OVERALL SITE PLAN
SCALE 1:1000 A1

GENERAL NOTES:

0

1

NOT ALL SERVICES HAVE NECESSARILY BEEN RECORDED AND
SHOWN ON THE DRAWINGS. THE CONTRACTOR IS RESPONSIBLE TO
LIAISE WITH THE RELEVANT SERVICE AUTHORITY PRIOR TO
COMMENCEMENT OF CONSTRUCTION TO DETERMINE THE LOCATION
AND LEVEL OF ALL EXISTING SERVICE UTILITIES. THE CONTRACTOR
SHALL BEAR THE COST OF ANY DAMAGE TO EXISTING SERVICES.

THE CONTRACTOR SHALL OBTAIN ALL AS-CONSTRUCTED SURVEY
FOR ROADWORKS, DRAINAGE WORKS, SERVICE CONDUITS ETC.
PRIOR TO BACKFILLING. ALL SURVEY TO BE CARRIED OUT BY A
LICENCED SURVEYOR TO THE REQUIREMENTS OF THE SHIRE
ENGINEER.

SURFACE LEVELS SHOWN ARE INTERPOLATED FROM A SPOT LEVEL

SURVEY, THEREFORE DESIGN LEVELS BASED ON THIS INFORMATION
MAY BE VARIED BY THE SUPERINTENDENT ON SITE.

20 40 60 80 100m

beep} |

SCALE 1:1000 A‘, 1:2000 A3-

 

ROADWORKS NOTES:

1

THESE DRAWINGS ARE TO BE READ IN CONJUNCTION WITH IPWEAQ &
NOOSA SHIRE COUNCIL STANDARDS.

THESE DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE
LANDSCAPE ARCHITECT'S DESIGN DRAWINGS.

SEDIMENTATION CONTROL DEVICES TO BE PROVIDED IN ACCORDANCE

WITH THE ENVIRONMENTAL MANAGEMENT PLAN.

ROAD PAVEMENTS TO BE COMPACTED TO ACHIEVE A MINIMUM DRY
DENSITY RATIO (M.D.D.R.) OF 100% STD

ALL CONDUITS TO BE IDENTIFIED BY BRASS PLAQUES ON KERB AND.
CHANNEL AS PER IPWEAQ STANDARD DRAWING R-0160 U.N.O.

WHERE CONCRETE DRIVEWAYS ABUT KERB & CHANNEL, THE
CONTRACTOR IS TO CONSTRUCT A COMMERCIAL CROSS-OVER IN
ACCORDANCE WITH IPWEAQ STANDARD DRAWING RS-051.

PROVIDE ENERGEX AND TELSTRA CONDUITS UNDER DRIVEWAYS &
FOOTPATHS (IF REQUIRED).

ALL WORK IS TO BE COMPLETED IN ACCORDANCE WITH ALTA
PROJECTS STANDARD SPECIFICATION.

ROADWORKS AND DRAINAGE SET-OUT INFORMATION |S AVAILABLE
FOR THE CONTRACTOR VIA COMPUTER MODEL PROVIDED BY ALTA

PROJECTS. HOWEVER, ALTA PROJECTS ACCEPTS NO RESPONSIBILITY

FOR INCORRECT SETOUT FROM THE DATA PROVIDED. CONTRACTOR
SHOULD CONFIRM THE CORRECT COORDINATES WITH THE
HORIZONTAL CURVE DATA PROVIDED ON THESE DRAWINGS.

CARPARK! INTERNAL PAVEMENT NOTES

© THESE DRAWINGS SHALL BE READ IN CONJUNCTION WITH ALTA PROJECTS STANDARD
SPECIFICATIONS, IPWEAQ, LOCAL AUTHORITY AND DEPARTMENT OF TRANSPORT AND MAIN
ROADS (DTMR) AND AUSTRALIA STANDARDS. ANY CONFLICTS SHALL BE REFERRED TO THE
ENGINEER FOR CLARIFICATION.

« ALTA PROJECTS HAVE NOT UNDERTAKEN A RISK ASSESSMENT OF THE PROPOSED CARPARK
DESIGN AND LAYOUT WITH RESPECT TO TRAFFIC OR PEDESTRIAN SAFETY, TRIP HAZARDS,
WPHS REQUIREMENTS ETC. SPECIALIST ADVICE SHOULD BE SOUGHT IN THIS REGARD.

