During Construction

The site arborist shall be present to supervise any excavation, trenching or tunnelling located on the site
that may affect any tree roots and shall keep a record of works to present to Noosa Shire Council after
completion of construction.

There will be no allowed access within the fenced off tree protection zones without the consent of the site
arborist.

Post Construction

A post construction assessment shall be undertaken by the site arborist to determine the health and vigour
of all retained trees on the site. Any documentation that council may require will be submitted for review at
this time.

The assessment shall include recommendations for any future pruning works or any corrective
arboricultural action to be taken if required.

The site arborist will liaise with the landscape architect and landscaper to minimise any disturbances to the
retained trees on the site during landscaping. If at any point landscape works with the landscaper are
identified that may cause damage to the trees, the site arborist is to work with the landscaper to eliminate
detrimental impacts.

Work or construction that is contrary to these guidelines shall make the person responsible or liable for any
damage to any tree.

If the work or construction contrary to these guidelines results in the loss of any tree, implementation of
remedial arboricultural procedures, and / or required removal of any tree, the person responsible is liable
for any cost incurred for these actions, in addition to any fines imposed by Noosa Shire Council.

If this work or construction results in the loss of any tree, a tree valuation (Thyer’s Method based on the
tree condition prior to construction) undertaken by the site arborist will determine the amount of
compensation available to the owner of the property, on and above any other cost incurred by the
responsible person.

At no point are these guidelines finite, and at any time the site arborist may designate additional procedures
or requirements to protect the trees on the site when required.




Arborist Report Impact Assessment – TSA: 5635.1 4 Ventura Street Sunrise Beach.
Treesafe Australia Pty Ltd. June 2025© *Refer to explanatory Notes.

Page 12 of 18
Log in to download the original file

MCU25 0079 - Negotiated Reference Documents (As Published).pdf · 23.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.