Noosa Harbour & Las Rias Foreshore Management Works Framework Dredge Management Plan
Customer Body Corporates of Noosa Harbour and Las Rias
Project 004024
Deliverable 002
Version 00
10 August 2026
Document Control
Document Identification
Title Noosa Harbour & Las Rias Foreshore Management Works
Project No 004024
Deliverable No 002
Version No 00
Version Date 10 August 2026
Customer Noosa Harbour Management Pty Ltd
Classification {None}
Author Josue Velez
Reviewed By Jeremy Visser
Project Manager Jeremy Visser
Amendment Record
The Amendment Record below records the history and issue status of this document.
Version Version Date Distribution Record
Contents
1 Context 1
1.1 Introduction 1
1.2 Objectives 1
2 Activity Description 2
2.1 Project Overview and Location 2
2.2 Construction Methodology 2
2.2.1 Overview 2
2.2.2 Revetment Wall Works 2
2.2.3 Sand Sourcing and Groyne Construction 3
3 Management Framework 4
3.1 Regulatory Context 4
3.2 Roles and Responsibilities 4
3.3 Training 5
3.4 Incidents and Complaints 5
3.5 Records 6
4 Receiving Environment and Key Project Impacts 7
5 Environmental Management and Monitoring 8
5.1 Water and Sediment Quality 8
5.2 Air, Noise, Light and Waste 9
5.3 Marine Megafauna and Shorebirds 10
5.4 Maritime Safety 11
5.5 Cultural Heritage 11
Context
Introduction
This report presents a framework dredge management plan (DMP) for undertaking foreshore management works along the Noosa River foreshore adjoining Noosa Harbour Resort and Las Rias Holiday apartments. This framework DMP sets the standards for environmental management to be adopted by a Contractor for these works and supports applications for environmental approvals. The Proponent for these works will be the collective body corporates of Noosa Harbour and Las Rias or a project manager acting on their half.
Prior to commencement of any works, the actions within this framework DMP are to be implemented by the Contractor and a detailed DMP is to be developed.
Objectives
This DMP constitutes a framework guiding the Contractor and associated parties to meet any applicable environmental legislation requirement, achieve best practice environmental management and anticipated regulatory requirements. This document aims to provide all relevant information, systems and procedures that will allow the Proponent and the Contractor to prevent or minimise potential environmental harm.
Specific objectives of this DMP include:
Identify sensitive receptors and potential impacts from the proposed activities
Ensure works are undertaken in a manner which avoids, manages and minimises potential environmental harm and protects receiving environment and sensitive receptors
Ensure works are compliant with legislative requirements and existing approvals
Ensure works meet the environmental and planning outcomes established under State and Federal government policy
Manage all waste streams in accordance with the waste management hierarchy of avoid, reduce, reuse, recycle, treat and dispose.
Activity Description
Project Overview and Location
The Project works consist of the following key elements:
Repair of a revetment wall
Dredging and pumping sand to:
Construct geotextile sand bag groynes
Nourish the foreshore, including complete burial of the revetment wall.
This will be supported by laydown and stockpiling of construction material at nearby parks, with materials to be loaded onto marine barges and transported to the works area.
Figure 2.1 shows the location of key project elements.
Construction Methodology
Overview
It is anticipated that all works would be undertaken by a single Principal Contractor, noting that aspects of the development may need specialist subcontractors (e.g. dredging contractor, marine contractor). The works would be undertaken with the following general sequence:
Mobilisation to site, including establishment of laydown areas
Reprofiling to prepare the site
Reconstruction of deteriorated segments of the revetment wall
Dredging and delivery of sand to fill geotextile containers in groyne configuration
Dredging and delivery of sand to bury revetment wall and groynes, including reprofiling works
Demobilisation.
Details of key components of construction are noted below. Note that the specific methodology may change depending on the Contractor appointed and would be confirmed through a Marine Execution Plan and Construction Management Plan.
