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               12.      OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Georgina Schramm
               Development Planner



               Enc:     Appeal Rights
                        Approved Plans/Documents
               cc.      Unitywater

               DECISION NOTICE HISTORY
               •     Original Decision Notice – 29 March 2022.
               •     Negotiated Decision Notice – 18 August 2022, with amendment to conditions 1, 3, 5, 15, 16, 19, 24, 30, 46, 56 & 79 and delete
                     conditions 2, 22, 23, 25, 26, 27 & 47.

               •     Decision Notice - Minor – MCU21/0228.01 – 19 February 2024, with an amendment to conditions 1 & 46.




                                                                                                                                Page 16 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Page 17

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 17 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Used in these records

About this file

File size
202 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change - MCU21 0228 01 & OPW21 0364 01 [As Published].pdf · 202 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.