                     10.0 EXTERNAL CATCHMENTS DRAINAGE ROUTE

                     The eastern end of the Serenity Close roadway and the existing residential building at
                     the north-eastern corner of the Settlers Cove site; Macquarie Lodge and Petrie Mansions
                     were all constructed by RF Thompson Developments during the 1990’s and early 2000’s
                     predating the Settlers Cove Noosa Residential High Density Environmental Management
                     Plan (EMP 1) produced by WBM Oceanics Australia.

                     Current best practice of rainwater infiltration was not adopted for those early
                     developments and instead stormwater was collected and conveyed to Noosa Inlet via
                     traditional methods including the existing stormwater line mentioned in Section 2.0.

                     In accordance with the existing change approval and the previous version of this
                     report it is proposed that flows from external catchments be re-routed through the
                     development site on a revised alignment and in a traditional fashion consisting of
                     minor event flows conveyed underground via piped drainage with a landscaped
                     major event overland flow path above.


                     10.1 PIPED FLOWS (< 10 YEAR ARI)

                     The proposed route for minor event pipework and major event overland flow will be
                     generally westward from the existing sag point on Serenity Close following the
                     northern face of the proposed building and the southern extent of ‘quiet pool’
                     landscaped areas to the Serenity Close cul-de-sac head consistent with approved
                     architectural drawings.

                     It is proposed to upgrade existing pipework and headwalls within the road reserve
                     and pathway in order to cater for the increased catchment area but generally
                     maintain existing alignments and discharge point.

                     Notably the nett effect would be to combine the two (2) existing stormwater
                     discharge points into one with flows from the additional catchment area at the
                     eastern end of Serenity Close effectively moved around 120m westward.

                     A proposed sewer diversion will follow a similar route generally parallel to the
                     stormwater line.

                     Realigned pipework will be contained within an easement in favour of Council and ,
                     where sewer is adjacent a shared easement in favour of Council and Unity Water.
                     Notably the stormwater line passes under elevated structure in two areas, one in the
                     form of a footbridge and the other hotel units.
                     It is proposed that volumetric easements will be registered in these areas.

                     Refer to Engineering Drawings at Appendix A for details.

                     ________________________________________________________________________________________

                     A6769/25/SWMP/Rev OpW(A) – Feb 2025                                       Page 19 of 21
                     SH/PL
                                          Brah101 Pty Ltd t/as ALTA PROJECTS

Document Set ID: 24143616
                  23646596
Version: 1, Version Date: 24/09/2025
                          21/03/2025

Used in these records

About this file

File size
38.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Compiled Approved Plans OPW25_0042.02.pdf · 38.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.