Construction works are expected to take a period of 16 weeks and would require the temporary closure of this area during this time. While the foreshore is open to the public, due to its current eroded state, there is limited existing access and therefore disruption to public access would be limited.
Revetment Wall Works
While there is capacity for small excavators and similar plant to access the beachfront for construction works, access is not appropriate for trucks delivering rock and other material for construction. Additionally, there are no appropriate areas along the foreshore for the stockpiling of rock and material for construction. Therefore, it is intended that rock and geotextile material required for the revetment wall repairs would be delivered by road to temporary stockpiling areas located at the nearby Quamby Park and/or Bicentennial Park, subject to local approvals and site management arrangements to be agreed with Noosa Shire Council.
From these sites, material would then be loaded to marine barges and progressively delivered to the site for unloading and placement by excavators. These parks both have sloping foreshore access and would not require the use of any temporary structures (e.g. marine offloading facilities, pontoons), although beach access matting may be used to reduce potential erosion risks. The location of these stockpiling areas is shown in Figure 2.5 and included in the accompanying design pack. Following completion of all works, the contractor for the works would be required to ‘make good’ any disturbance in these parks to the satisfaction of Council, subject to relevant management arrangements.
All construction works on the foreshore of the site would involve excavators and similar plant.
Sand Sourcing and Groyne Construction
Following completion of the revetment wall repair, sand sourcing and groyne construction works will proceed in parallel. This will involve dredging sand from the sandbank immediately north of the Noosa River channel with a cutter suction dredge, with material then hydraulically pumped back to the site and directly into the geosynthetic containers. These containers will be placed in the configuration of the groyne, with additional layers added as the base layers are completed. Excess water from the dredging will filter through the bags and back to the Noosa River.
Once the groynes are completed, additional sand will be dredged and pumped to bury the revetment wall and groynes and achieve the design beach profile. This will involve some support from an excavator to ensure appropriate profile is met. Excess water from this placement will flow back to the Noosa River.
The location identified for sand sourcing is shown in Figure 2.4 and in the detailed design plans accompanying this application. This site has been chosen as it immediately adjoins the main channel and therefore can be dredged in a way that does not cause change in local hydrodynamic conditions. Dredging would occur across the footprint to a maximum depth of 1m to ensure only sand is targeted. The footprint shown is currently 7054m2 with a total capacity of 7054m3 if cut to a 1m depth, well in excess of the sand requirements for the project.
Pumping of sand will require the use of pipelines from the dredging area to the site. To avoid navigational safety risks, the pipeline will be sunk under the channel. Due to the proximity of the dredging area to the site, booster pumps are unlikely to be required.
Following completion of dredging works, the dredge vessel and associated pipe will be demobilised. All land-based plant and site equipment will also be demobilised.
Location of project elements
I:\004024- Noosa Resort\JPG\Fig2.2.projectlocation.png
Management Framework
Regulatory Context
The proposed works will be subject to the following approvals (being obtained by the Proponent):
Development Permit for Prescribed Tidal Works associated with:
Revetment wall repairs
Groyne construction
Establishment of a once off sand sourcing site
Development Permit for Material Change of Use (MCU) associated with concurrence Environmental Relevant Activities (ERAs) for capital sand sourcing (dredging) works
Environmental Authority associated with ERA 16(1)(a) for capital sand sourcing (dredging) works
Allocation of Quarry Material for the proportion of sand brought above mean high water springs (MHWS) during works.
These approvals will establish environmental and operational controls for the Project works and will supersede any requirements of this framework DMP to the extent of any inconsistency.
At a minimum, the following key performance outcomes are anticipated through these approvals or otherwise adopted for the Project:
No loss of marine plants
No oxidation of acid sulphate soils (ASS)
No generation of turbid plume >200m from dredging and work locations
No mortality of marine megafauna or shorebird species
No lighting, noise or dust emissions outside of standard hours (daytime, Monday to Saturday) or community expectations
All waste is accounted for and appropriately disposed
No uncontrolled release of hazardous contaminants
No maritime safety incidents
No disturbance of cultural heritage material.