SETOUT

« EXISTING SURFACE LEVELS AND CONTOURS SHOWN ARE BASED ON DIGITAL SURVEY
MODELS PROVIDED. EXISTING LEVELS MUST BE CONFIRMED ON SITE BY THE CONTRACTOR
AND ANY DISCREPANCIES REFERRED TO THE ENGINEER.

« ALLCARPARK SETOUT TO BE AS PER DIGITAL CO-ORDINATES OR DIMENSIONED DRAWINGS
PROVIDED. CONTRACTOR MUST NOT RELY ON DIGITAL DRAWING FILES OR SCALING OF
DRAWINGS.

SUBGRADE

 SUBGRADE SHALL BE OF SOAKED CBR 15 MATERIAL OR BETTER, FREE FROM TOPSOIL,
ORGANIC OR OTHER DELETERIOUS MATERIAL.

* SUBGRADE SHALL BE COMPACTED TO 98% MDD (AS 1289 E1.1) AND SHALL NOT SHOW
MARKED DEFLECTION UNDER 8 TONNE AXLE LOAD AT PROOF ROLL.

« ANY SOFT SPOTS SHALL BE EXCAVATED TO COMPETENT MATERIAL AND REPLACED WITH
SELECT MATERIAL FROM SITE OR TYPE 2.5 GRAVEL AT THE ENGINEER'S DIRECTION.

* SUBGRADE SHALL BE GRADED TO PROFILES MATCHING FINISHED SURFACE AND ALL AREAS
SHALL DRAIN TO SUBSOIL DRAINS.

» SUBSEQUENT PAVEMENT LAYERS MUST NOT BE PLACED UNTIL THE ENGINEER HAS
APPROVED ALL TEST RESULTS, SUCCESSFUL PROOF ROLL HAS BEEN CARRIED OUT AND THE
ENGINEER HAS PROVIDED WRITTEN APPROVAL TO PROCEED.

 

GRANULAR PAVEMENT

« FINAL PAVEMENT DESIGN SHALL BE DETERMINED BY THE ENGINEER UPON RECEIPT OF

SUBGRADE SOAKED CBR RESULTS AFTER THE COMPLETION OF BULK EARTHWORKS.

» ALL GRANULAR PAVEMENT SHALL COMPLY STRICTLY WITH ALL CURRENT DTMR QUALITY
STANDARDS FOR THE NOMINATED PAVEMENT TYPE AND SHALL BE SUPPLIED BY A DTMR
ACCREDITED QUARRY.

« PAVEMENT PLACEMENT SHALL NOT COMMENCE UNTIL MATERIAL QUALITY TEST RESULTS
HAVE BEEN APPROVED BY THE ENGINEER.

PAVEMENTS SHALL BE PLACED AT DEPTHS NOT EXCEEDING 200mm AND SHALL BE
COMPACTED TO 100% MDD (AS 1289 E1.1), SLURRIED AND TRIMMED TO PROFILE REFLECTING
FINAL DESIGN SUCH THAT A TIGHT PAVEMENT MATRIX IS ACHIEVED

WHERE CEMENT TREATMENT |S NOMINATED BY THE ENGINEER CEMENT DESIGN AT THE
NOMINATED RATE MUST TAKE PLACE AT AN ACCREDITED PUG MILL. NO ON-SITE CEMENT
TREATMENT WILL BE ACCEPTED.

* ASPHALT PRIME SHALL NOT BE PLACED OVER BASE COARSE PAVEMENT UNTIL:

- ALL TEST RESULTS HAVE BEEN APPROVED.

- ASUCCESSFUL PROOF ROLL HAS BEEN CARRIED OUT.

- AS CONSTRUCTED SURVEY HAS BEEN APPROVED.

- ENGINEERS WRITTEN DIRECTION TO PROCEED IS OBTAINED.

eeee

REINFORCED CONCRETE NOTES:

GENERALLY, CONCRETE SHALL BE IN ACCORDANCE WITH AUSTRALIAN STANDARD SPECIFICATIONS
AS 3600 "SAA CONCRETE STRUCTURES CODE".

