2022-09-15 Ordinary Meeting Minutes

of 26

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

ORDINARY MEETING MINUTES                                                 15 SEPTEMBER 2022


        Landscaping
        11.   A minimum of 20% of the site must be retained as soft landscaping.
        12.   To screen the development, screening vegetation must be planted for the full
              length of the north and south boundaries, with the exception of the bin/gas/bike
              store area, in accordance with Council’s Planning Scheme Policy PSP2 -
              Landscaping. The planted vegetation must have a minimum pot size of 200mm
              and consist of native, endemic species with a mature height of not less than 8
              metres and a maximum spacing of 2 metre centres.
        13.   A mix of native landscaping, such as ground covers, shrubs and trees, is provided
              for a width of 5 metres from the seaward or rear boundary of the site. The planted
              vegetation must have a minimum pot size of 200mm and consist of native, endemic
              species as per Table 3.1 & 3.2 of PSP2 Landscaping for suitable coastal species.
              The planted vegetation must be planted at the following density:
              a.   trees must have a maximum spacing of 6m;
              b.   shrubs must have a maximum spacing of 1.5m; and
              c.   ground covers planted between the trees and shrub must achieve a dense
                   coverage.
        14.   The development is to provide adequate landscape buffering to protect the
              character of the beachfront, to the reasonable satisfaction of the Manager
              Development Assessment.
        15.   Two 100 litre street trees must be provided within the frontage. The trees must be
              a coastal species in accordance with PSP2 – Landscaping.
        Coastal Protection
        16.   External colours and finishes of the building must comprise                     of
              muted/environmental tones that blend with the natural environment.
        Pedestrian Access
        17.   A pedestrian access gate must not be installed along the seaward property
              boundary with direct access by residents to the beachfront area not being
              permitted.
        Geotechnical Stability
        18.   A footing system and erosion protection system must be designed for the proposed
              development to withstand the short-term erosion associated with a 500-year
              average recurrence interval storm event combined with shoreline recession due to
              sea-level rise for 2100 climate change. The short-term erosion associated with a
              500-year average recurrence interval storm event combined with shoreline
              recession due to sea-level rise for 2100 climate change to be considered for the
              design as per the recommendations of the Royal Haskoing DHV report ‘Report 66
              Seaview Terrace, Sunshine Beach Coastal Hazards Assessment, reference
              PA2906-RHD-ZZ-XX-RP-Z-0001 dated 3 June 2022.
        19.   The footing system and erosion protection system must in accordance with the
              works detailed in the Tectonic report “Geotechnical Investigation, Proposed
              residence 66 Seaview Terrace, Sunshine Beach”, (Reference 21370-001-Rev 1
              dated 28 April 2022) and other supporting documents referenced in the Tectonic
              report.
        20.   The design must include the protection of the northern and southern boundaries of
              the site to prevent erosion on neighbouring properties exposing the side
              boundaries of the site to erosion. The minimum extent of the side boundary
              protection must be determined by a line drawn at 28° extending upwards to the
              west from the base of the rear point of the erosion as per the recommendations of

                                                                               Page 18 of 26
Log in to download the original file

2022-09-15 Ordinary Meeting Minutes(PDF, 881KB).pdf · 902 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.