These outcomes have been adopted throughout this framework DMP.
Roles and Responsibilities
Noosa Harbour staff and contractors are responsible for ensuring compliance with this DMP and associated approvals as well as general duties of care assigned under legislative instruments. This includes the general environmental duty, set out in s319 of the Environmental Protection Act 1994 (Qld):
A person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to minimise the harm.
Specific roles and responsibilities under this DMP are set out in Table 3.1.
Roles and Responsibilities under DMP
Role Responsibility Reports to
Proponent / Project Manager Overall responsibility for environmental management and compliance Obtaining and/or amending all environmental approvals; Review and approval of Contractor DMP Management of Contractor, including auditing of Contractor activities against DMP, approvals and contract specifications Notifying relevant government agencies of commencement and completion of works Reporting of environmental incidents to relevant government agencies. Body corporates
Contractor Superintendent Responsibility for day-to-day environmental management of all dredging and placement activities Implementation of actions in DMP Notifying Proponent / Project Manager of commencement, progress and completion of works Monitoring of impact of activities Implementation of corrective actions where required; and Reporting of environmental incidents to Proponent / Project Manager and relevant government agencies. Proponent / Project Manager
Contractor Staff Day-to-day implementation of DMP , as directed by Contractor Superintendent. Contractor Superintendent
Training
Noosa Harbour will ensure that the Contractor Superintendent will be appropriately inducted in the requirements of this DMP and associated approvals. The nature of this induction will be at the discretion of the Proponent.
The Contractor will be responsible for providing sufficient training and inductions for all staff in the requirements of the DMP, approvals, the general environmental duty, and general legislative compliance. Where relevant, the Proponent may set specific training requirements for the Contractor and their staff.
Incidents and Complaints
Any complaints received are to be recorded in a central Complaints Register maintained by the Proponent / Project Manager and to be governed in accordance with the Proponent’s complaints procedure. The Complaints Register must be maintained for the duration of the dredging works and an appropriate time thereafter (determined at the discretion of the Proponent and must include the following information:
Time, date, name and contact details of the complainant
Reasons for the complaint
Any investigations undertaken
Conclusions formed
Any actions taken.
Environmental incidents include any actual, possible or impending breach of performance criteria under the Contractor DMP, approval conditions, the general environmental duty or other legislative duties. Where an incident occurs, the following parties must be notified:
Proponent / Project Manager
Contractor Superintendent
Department of the Environment, Tourism, Science and Innovation (DETSI) – for instances of pollution, general environmental harm and/or breach of approval conditions
Department of Primary Industries (DPI) – for instances of damage to marine plants
Maritime Safety Queensland (MSQ) – for incidents related to or resulting in vessel collisions, obstruction of navigable areas, spills and impacts to aids to navigation.
Where possible, immediate action should be taken (at the discretion of the Proponent / Project Manager and/or Contractor Superintendent) to prevent further environmental harm, with more detailed corrective and/or rehabilitation action to be undertaken as set out in this DMP and/or as agreed with relevant agencies.
Records
All records required by this DMP and associated approvals must be retained by the Contractor for a minimum of five years. A copy of all records is to be provided to the Proponent on completion of the works.
Receiving Environment and Key Project Impacts
The lower Noosa River is part of a wave-dominated barrier estuary, with significant sand shoals formed throughout the river. The northern banks of the river are mostly undeveloped and features extensive mangrove and coastal forest communities, with other significant remnant vegetation also present at Noosa heads (across the river from the works site) and in upstream portions of Weyba Creek. The works site itself does not feature vegetation due to the developed and heavily eroded nature of the land but forms part of the broader mosaic of habitat and environmental values associated with the river. Within this area, key environmental features of note are:
Sand shoals and intertidal habitats utilised by resident and migratory shorebirds and waders, including areas of significant shorebird roosting and feeding areas near the river mouth
Generally low turbidity and high quality marine waters, with no major industrial discharges
These waters are scheduled as high ecological value (HEV) under the Environmental Protection (Water and Wetland Biodiversity) 2019, carrying a management intent of maintaining indicators for all environmental values (EVs)
Periodic seagrass, although this fluctuates with the dynamic sand shoals.