IN ADDITION TO THE ABOVE CODE THE FOLLOWING AUSTRALIAN STANDARD

SPECIFICATIONS AND CODES OR THEIR LATEST REVISION SHALL APPLY:

AS 1012 PTS 1-19 METHODS FOR THE TESTING OF CONCRETE (METRIC UNITS).

AS 3583.1,2,3,8 METHODS OF TEST FOR SUPPLEMENTARY CEMENTITIOUS.
MATERIALS FOR USE WITH PORTLAND CEMENT.

AS 3582.1 SUPPLEMENTARY CEMENTITIOUS MATERIALS FOR USE WITH PORTLAND
CEMENT- FLY ASH

AS 1141 METHODS FOR SAMPLING AND TESTING AGGREGATES.

AS 1302 STEEL REINFORCING BARS FOR CONCRETE.

AS 1303 HARD DRAWN STEEL REINFORCING WIRE FOR CONCRETE.

AS 1304 HARD DRAWN STEEL WIRE REINFORCING FABRIC FOR CONCRETE.

AS 3972 PORTLAND AND BLENDED CEMENTS.

AS 1379 READY-MIXED CONCRETE (METRIC UNITS)

AS 2758 PART 1 CONCRETE AGGREGATES.

AS 1478, 1479 CODE OF PRACTICE FOR USE OF CHEMICAL ADMIXTURES IN CONCRETE.

AS 3610 FORMWORK FOR CONCRETE.

SUPPLY:

ALL CONCRETE IS TO BE SUPPLIED BY A LICENSED READY MIXED CONCRETE MANUFACTURER. NO ON SITE
BATCHING IS ACCEPTABLE.

MANUFACTURERS MUST HAVE AN APPROVED AND CERTIFIED QUALITY ASSURANCE PROGRAM IN PLACE AND
BE APPROVED BY THE ENGINEER PRIOR TO SUPPLY OF ANY CONCRETE.

ALL MATERIALS, STORAGE, BATCHING, ETC. TO CONFORM TO THE REQUIREMENTS OF THE RELEVANT
AUSTRALIAN STANDARDS.

ALL CONCRETE TO BE NORMAL-CLASS IN ACCORDANCE WITH AS 3600 UNLESS NOTED OTHERWISE.

ALL CONCRETE SHALL HAVE A SHRINKAGE STRAIN NOT EXCEEDING 600 MICROSTRAIN

ALL CONCRETE IS SPECIFIED BY 28 DAY COMPRESSIVE STRENGTH UNLESS NOTED OTHERWISE.

ALL REINFORCEMENT TO BE SUPPLIED BY A REGISTERED MANUFACTURER WITH AN APPROVED AND
CERTIFIED QUALITY ASSURANCE PROGRAM IN PLACE. ALL REINFORCEMENT IS TO COMPLY WITH THE
REQUIREMENTS OF AS 1302, AS 1303 AND AS 1304 AS APPLICABLE.

ALL REINFORCEMENT IS TO BE DELIVERED TO SITE FREE FROM OIL, GREASE OR OTHER SURFACE
COATINGS WHICH MAY IMPAIR BOND TO CONCRETE.

ALL REINFORCEMENT TO BE 500 MPA MINIMUM YIELD UNLESS NOTED OTHERWISE.

FORMWORK:

ALL CONCRETE OTHER THAN CAST AGAINST GROUND, SHALL BE PLACED AGAINST TIMBER, PLYWOOD
OR STEEL FORMS.

ALL FORMWORK SHALL COMPLY WITH THE REQUIREMENTS OF AS 1509 AND AS 1510.

REFER ARCHITECT'S DRAWINGS FOR REQUIRED FORMWORK CLASS WHERE APPLICABLE. CLASS B
FORMWORK SHALL BE ADOPTED UNLESS NOTED OTHERWISE.

ALL TEMPORARY FORMWORK, FALSEWORK, PROPPING, BRACING, TO BE DESIGNED AND CERTIFIED
BY A REGISTERED PROFESSIONAL ENGINEER (RPEQ) PRIOR TO ERECTION.

ALL REINFORCEMENT TO BE SUPPORTED OFF FORMS WITH PLASTIC OR PLASTIC TIPPED WIRE CHAIRS.
TO PROVIDE THE SPECIFIED COVER. ALL CONCRETE CAST AGAINST GROUND TO BE UNDERLAIN BY
WATERPROOF MEMBRANE.

