FINANCIAL PERFORMANCE REPORT SEPTEMBER 2026 · Attachment 5 - Capital Financial Performance 30 September 2026
Attachment 5 - Capital Financial Performance 30 September 2026
Capital Expenditure Progress
Capital Expenditure - 30 September 2026
120,000
100,000
80,000
$'000
60,000
40,000
20,000
-
July August September October November December January February March April May June
Axis Title
Budget Actual
Capital Expenditure Progress by Portfolio
Actuals to
Annual Budget
% - 30 september 2026
45.00%
40.00%
35.00%
30.00%
25.00%
20.00%
15.00%
10.00%
5.00%
38.34% 40.18% 17.47% 6.34% 18.77% 21.27% 9.53% 0.00%
0.00%
Plant & Equipment Council Owned Buildings Other Structures Roads, Bridges & Stormwater Fleet Intangibles
Freehold Land Footpaths
Actuals to
Annual Budget
%