The area is also a popular recreational area, featuring boat-based activities by residents and tourists together extensive use of the foreshore. The works site is also immediately adjacent to resort areas used for recreational and tourism purposes.
Within this context, the key environmental risks of the Project requiring management are:
Generation of a turbid plume, including of contaminants within dredged material either through dredging and placement
Exposure of ASS through dredging and placement above MHWS
Loss of core shorebird roosting and foraging habitat
Strike of marine megafauna by vessels
Release of pollutants into the marine environment
Interference with recreational and commercial marine traffic.
These form the basis of the management measures relevant to the Project.
Environmental Management and Monitoring
Water and Sediment Quality
Key water and sediment-related Projects risks relate to dredge and placement plumes, oxidation of ASS, and potential marine pollution.
Water and sediment management actions
Objective To ensure Project works do not negatively impact long-term water quality associated with the EVs for the lower Noosa River.
Performance criteria No generation of turbid plume >200m from dredging and work locations No uncontrolled release of hazardous contaminants No oxidation of ASS
Actions Responsibility Timing
Undertake sediment testing in accordance with the National Assessment Guidelines for Dredging 2009 at the dredging location to identify potential pockets of ASS and contaminants Contractor Prior to commencement of works
Based on results of sediment testing, prepare a detailed dredging plan that avoid pockets of ASS, contaminants and silt OR If ASS pockets cannot be avoided, prepared an ASS Management Plan for the treatment of any ASS to be dredged Contractor Prior to commencement of works
Implement the detailed dredging plan OR ASS Management Plan Contractor During works
If pockets of silt are hit during dredging, immediately cease and dredge in other areas of known clean sand Contractor As required
Ensure appropriate pollution control equipment is available on every works vessel (dredge, work barges, support vessels) and at the foreshore works site Contractor During works
Ensure any fuel and hazardous contaminants are stored in bunded locations above Highest Astronomical Tide. Contractor During works
Immediately contain any spill, with all major spills (>15L) in the marine environment to be accompanied by deployment of spill boom or equivalent Contractor As required
Ensure all equipment is in good working order and free from leaks Contractor At all times
Monitoring Responsibility Timing
Visual monitoring of plumes at dredging and placement sites Contractor Continually
Visual inspection of fuel and hazardous contaminant storage sites Contractor Daily
Visual inspections of vessels for spill response equipment Contractor Weekly
Visual inspections of equipment for leaks Contractor Daily
Corrective Action Responsibility Timing
If excessive plumes are generated, investigate the cause of the plume and alter works to reduce plume extent. This may include one or more of the following: Cessation of dredging Movement of dredging location Dredging or placement only on outgoing/incoming tide Deployment of a silt curtain around dredging or placement sites Contractor As required
If ASS is oxidised, immediately treat and undertake an investigation to identify and implement remediation actions Contractor As required
If there are uncontrolled pollution events, liaise with MSQ to undertake a clean-up Contractor As required
Reporting Responsibility Timing
Prepare an Environmental Performance Report detailing: Activities undertaken; Environmental management actions undertaken; Results of monitoring; Any incidents and/or non-conformance with performance criteria and correction action undertaken; and Any perceived risks and/or concerns. Contractor Weekly
Maintain Environmental Performance Report and audit results. Contractor & Proponent Up to 5 years post works
Auditing Responsibility Timing
Inspection of works area to test compliance with conditions. Proponent / Project Manager Monthly
Air, Noise, Light and Waste
Dredging and foreshore management works will produce noise and may generate limited dust at the foreshore works site and laydown areas. The works will generate waste requiring management.
Air, noise, light and waste
Objective To ensure Project works do not negatively impact long-term amenity associated with the immediate area or produce unmanaged waste.