TRANSPORT:

ALL CONCRETE IS TO BE TRANSPORTED TO SITE IN AGITATOR TRUCKS.

CONCRETE NOT PLACED WITHIN ONE HOUR AFTER BATCHING MAY BE REJECTED AT
THE ENGINEER'S DISCRETION.

PLACEMENT, COMPACTION AND FINISHING:

CONCRETE TO BE PLACED IN FORMS BY HORIZONTAL 'CHUTING' NO MORE THAN 3M, CONCRETE
PUMPING OR KIBBLING.

UNDER NO CIRCUMSTANCES SHALL CONCRETE BE INDUCED TO FLOW HORIZONTALLY BY USE OF
VIBRATORS.

ALL CONCRETE SHALL BE PLACED CONTINUOUSLY BETWEEN CONSTRUCTION JOINTS AS DETAILED
IN SUCH A MANNER AS TO AVOID 'COLD JOINTS'. CONSTRUCTION JOINTS SHALL BE LOCATED AS
DETAILED ON DRAWINGS OR AS INSTRUCTED IN WRITING BY THE ENGINEER.

ALL CONCRETE IS TO BE COMPACTED UPON PLACEMENT USING 50mm DIAMETER VIBRATORS.
SLABS AND BEAMS ARE TO HAVE A FILM OF APPROVED ALPHATIC ALCOHOL APPLIED TO THE
SURFACE,

DIRECTLY AFTER SCREEDING, PRIOR TO FLOATING, REGARDLESS OF WEATHER CONDITIONS.
ADDITIONAL PROTECTIVE MEASURES SUCH AS CHILLED MIX WATER, SHADING PLACEMENT AREAS,
WIND BREAKS, ETC. MAY BE REQUIRED BY THE ENGINEER IF PLACING CONCRETE DURING
UNUSUALLY HOT, DRY OR WINDY CONDITIONS.

ALL CONCRETE SLABS SHALL BE STEEL TROWEL FINISHED UNLESS NOTED OTHERWISE.

BROOM FINISHING, WHERE SPECIFIED, SHALL BE CARRIED OUT AFTER STEEL TROWEL FINISHING
ALL CONCRETE TO BE ORDERED AND PLACED AT 80MM SLUMP UNLESS NOTED OTHERWISE.

NO WATER TO BE ADDED ON SITE UNLESS APPROVED BY THE ENGINEER.

TESTING:

ALL CONCRETE TESTING IS TO BE CARRIED OUT BY A NATA REGISTERED LABORATORY,

IN STRICT ACCORDANCE WITH THE REQUIREMENTS OF AS 1012.

THE FOLLOWING TESTING SCHEDULE IS TO BE ADOPTED IN ADDITION TO THE REQUIREMENTS
OF THE MANUFACTURER'S QUALITY ASSURANCE PROGRAM

- AMINIMUM OF ONE TEST (3 CYLINDERS) TO BE TAKEN FROM EACH ELEMENT CAST ON ANY
GIVEN DAY (EG. COLUMNS, FOOTINGS, ETC)

- AMINIMUM OF ONE TEST (3 CYLINDERS) TO BE TAKEN FROM EACH CONCRETE STRENGTH
GRADE CAST ON ANY GIVEN DAY.

- A MINIMUM OF ONE TEST (3 CYLINDERS) TO BE TAKEN FROM EACH 50m? OR PART THERE OF
CAST ON A GIVEN DAY FOR EACH STRENGTH GRADE.

ALL SAMPLES ARE TO BE TAKEN FROM THE AGITATOR, ON SITE.

IF WATER IS ADDED ON SITE, WITH THE ENGINEER'S PERMISSION, SAMPLES FOR TESTING
SHALL BE TAKEN AFTER THE ADDITION OF WATER.

CURING:
ALL CONCRETE IS TO BE CURED BY AN APPROVED METHOD FOR A MINIMUM OF 28 DAYS AFTER FINISHING.
CURING METHOD IS TO BE APPROVED BY THE ENGINEER PRIOR TO CONCRETE PLACEMENT AND SHALL
GENERALLY CONSIST OF ONE OR A COMBINATION OF THE FOLLOWING METHODS

- CONTINUOUS WATER PONDING.

