(g) provide all equipment, materials, items, plants, and tools reasonably needed
for the undertaking of the relevant Project, other than that equipment stated
as being the responsibility of the Service Provider under Item 5.4 and Item 6
of the Project Particulars;
(h) use all reasonable endeavours to create and facilitate local community
support for, and engagement in, the Project;
(i) | comply with the Operations Manual, in so far as it is applicable to the Project
Sponsor; and
(j) facilitate safe and secure access to the Site of the Project for the Team for the
duration of the Project.
4.5 Work Plan
(a) The parties must perform the Project in accordance with, and otherwise
comply with, the Work Plan.
(b) No alteration to the Work Plan will be effective unless and until the change to
the Work Plan is agreed by both parties.
4.6 Project-specific work health and safety plan
(a) Prior to undertaking any Project activities, a work health and safety plan, must
be finalised and agreed between the parties to this Agreement.
(b) The Service Provider must prepare a work health and safety plan for the
Project which is consistent with this Agreement, the Agreement for Services,
the Deed (including the Operations Manual) and the Guidelines and provide a
draft plan to the Project Sponsor for comment.
(c) Without limitation, the work health and safety plan must:
(i) | detail the procedures that the Service Provider and Project Sponsor will
take in order to manage any work health and safety risks and incidents
that may arise during the undertaking of the Project;
(ii) | detail the roles and responsibilities of the Service Provider, Team
Supervisors, other Personnel of the Service Provider, and the Project
Sponsor (as applicable) in relation to work health and safety; and
(iii) | comply with all relevant work health and safety standards, policies and
Laws as applicable to the Project.
(d) Within 10 Business Days of receipt of the draft work health and safety plan
provided under clause 4.6(b), the Project Sponsor must provide detailed
comments on the draft plan. In providing comments on the draft work health
and safety plan, the Project Sponsor must consult, or provide contact
information so as to allow the Service Provider to consult, with any other
stakeholders who have shared responsibility for the work health and safety of
the Team.
(e) The Service Provider must consider all input from the Project Sponsor and
any other stakeholders consulted in accordance with clause 4.6(d) and
finalise the work health and safety plan.
(f) | Once finalised under clause 4.6(e), the work health and safety plan will form
part of this Agreement and the parties must perform the Project in accordance
with the final work health and safety plan.
(g) The Service Provider must, in consultation with the Project Sponsor and
stakeholders (as applicable), promptly update and modify the work health and
safety plan from time to time so as to address any new risks, changes in
circumstances or changes in applicable Laws and standards.
Green Army Project Agreement in relation to Managing weed threats from bushland reserves and coastal habitats in Noosa LGA.
Project ID B0270003901G TEM5191 issued 09/04/2015 page 13See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.