Performance criteria No lighting, noise or dust emissions outside of standard hours (daytime, Monday to Saturday) or community expectations All waste is accounted for and appropriately disposed
Actions Responsibility Timing
All works are to be undertaken 7:00am to 6:00pm Monday to Saturday, inclusive, with no work on public holidays. This does not preclude non-mechanical works outside of hours (such as site inspections) or necessary vessel movements in liaison with the Regional Harbour Master (RHM). Contractor During works
Investigate any complaints received regarding air, noise, vibration, lighting or waste to determine if there is an impact to local amenity. Contractor As required
Ensure equipment is working within appropriate noise and exhaust specifications. Contractor At all times
Develop and implement detailed waste management strategies in accordance with the waste management hierarchy of: Avoid or reduce, e.g. plan resources required for works with sufficient detail to prevent need for excess; remove need for certain waste streams where possible Reuse and recycle, e.g. identify what resources can be used for multiple purposes and/or sent to other users post works (including recycling facilities) Treat and dispose. Contractor During works
Capture and isolate all waste for disposal at appropriately licenced facilities. Contractor During works
Monitoring Responsibility Timing
Visual monitoring of works area (including Noosa River) to identify waste. Contractor Daily
Check of equipment and plant functionality against specifications. Contractor Daily
Review of complaints Contractor As required
Corrective Action Responsibility Timing
If emissions or amenity impacts are caused by equipment or plant, identify options to attenuate impact, including through use of: Screens Scheduling of work to periods when receptors are upwind Limiting operational hours. If suitable impact attenuation options are not available, discontinue use of the plant or equipment until it can be repaired. This may require stop works unless backup equipment is available. Contractor As required
If waste inappropriately managed, collect any loose waste and remediate impacts. Contractor As required
Reporting Responsibility Timing
Prepare an Environmental Performance Report detailing: Activities undertaken; Environmental management actions undertaken; Results of monitoring; Any incidents and/or non-conformance with performance criteria and correction action undertaken; and Any perceived risks and/or concerns. Contractor Weekly
Maintain Environmental Performance Report and audit results. Contractor & Proponent Up to 5 years post works
Auditing Responsibility Timing
Inspection of works area to test compliance with conditions. Proponent / Project Manager Monthly
Marine Megafauna and Shorebirds
Marine-based works could lead to the strike of marine megafauna and/or the disturbance of roosting and foraging shorebirds.
Marine megafauna and shorebird management measures
Objective To ensure Project works do not negatively impact on marine megafauna and shorebirds.
Performance criteria No strike of marine megafauna or shorebirds
Actions Responsibility Timing
Where shorebirds are present within the dredging area, dredge alternative parts of the shoals to avoid direct interaction. Contractor During works
Do not approach within 50m of marine megafauna during vessel movements. Contractor As required
Monitoring Responsibility Timing
Marine observations during all vessel movements/ Contractor Daily
Inspect sand shoals for shorebirds prior to dredging and dredge movements. Contractor Daily
Corrective Action Responsibility Timing
If vessel strike occurs, liaise with DETSI regarding appropriate management response. Contractor As required
Reporting Responsibility Timing
Prepare an Environmental Performance Report detailing: Activities undertaken; Environmental management actions undertaken; Results of monitoring; Any incidents and/or non-conformance with performance criteria and correction action undertaken; and Any perceived risks and/or concerns. Contractor Weekly
Maintain Environmental Performance Report and audit results. Contractor & Proponent Up to 5 years post works
Auditing Responsibility Timing
Inspection of works area to test compliance with conditions. Proponent / Project Manager Monthly
Maritime Safety
Vessel movements and use of dredge pipelines can cause risk of collisions with other vessels and river users.