- COMPLETE ENCASEMENT IN A WATERPROOF FILM (EG. POLYTHENE).

- APPLICATION OF AN APPROVED CURING COMPOUND.

 

NOTE: ONLY DRAWINGS MARKED "FOR CONSTRUCTION" AND BEARING AN ORIGINAL SIGNATURE SHALL BE USED FOR CONSTRUCTION PURPOSES.

Design:

 

 

 

REV

 

DATE DESCRIPTION BY | CHKD

 

 

 

 

 

DIRECTOR APPROVAL
RPEQ- 4784

 

Checked

 

Datum _AHD

PROJECT:

Web: hitp:/www.alta.net.au

 

A‘ SHEET SIZE

 

 

 

for CAPE BOUVARD DEVELOPMENTS

FILENAME : 96107-18-RO1-R02.éug-DATE 281/18 12:Mipm - XREF': a8 107-X-BASE; a6107-X-SURVEY; a6107X-ARCH landscape: a61O7-X-ARCH; H-Aporoved-SH; H-Chfbted-SH

PROPOSED RESIDENTIAL DEVELOPMENT STAGES 4A & 4B

roan Brah 101 pty Itd Va Alta Projects
: ABN. 91611 354 511
Date: MAY 2016 26 Memorial Avenue, Cotton Tree
PO Box 559, Cotton Tree, QLD, 4558
bE Tel (07) 5475 4125 Fax (07) 5479 1607] at SERENITY CLOSE, NOOSA

ENGINEERING : DESIGN : MANAGEMENT mail: [email protected]

DRAWING TITLE:
ROADWORKS OVERALL SITE PLAN AND NOTES.

 

 

Revision Sheet
1 of 1

DRAWING No: 46107/18/RO1

 

© This plan is Copyright. Other than for the purposes of and subject to the conditions prescribed wander the
Copyright Act, no part of it may in any form or by any means (electronic, mechanical, micro copying, photo
copsing, recording or otherwise) be reproduced, stored in a retrieval system or transmitted without the prior

faften permfsion of AUfh Project. Alf ntellctanl property eusins wiln AKI Projects leagues shoal
Council Ref Seavected fo AUT Poets rer "

 

 

 
Full text of the other 3 pages

Page 2

        

{SSSSSSSSSSSSSS

|
PZZ774
przeeeE ZO

aes Sess SSS

i

     
         
   
    

ss)

FLA DELLA EEN

 

PROPOSED CONCRETE
COMMERCIAL DRIVEWAY. REFER
DRAWING R04 FOR DETAILS

  

RL15.25

RL15.0

ars rChus 60
: WR x

;
2 “NX

ZPZTZZT A)

[LEELA LT LAZLALE

 

  

STAGE 4B "\,
BASEMENT ~~
FFL12.10

   
   

«

 

LEGEND:
Dy PROPOSED LIGHT DUTY CONCRETE
PAVEMENT AREA
PROPOSED TYPE''' INTEGRAL KERB
Be

PROPOSED TYPE 'B3’ INTEGRAL KERB

seemeeQ@eess= PROPOSED DRAINAGE NETWORK

TPIT ~~ PROPOSED TOP OF BATTER

------ PROPOSED TOE OF BATTER
5
oe PROPOSED DESIGN SURFACE LEVEL

----+- 50—---— FINISHED SURFACE CONTOUR

_509 EXISTING SURFACE CONTOUR
—— —£I0H— — — EXISTING OVERHEAD ELECTRICAL
—— —EUG— — — EXISTING UNDERGROUND ELECTRICAL
—— —1 — ——_ EXISTING TELSTRA RETICULATION
— — —p— — —_ EXISTING STORMWATER DRAINAGE
— — —w— — —_ EXISTING WATER RETICULATION
— — —s— — —_ EXISTING SEWER RETICULATION
—— —c— —— EXISTING GAS MAIN

2 EXISTING TREE

PROPOSED CONCRETE DOWEL JOINT
PROPOSED CONCRETE BOLSTER JOINT
PROPOSED CONCRETE EXPANSION JOINT

 

ALL KERB, KERB & CHANNEL,
WHEELSTOPS & BOLLARDS TO
BE PAINTED "SAFETY YELLOW"

