RFI - Appendix B Civil Engineering Report · MCU22/0038

of 110

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (17.1 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 3, section 1. The text section number identifies this passage in the reader.

  13 May 2022



         Issue - Stormwater Management Plan - Quantity
         Section 4.5.2 of the Stormwater Management plan does not detail how the existing stormwater
         infrastructure will take into account any increases in stormwater quantity and flows from the
         development of this site.

         Information Required
         Provide further information of how the site does not change the existing hydrological regime including
         drainage patterns and run-off quantity. Detail how the existing stormwater infrastructure for the Noosa
         Civic Shopping Centre and Hofmann Drive drainage systems, accounts for any increases or changes in
         runoff from the site.


Response:
Stormwater discharge from site is consistent with the overall Noosa Civic and Noosa Business Centre
masterplanning. The proposed development will connect into the drainage system for Noosa Civic and
Hofmann Drive. The sites minor flows will run through the existing pipe system whilst major flows will
overland flow down the internal roads prior to discharging to the creek to the south of the site in
accordance with the overall Noosa Civic and Noosa Business Centre development. There will be no
impacts to external developments as a result of the flows through the internal site system.


         Issue – Grass Swale construction on northern boundary
         The earthworks appear to encroach into Cov I. SP182845

         Information Required
         Provide information detailing how vegetation, and the Tree protection zones of this vegetation, in
         Covenant I will be protected during construction of the swale and batters along the northern boundary of
         the site.

Response:
All earthworks have been revised to be fully contained within the development site and do not extend
over the boundary. Any works completed within the vicinity of existing trees to be retained will be
completed under the supervision of the project arborist as required.

Should you require further information or clarification on any items within this request for information
response please feel free to contact the undersigned.

Yours faithfully




Lachlan Stephenson
For and on behalf of
MPN CONSULTING PTY LIMITED
ls:ls




  Excellence with Economy in Engineering                                                                  3
  l:\8000-8999\8600-8699\8662\letter\13-05-22 noosa council ltr.docx

Used in these records

About this file

File size
17.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

RFI - Appendix B Civil Engineering Report.pdf · 17.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.