2.      Provide amended plans and supporting calculations which fully address Condition 30 of
        MCU21/0083. If the applicant does not have the capability to undertake modelling, then
        a deemed-to-comply approach such as that nominated in Section 4.3 of the Flooding
        and Stormwater Management Guidelines (SCC, 2020) may be an acceptable
        alternative. Include calculations for the maximum water level in the detention tank and
        demonstrate that freeboards are met.
Issue
Freeboard to unit FFL’s
Information Required
3.      Some of the nominated Unit FFLs have minimal elevation above the driveway levels and
        resulting surface stormwater flows. Consider improving the resilience of the units to local
        flooding by providing a step-up into the units from the carport and garage areas.
Issue
The applicant has not provided sufficient information to demonstrate compliance with
Conditions 42-45 of MCU21/0083.
Information Required
4.      Provide the required Operational Waste Management Plan that demonstrates
        compliance with the conditions. The plan must include but not be limited to:
        4.1. Load rating on the underground tanks. Please note that refuse collection trucks
              weigh 23.5T
        4.2. The location and number of 1100 litre bins
        4.3. The expected service levels (Refuse, Recycle and Garden)
        4.4. Clarification if the pedestrian shared zone has an awning and suitable horizontal
             and vertical clearances are available for the whole length of the refuse collection
             truck route within the site
Issue
The submitted plans do not provide sufficient information to demonstrate how service provision
(i.e. the location of the Pad Mount Transformer, fire fighting booster pump, water, sewer,
power, WSUD, loading bays, waste bin storage etc) will impact on the provision of landscape
areas to meet Performance Outcomes PO1, PO2, PO3, P12, of the Landscape Code in
relation to the sites general amenity, the provision of shade and a sustainable outcome.
Information Required
5.      Provide a Consolidated Services Plan to demonstrate how the applicable Performance
        Outcomes can be achieved. This may include:
        5.1. a single overlayed plan to show areas of deep planting exclusive of services where
             trees are capable of being planted and allowed to grow to full form without
             management input (heavy pruning, removal, interference with infrastructure
        5.2. the location of the Pad Mount Transformer
        5.3. the location of the fire fighting booster pump
Issue
The submitted plans do not demonstrate compliance with a few of the conditions MCU21/0083
Information Required
6.      Indicate on the plans the directional signage as described in Condition 27




                                                                                           Page 2 of 3
Log in to download the original file

Information Request OPW22-0319.pdf · 134 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.