 

0 2.0 4.0 6.0 8.0 10.0m

|

SCALE 1:100 At, 1:200 A3

 

NOTE: ONLY DRAWINGS MARKED "FOR CONSTRUCTION" AND BEARING AN ORIGINAL SIGNATURE SHALL BE USED FOR CONSTRUCTION PURPOSES. ] Design: PBL

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Brah 101 pty Itd t/a Alta Projects PROJECT. DRAWING THLE
Drawn: MJ y ss ROADWORKS LAYOUT PLAN
A.B.N. 91 611 354 511
Date: May 2046 ABN oteits645ii = | PROPOSED RESIDENTIAL DEVELOPMENT STAGES 4A & 4B
checees L Tal (07) 8475 4128 Fax (07) 479 1607 | at SERENITY CLOSE, NOOSA DRAWINGNO: A64Q7/18/RO2 ae
ecker : . . Email: [email protected] = 7 —
ENGINEERING : DESIGN : MANAGEMENT © This plan is Copyright. Other then for the purposes of and subject to the conditions prescribed under the
www. net. 0] ct, no part of it may in any form or by any means (electronic, mechanical, micro copying, photo—
[enor] senseo Ra ies a | set SiaGcroR MpaROVAL Dan a Web: hitp/mwwalta.net.au for CAPE BOUVARD DEVELOPMENTS ene cid ania iu” declaw sttaty t a i r
REV | DATE DESCRIPTION BY | CHKD RPEQ- 4784 ‘At SHEET SIZE FILENAME : 26107-18-RO1-R02.dwg -DATE : 3/10/18 -155tpm - XREF's: a6107-X-BASE; a6107-X-SURVEY; a6107-X-ARCH landscape: aB107-X-ARCH; H-Approved-SH; H-Chelked-SH Council Ref: Tededel aun Pret AT Snfeiectl property remains within ALTA Projects. all enquiries should

 

 

Page 3

 

    
 
 

 

 

  

  
    

  
   

 

  

  
 
    

    

 

 

 

 

 

 

 

 

 

 

 

 

 

    
 

  

 

 

 

 

 

 

 

 

 

 

 

 

al
ol
a
| RAMP 1
4m 2.7m 7m , 15.6m
1
SERENITY CLOSE (FALL AME
an
VARIES ! VARIES
VARIES VARIES
RL15.75 1RL15.75 -IRL15.60 pits.29 Se MAXFALL ting 1S MAK
oe = RL14.92 | | SOFFIT FFL 15.0
2 4
g om call 7 STAGE 4B
N 1in8 pals BASEMENT
RUZ 35 f AS |RUI21 airy SM FALL Ch puta _FFL12.10
SECTION
SCALE 1:100 AT
RAMP 2
CONCRETE CARPARK 975m
SOFFIT FFL 17.1 i 3.05
2m. Am.
5% MAX FALL wo STAGE 4A ,
aN RL14,.78 10% MAX 5 7 BASEMENT B99 Car Vertical Clearance
=> SI FALL) orig POR FALL | RL14.2 FFL14.20 Overall Length 5.200m
= Overall Width 1.940m
Overall Body Height 2.200m
Min Body Ground Clearance 0.100m
Track Width _ 1.840m
SECTION Lock-to-lock time _ , 4.00s
SCALE 1100 At Curb to Curb Turning Radius — 6.300m
0 2.0 40 6.0 8.0 10.0m_
SCALE 1:100 A1, 1:200 A3
NOTE: ONLY DRAWINGS MARKED "FOR CONSTRUCTION" AND BEARING AN ORIGINAL SIGNATURE SHALL BE USED FOR CONSTRUCTION PURPOSES. Design: MB Brah 101 pty Itd Ua Alta Projects PROJECT: DRAWING TITLE:
Drawn: MB DRIVEWAY RAMP LONG SECTIONS
Date: MAY 2016 26 Memorial Aventis. Cotton Tree PROPOSED RESIDENTIAL DEVELOPMENT STAGES 4A & 4B
ff) PO Box 559, Cotton Tree, QLD, 4558 Revision Sheet
IE Tel (07) 5475 4125 Fax (07) 5479 1607] at SERENITY CLOSE, NOOSA DRAWING No: 64(97-18-RO3 A | 1 of 1

osiror018

REVISED SECTIONS

 

