20281 CD C - Landscape
Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.
Notes:
- Place the rootball on a firm base.
- Thoroughly water the root ball immediately after planting.
- Cultivate sides of excavated hole 50mm deep.
- Do not disturb kerb, road pavement or road side drainage works.
- Tease out roots on side of rootball when planting.
- Ensure top of rootball is not buried; expose and set flush with finished level.
Notes:
Set soil level at top of
- Place the rootball on a firm base.
rootball (at flare of trunk)
- Thoroughly water the root ball immediately after planting.
- Cultivate sides of excavated hole 50mm deep.
Pull away mulch - Do not disturb kerb, road pavement or road side drainage works.
from base of plant - Tease out roots on side of rootball when planting.
- Ensure top of rootball is not buried; expose and set flush with finished level.
50x50x2400 HW Timber stake: Form mulch berm
Place 600mm into the ground. Do to the perimeter of Notes:
not place through rootball. Secure the rootball - Place the rootball on a firmed base to achieve required FSL.
with hessian ties by looping in a - Thoroughly water the root ball immediately after planting.
figure eight pattern. - Number of stakes will vary with pot size. Refer plant schedule.
- Cultivate sides of excavated hole 50mm.
Raise plant 20-30mm above Distance to local
authority 90mm∅ capped slotted pipe
top of kerb. Hardwood stake: Place 600mm 75mm below top of planter
requirments
into the ground. Do not place connected to drainage system
Do not excavate through rootball. Secure with per Hydraulic Engineer
within 50mm of ties by looping in a figure eight River stone to
edge restraint or pattern. top of pipe
Hardwood Stake: Mulch
pavement. 100
Top of Kerb Raise plant 50mm above 25x25x90mm Place 600mm - refer to plans for organic or
FSL finished surface level. into the ground. Do not inorganic locations
Mulch: Pull away from base place through rootball.
of plant. Secure with ties by looping
50 Light weight podium mix per
300
Form an earthen basin in a figure eight pattern.
2
varies
specification
around base of plant. Mulch: Pull away from
Topsoil blend 1 1
base of plant.
1 Geotextile fabric
Bio-degradable Geo-fabric Form an earthen basin
30mm Atlantis drainage cell
Topsoil blend around base of plant.
or similar approved
min 300
Water retention
additive
Water retention additive Topping slab - If required.
100mm drainage gravel in
1 Topsoil blend Depth varies to achieve falls
heavy or poor draining soils. Connect drainage gravel Fertiliser: Do not allow
1 to drain.
to back of kerb, subsoil fertiliser to come in Fertiliser: Do not allow
Incorporate slow release organic drainage where contact with roots. contact with roots. Waterproofing and protection
fertilizer and water retention applicable width (w) - to Architect's Specification.
10 - 20mm Drainage gravel
additives to backfill per 2xw Water retention additive Podium / basement slab
Manufacturer's recommendations - refer Engineer's detail.
1 STREET TREE PLANTING 2 45-200ltr PLANTING 3 140-300mm PLANTING 4 PODIUM PLANTER
CD-200 1:10@A1, 1:20@A3
CD-200 1:10@A1, 1:20@A3 CD-200 1:10@A1, 1:20@A3 CD-200 1:10@A1, 1:20@A3
All trees to have 100% NATSPEC inspection prior to delivery to site
Notes: FSL
(X)
- All timber to be CCA pressure treated to
AS1604, Hazard 5, rough sawn pine. Timber edge
- All timber edges to be arissed to comply
with council standards.
FSL
- All timber ends to have one coat of Stakes Mulch
Cuprinol or equal prior to installation.
- to 100mm depth
- Stakes to be 400mm into ground at max.
1200mm centres, or as required to obtain Existing/compacted
Turf as specified
smooth curves. Top of stake to finish /subgrade/subase Soil blend or site topsoil
20mm below top of timber edge. Where - to 300mm depth
Topsoil
timber edges meet at corners provide
- to 100mm depth
double stakes.
- All fixings to be hot dipped galv. Cultivate subgrade
Cultivated subgrade
- Leading edge is to be free of burrs and - to 150mm depth
- to 150mm depth
splinters.
Existing subgrade
TIMBER EDGE STAKES (X) = Height above
38 50 finished surface level FIXINGS
50mm Bugle Headed
FLUSH
Batten Screws.
6 GARDEN BED TYPE 1 7 GARDEN BED TYPE 2 8 TURF PROFILE
100
20mm
100mm
150mm
75mm Bugle Headed
Batten Screws.
100mm Bugle Headed
CD-200 1:10@A1, 1:20@A3 CD-200 1:10@A1, 1:20@A3
Turf profile scale 1:5CD-200 1:5@A1, 1:10@A3
Batten screws.
100x38mm
50x50mm
5 EDGE TYPE 1- STREET TREES
CD-200 1:5@A1, 1:10@A3
Timber garden edge
Revision Date Amendment Drawn Checked
APPROVAL ONLY
CONSTRUCTION DETAILS NOT FOR CONSTRUCTION
A
B
C
2021.07.14
2021.07.14
2021.07.20
For Approval
For Approval
For Approval
XL
XL
XL
CS
CS
CS
CD-200 scale as noted
31 BOTTLEBRUSH AVENUE, NOOSA HEADS
20281 COLE PROJECTS QLD PTY LTD
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (20281 CD C - Landscape.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.