BUNNINGS WAREHOUSE, NOOSAVILLE | S
SURFACE WATER MANAGEMENT PLAN C Cardno
Bio-retention Systems
Bio-retention systems effectively combine a grass or vegetated swale with an infiltration
trench. They are considered to be extremely effective in removing sediment and nutrients.
Long bio-retention basins will be employed on site in the landscape divides of the car-park
area, in order to treat stormwater to an appropriate standard prior to release.
Porous Pavements
Porous pavements are not appropriate for high traffic areas due to increased maintenance
requirements. They are also less effective in steep areas. However, for relatively flat, low
traffic roads they could be suitable for this development, although their perceived expense
often leads to the preference of other measures in reaching quantity and quality. objectives.
Constructed Ponds and Wetlands
Wetlands require reasonably large flat areas of land. Given the constraints of this
development, and the ability to use bio-retention systems, the use of ponds or wetlands is
not recommended. @
Rainwater Tanks
The ability exists to install rainwater tanks throughout the development to reduce overall
water consumption. Tanks will be employed on site to collect roof runoff and provide a
source of irrigation for the nursery.
4.4 Proposed Stormwater Management
In summary, the stormwater management practices considered appropriate for use in this ,
development are:
« Rainwater tanks to collect roof runoff, to supply nursery irrigation needs;
* bio-retention swales, located in the car park landscape divides; and
¢ adetention basin for stormwater attenuation, located in the southeast corner.
To ensure that the Water Quality Objectives (described in the following section) can be
met, devices will be sized such that all stormwater up to the three-month design flow will ©
have passed through the nominated measures for treatment.
4.5 Site Specific Objectives
Water Quality Objectives (WQO) for the study site have been derived with reference to the
Queensland Environment Protection Agency Queensland Wafer Quality Guidelines (March
2006). The site is inland, and discharges would flow for approximately one kilometre along
what would be categorised in the guidelines as a ‘lowland stream’. It is located within in the
South-east Region. The WQQs so derived are shown in the table below.
Table 10 Water Quality Objectives
Suspended Sediments 6 mg/L
Total Phosphorus 50 pg/L
, Total Nitrogen 500 pg/L
Bunnings Warehouse Version 3 8 February 2007
J\3501 -54\WPASWMP3.doc Commercial in Confidence Page 10See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
0015E24E.001.pdfRelated documentPublic source context ↗
07/0256 - MCU - Bunnings Warehouse [As Published]Related documentApplication case desk ↗
About this file
- File size
- 13.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.