 

REV

 

DATE

 

DESCRIPTION

 

BY

 

CHKD

 

 

DIRECTOR APPROVAL

RPEQ- 4784

Checked

 

ENGINEERING : DESIGN : MANAGEMENT Email: [email protected]

 

Datum _AHD

Web: hitp:/www.alta.net.au

 

 

A‘ SHEET SIZE

 

FILENAME :26107-18-R02- ROADWORKS SECTIONS dug DATE : 810/18 - 1:80pm - XREF':H-Approved-SH; H-Checkoo-SH

 

 

for CAPE BOUVARD DEVELOPMENTS

 

Council Ref:

© This plan is Copyright. Other than for the purposes of and subject to the conditions prescribed wander the
Copyright Act, no part of it may in any form or by any means (electronic, mechanical, micro copying, photo
copsing, recording or otherwise) be reproduced, stored in a retrieval system or transmitted without the prior
wnitten permission of ALTA Projects. all intellectual property remains within ALTA Projects, all enquiries should
be directed to ALTA Projects.

 

 

 

Page 4

 

COMMERCIAL DRIVEWAY 'A' - 5.70m WIDTH

 

 

  

 

 

 

 

 

 

 

 

 

 

   

 

 

 

 

 

 

 

 

 

 

 

COMMERCIAL CROSSOVER NOTES:-
1. Concrete N32 in accordance with AS 1379 and AS 3600.
2. Reinforcing fabric to AS 1304. Lap fabric 250mm.
3. Depths of concrete and reinforcing steel shown are the
minimum requirements for good foundation conditions, and
average traffic loading. Where this does not apply, depths of PROPERTY BOUNDARY
concrete and reinforcing shall be increased to suit specific |
conditions.
4. Reprofile adjacent footpath to match driveway. Footpath SAWCUT AND
earthworks adjoining concrete must be well compacted BREAKOUT BACK OF
5. Compaction for subgrade 95% Standard to AS 1289.5.1.1. KERB AND CHANNEL
6. Where subgrade is less than CBR 5 excavate and provide concrete Oo nn
imported material to satisfaction of the Superintendent. CONCRETE I ~
7. Concrete driveway unless otherwise approved FOOTPATH FOOTPATH ann CESS
8. Paver and/or proprietary concrete surface finishes to driveway bl z x @
shall only be used when approved by Local Authority. Ss
9. Refer project drawings or Local Authority Standard Drawings 3
for Verge Type Cross Sections. s
10. All dimensions in millimetres. 2
= t= |
[ 600 (Kerb taper
1500 NOM 1500 NOM |
B1 BARRIER KERB
COMMERCIAL DRIVEWAY AND CHANNEL
(<)) CROSSOVER ‘A’ DETAIL
NOTE: DRIVEWAYS ARE TO BE CONSTRUCTED IN
ACCORDANCE WITH IPWEAQ STD DRG RS-051
ALL KERB, KERB & CHANNEL,
WHEELSTOPS & BOLLARDS TO
BE PAINTED "SAFETY YELLOW"
NOMINAL FACE. ALL KERBS ADJACENT CONCRETE
OF KERB PAVEMENTS TO BE PAINTED
' "SAFETY YELLOW’
110 | 49
pope
—_—____
150
SETOUT POINT & LEVEL
& PROPOSED CONCRETE PAVEMENT LEVEL
| ~ - 125mm CONCRETE (N32)
KERB TO BE CAST . VISQUEEN VAPOUR BARRIER a < a SL82 MESH TOP 40 COVER
INTERGRAL WITH SLAB EARTHWORKS LEVEL 3 (TO BE CONFIRMED DURING
CONSTRUCTION)
INTEGRAL KERB - TYPE B
PAVEMENT JOINTS TO EXTEND THROUGH KERB KKK 100mm CBR15 MATERIAL
DIOS onpacteb 10 100% MBO

NOMINAL FACE
OF KERB

 

KERB TO BE CAST
INTERGRAL WITH SLAB

    

SONS

 

 

 

ALL KERBS ADJACENT CONCRETE

PAVEMENTS TO BE PAINTED
"SAFETY YELLOW’

 

 

