SPECIAL MEETING AGENDA 30 NOVEMBER 2022
Risks & Opportunities
Financial Risk Mitigation
Market fluctuation may lead to greater future capital • Broad construction industry movement is
costs. Other infrastructure projects seeing unclear although remains volatile. Considered
significant market cost increases. unlikely that a rapid reduction over near future
(22/23 FY) will be experienced. Contract signing
prior to expiration of the tender validity period
will fix current market rate.
• A 10% contingency has been allowed.
• The total cost is covered by the levy to the
NWRA and if an increase in cost is experienced,
it will be captured in future levy instalments.
Value for money • Pricing has been assessed as in-line with
current market rates.
90-day tender validity period expired on 25 October • Contract documents are to be prepared and
2022. Risk of rate rise as result of re-negotiation transmitted to the Contractor for execution as
and potential need for additional market factor soon as tender award is approved.
contingency. • The tenderer has yet to withdraw the offer, or
advise any other change in writing, and as such
the tender remains valid and current until such
time.
Final contract value exceeds budget. • Budget variation is based on current market
pricing. Contingency has been included in the
budget variation for unforeseen project costs.
• BR2 adjustment to budget will be prepared.
• Any price increase will be captured in the
allocation of levy costs to the residents.
Constructability Risk
Physically constrained work areas restrict available • Methodology considered in detail by evaluation
construction plant, equipment and methodologies panel.
and will impact traffic (vehicles and boating vessels) • Constrained works area has been taken into
and pedestrian movements through area. account by the contractor and has been planned
for.
• Works are targeted to occur during winter
months where possible in an attempt to
minimise potentially adverse seasonal weather
impacts.
The constrained site and proximity to adjoining • Constrained works area has been taken into
residents adds risks to the contractor. account by the contractor and has been planned
for.
• Progress works whilst capable construction
services are available.
• Contractor has experience undertaking works to
similarly constructed infrastructure.
Legal Risk
Potential claims from property owners alleging • Construction methodology will attempt to
noise, odour and access impacts from works. mitigate majority of access issues for residents
and businesses, with short-term closures of lock
system only.
Page 12 of 14