29. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed water tight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
241071 - Flood Storage Calculations no date
Prepared by Lindsay Consulting
24-1071- A Flood Storage Model Site Plan 29 December 2024
F1
Prepared by Lindsay Consulting
24-1071- A Flood Storage Model Perspective View 29 December 2024
F2
Prepared by Lindsay Consulting
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
Equitable Access and Facilities
2. The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
b. the Anti-Discrimination Act 1991 (Queensland); and
c. the Disability (Access to Premises – Buildings) Standards.
Page 5 of 7
Document Set ID: 23690366
Version: 4, Version Date: 16/04/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original