  

SEX K RRR
SSO
RRR RINE

     

INTEGRAL KERB - TYPE B3
PAVEMENT JOINTS TO EXTEND THROUGH KERB

 

 

LIGHT DUTY CONCRETE PAVEMENT DETAIL

SCALE 1:10

   

VISQUEEN VAPOUR BARRIER

   

FINISHED PAVEMENT LEVEL

  

100mm CONCRETE (F'C = 25MPa)

CONCRETE FOOTPATH

SCALE 1:10
e PROVIDE BOLSTER JOINTS @ 3m CTS

100

SL72 MESH
40 COVER

 

20mm SAND LAYER

¢ PROVIDE EXPANSION JOINTS @ 12m CTS

1500

4IN8

SL72 MESH

3500 NOM

| 25%

200UM VISQUEEN.

50mm BEDDING SAND

40 TOP COVER.

(_».\ SECTION

YT) SCALE 1: 20 (A1)

DOWEL SOCKETS TO
MANUFACTURERS SPEC.
OR EQUAL

PROPERTY
BOUNDARY

—/

 
 
 

 

175 MIN

- TOOL FINISH EDGES

R16 GALVANISED DOWELS (400 LONG)
| AT 300 CTS CENTRAL

SL82 MESH
& COVER

 

125

 

 

 

 

 

 

 

SL82 MESH
40 COVER

125

 

  

 

200

 

 

PROVIDE AT 9.0m

200 UM VISQUEEN

 

LIGHT DUTY CONCRETE PAVEMENT DOWEL JOINT (DJ)

x 9.0m MAXIMUM CENTRES

NTS.

DOWEL SOCKETS TO
MANUFACTURERS SPEC.
OR EQUAL

   
  
  

R16 GALVANISED DOWELS
(400 LONG) AT 300 CTS

10mm ABELFEX OR EQUIV.

200 UM VISQUEEN

LIGHT DUTY CONCRETE PAVEMENT EXPANSION JOINT (EJ)

N.T.

CUT EVERY SECOND
WIRE OF MESH

S

TOOL FINISH CONCRETE
BREAK SLAB FULL DEPTH
WHILE STILL "GREEN"

 

 

 

 

 

 

 

 

200 UM VISQUEEN
LIGHT DUTY CONCRETE PAVEMENT BOLSTER JOINT (BJ)
NTS.
NOTE: ONLY DRAWINGS MARKED "FOR CONSTRUCTION" AND BEARING AN ORIGINAL SIGNATURE SHALL BE USED FOR CONSTRUCTION PURPOSES. | Design: MB . PROJECT: DRAWING TITLE
Drawn MB Brat 101 ply td va Ala Projects ROADWORKS DETAILS
Date: MAY 2016 26 Memorial Aventis. Cotton Tree PROPOSED RESIDENTIAL DEVELOPMENT STAGES 4A & 4B

/ PO Box 559, Cotton Tree, QLD, 4558 Revision Sheet

Check - Tel (07) 475 4125 Fax (07) 5479 1607 at SERENITY CLOSE, NOOSA DRAWING No: 46497.48-RO4 | 1 of 1
ecked - ] ENGINEERING : DESIGN : MANAGEMENT ail: [email protected] © This plan is Copyright, Other than for the purposes of and subject to the conditions prescribed under the
Copyisn dct ao fortat & amy in any frm dr Oy aay teens (electron, mcehanlal mic copying, pholo=

 

 

 

DIRECTOR APPROVAL

Datum _AHD

Web: hitp:/www.alta.net.au

 

 

 

 

 

Rev | DATE DESCRIPTION BY | CHKD

 

 

RPEQ- 4784

 

 

A‘ SHEET SIZE

FILENAME : 26107-18-R04.dug -DATE: 28018. 12:46pm - XREFS: H-Approved-SH; H-Checked-SH

 

 

for CAPE BOUVARD DEVELOPMENTS

copsing, recording or otherwise) be reproduced, stored in a retrieval system or transmitted without the prior
wnitten permission of ALTA Projects. all intellectual property remains within ALTA Projects, all enquiries should

 

Council Ref:

be directed to ALTA Projects.

 

 

Used in these records

About this file

File size
2.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Civil Drawings - Driveway.pdf · 2.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.