Decision Notice - Approved by Delegation of Authority MCU21 0164

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Officer: 	Patrick Murphy
Direct Telephone: 	07 5329 6436
Our Reference:	MCU21/0164
Your Reference:	002047
22 December 2021
Coffee Rock Investments P/L TTE
C/- RG Strategic Australia
PO Box 1818
NOOSA HEADS QLD  4567
[email protected]
Dear Sir/Madam,
Decision Notice
Planning Act 2016
I refer to your application and advise that on 16 December 2021, Council decided to approve the application, subject to conditions.
Details of the decision are as follows:
application details
Application No:	MCU21/0164
Street address:	6/52 Hastings St Noosa Heads
Real property description:	Lot 6 BUP 4745
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Material Change of Use – Food and Drink Outlet
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
PLANNING
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.

Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.

Plan No.	Rev.	Plan/Document Name	Date
TP 1.00	B	Ground Floor Plan, prepared by Frank Macchia	02.10.2021
TP 1.01	B	First Floor Plan, prepared by Frank Macchia	02.10.2021
TP 2.00	B	Elevations – with landscape, prepared by Frank Macchia	02.10.2021
TP 2.01	B	Elevations – no landscape showing, prepared by Frank Macchia	02.10.2021
TP 3.00	B	Sections - with landscape, prepared by Frank Macchia	02.10.2021
TP 3.01	B	Sections – no landscape showing, prepared by Frank Macchia	02.10.2021
TP 4.00	B	Perspective, prepared by Frank Macchia	02.10.2021
TP 4.01	B	Perspectives, prepared by Frank Macchia	02.10.2021
TP 4.02	B	Perspectives, prepared by Frank Macchia	02.10.2021
TP 4.03	B	Perspectives, prepared by Frank Macchia	02.10.2021
External Building Finishes
The development must be constructed in lightweight and natural materials, such as timber, as detailed on the approved plans.
Currency Period
This development approval lapses if the use has not happened by 16 December 2027, unless an application to extend the currency period is approved by Council.
Nature and Extent of Approved Use
The approved use must not operate outside the hours of 6am to 12:00 midnight           7 days a week.
Any live music must be contained within an enclosed acoustically treated environment.
The approved uses and associated activities must not result in environmental nuisances such as noise, visual or odour impacts that unreasonably diminish the amenity of the area or surrounding uses.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the issue of a Development Permit for Operational Works. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.

Frontage Works
The road reserve at the frontage must be landscaped in accordance with the approved landscape plan and maintained by the property owner for the life of the development.
The existing pavement/pavers within the road reserve must not be modified.
Landscaping
The development site must be landscaped in accordance with the approved landscape plan. The works must be undertaken in accordance with an Operational Works approval and the Noosa Plan for that specific area.
All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached.
All landscape works must be maintained generally in accordance with the approved design for the life of the development.
Damage to infrastructure
Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel, bridges or roadways must be repaired or reinstated to at least pre-existing conditions.
referral agencies
Not Applicable
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Infrastructure Charges
All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges
Equitable Access and Facilities
The plans for the proposed building work have NOT been assessed for compliance with the requirements of the National Construction Code - Building Code of Australia (Volume 1) as they relate to people with disabilities.  Your attention is also directed to the fact that in addition to the requirements of the National Construction Code as they relate to people with disabilities, one or more of the following may impact on the proposed building work:
the Disability Discrimination Act 1992 (Commonwealth);
the Anti-Discrimination Act 1991 (Queensland); and
the Disability (Access to Premises – Buildings) Standards.
Advertising Devices
All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1 (Administration) 2015 including both temporary and permanent signage. All freestanding, pylon or pole signs or signage that is illuminated requires approval from Council prior to being installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is prohibited from being erected in the Shire.

6	property notes
Not Applicable
VARIATION approval details
Not applicable.
further development permits required
Type of Development Permit Required	Subject of the required Development Permit
Development Permit for Building Works	All building work.
Operational Works	Landscaping,
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

Yours faithfully,
Kerri Coyle
Manager Development Assessment

Enc:	Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer1.xml]
Page 4 of 4

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 4

[Attachment: image1.png (image text)]
K Coy fs


[Attachment: image3.png (image text)]
ee) NOOSA COUNCIL
Log in to download the original file

Decision Notice - Approved by Delegation of Authority MCU21 0164.docx · 368 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.