Maritime safety management measures
Objective To ensure Project works do not negatively impact on maritime safety and use of the river
Performance criteria No maritime safety incidents
Actions Responsibility Timing
Develop a Marine Execution Plan in consultation with the RHM. At a minimum, the dredged material pipeline must be submerged under the main navigation channel. Contractor Prior to commencement of works
Implement the Marine Execution Plan Contractor During works
Monitoring Responsibility Timing
Monitor in accordance with Marine Execution Plan Contractor Daily
Corrective Action Responsibility Timing
If maritime safety incidents occur, liaise with MSQ to respond Contractor As required
Reporting Responsibility Timing
Prepare an Environmental Performance Report detailing: Activities undertaken; Environmental management actions undertaken; Results of monitoring; Any incidents and/or non-conformance with performance criteria and correction action undertaken; and Any perceived risks and/or concerns. Contractor Weekly
Maintain Environmental Performance Report and audit results. Contractor & Proponent Up to 5 years post works
Auditing Responsibility Timing
Inspection of works area to test compliance with conditions. Proponent / Project Manager Monthly
Cultural Heritage
No cultural heritage features are expected to occur within the works area as they represent dynamic coastal areas subject to historical disturbance. However, there remains the risk of encountering unknown cultural heritage features during dredging.
Cultural heritage management measures
Objective To ensure the Project works do not negatively impact cultural heritage
Performance criteria No disturbance of cultural heritage material
Actions Responsibility Timing
- - -
Monitoring Responsibility Timing
Inspect each dredge load for evidence of cultural heritage material Contractor Continually during dredging
Corrective Action Responsibility Timing
If Aboriginal cultural heritage items are found during works, the following steps are to be taken: Stop works. Take photographs of disturbed items and record the location. Ensure cultural heritage items are not moved any further. Notify the cultural heritage coordinator to allow them to attend. If a find occurs while monitors are on site, works in the immediate area must stop to allow the monitors to assess, however works in surrounding areas may continue. An agreement must be reached Contractor & Proponent As required
If human remains or Aboriginal cultural heritage features are discovered and/or disturbed, stop work immediately and consult with relevant government agency and/or Aboriginal Party representatives. Contractor & Proponent As required
[word/footer2.xml]
This report is prepared by BMT Commercial Australia Pty Ltd ("BMT") for the use by BMT's client (the "Client"). No third party may rely on the contents of this report. To the extent lawfully permitted by law all liability whatsoever of any third party for any loss or damage howsoever arising from reliance on the contents of this report is excluded. Some of the content of this document may have been generated using the assistance of Artificial Intelligence (AI).
Where this report has been prepared on the basis of the information supplied by the Client or its employees, consultants, agents and/or advisers to BMT Commercial Australia Pty Ltd ("BMT") for that purpose and BMT has not sought to verify the completeness or accuracy of such information. Accordingly, BMT does not accept any liability for any loss, damage, claim or other demand howsoever arising in contract, tort or otherwise, whether directly or indirectly for the completeness or accuracy of such information nor any liability in connection with the implementation of any advice or proposals contained in this report insofar as they are based upon, or are derived from such information. BMT does not give any warranty or guarantee in respect of this report in so far as any advice or proposals contains, or is derived from, or otherwise relies upon, such information nor does it accept any liability whatsoever for the implementation of any advice recommendations or proposals which are not carried out under its control or in a manner which is consistent with its advice.
© BMT 2026
004024 | 002 | 00 6 10 August 2026
[word/footer3.xml]
© BMT 2026
004024 | 002 | 00 5 10 August 2026
[word/header2.xml]
Noosa Harbour & Las Rias Foreshore Management Works
[word/header3.xml]
Noosa Harbour & Las Rias Foreshore Management Works
[word/header5.xml]
Noosa Harbour & Las Rias Foreshore Management Works
[Attachment: image3.png (image text)]
RED LuLg
LEGEND Title: Figure:
Tidal Works Location of the Project including tidal works and 22
{S Geotextile Sand Bags proposed dredging area. -
[) Sand Compartments Bureaus or ate taatnproain hmap
‘putilcaon
(T dows not warrant
(1) Revetment of maker rg he carvency and
\\ Indicative dredging area
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
R.004024.002.00_QuambyPl_DMP.docxRelated documentApplication case desk ↗
About this file
- File size
- 3.4 MB (large file)
- File type
- DOCX
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.