2016-09-06 S&O Committee - Attachment 1 to Item 2 - Asset Management Roadmap
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
ID Task Name Duration 16 23 May '16 27 Jun '16 1 Aug '16 5 Sep '16 10 Oct '16 14 Nov '16 19 Dec '16 23 Jan '17 27 Feb '17 3 Apr '17 8 May '17 12 Jun '17 17 Jul '17 21 Aug '17 25 Sep '17 30 Oct '17 4 Dec '17 8 Jan '18 12 Feb '18 19 Mar '18 23 Apr '18 28 May '18 2 Jul '18 6 Aug '18 10 Sep '18 15 Oct '18 19 Nov '18 24 Dec '18 28 Jan '19 4 Mar '19 8 Apr '19 13 May '19 17 Jun '19 22 Jul '19 26 Aug '19 30 Sep '19 4 Nov '19 9 Dec '19 13 Jan '20 17 Feb '20 23 Mar '20 27 Apr '20 1 Jun '20 6 Jul '20 10 Aug '20 14 Sep '20 19 Oct '20 23 Nov '20 28 Dec '20 1 Feb '21 8 Mar '21 12 Apr '21
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 AMS Enablers 320 days
2 Improvement RoadMap (short) 1 mon CH2M
3 Agreed Program Manager (short) 1 day NSC Management Team
4 Refine Asset Management Governance Arrangements 30 days
5 Develop Draft Governance Structure for Council Consideration 2 wks Bryan O'Connor
(short)
6 Refine, seek approval of and embed stucture (short) 1 mon AMT,Bryan O'Connor,NSC Management Team
7 Communications 300 days
8 Develop draft Communications Framework for internal stakeholders 2 wks Deb Bambrook,Bryan O'Connor
(short)
9 Refine, seek aproval of and institutionalise Internal Communications 1 mon AMT,Bryan O'Connor,Deb Bambrook,NSC Management Team
Framework (short)
10 Develop draft Communications Framework for external stakeholders 1 mon Bryan O'Connor,Deb Bambrook
(medium)
11 Refine, seek approval of and institutionalise External 3 mons AMT,Bryan O'Connor,Deb Bambrook,NSC Leadership Team
Communications Framework (medium)
12 Change Management 280 days
13 Engage with HR on Change Management Approach (short) 1 mon Will Burgess-Dean,Bryan O'Connor
14 Develop and/or integrate any necessary Change Management 3 mons AMT,Bryan O'Connor,Will Burgess-Dean
documentation protocols (medium)
15 Context of the Organisation 175 days
16 Develop SAMP 175 days
17 AMS Scope 20 days
18 Agree Scope of AMS Asset Coverage (short) 1 wk Bryan O'Connor,AMT
19 Document rationale for AMP scopes and priorities (short) 2 wks AMT,Bryan O'Connor
20 Develop Noosa AMS Functional "Block Diagram" (short) 1 mon AMT,Bryan O'Connor
21 Environmental Scan 25 days
22 Data gathering for AMS PESTLE / SWOT Analysis ‐ Optional (short) 1 mon Deb Iezzi,AMT,Bryan O'Connor
Alternatively, employ Corporate Plan outputs
23 AMS PESTLE / SWOT Analysis Workshop ‐ prep and delivery 1 wk Deb Iezzi,Bryan O'Connor,External Provider
(short)
24 Stakeholder Analysis (Incorporate in AMP Development) 80 days
25 Develop Approach and Template (short) 1 mon Bryan O'Connor,AMT
26 Consolidate current stakeholder information (short) 1 mon AMN,AMT,Bryan O'Connor
27 Mapping Stakeholders and Needs (Short) 2 mons Bryan O'Connor,AMN
28 AM Objectives (Levels of Service) 80 days
29 Document currently available Levels of Service (short) 1 mon AMN,Bryan O'Connor
30 Develop Noosa Los Framework (short) 1 mon Bryan O'Connor,AMN,AMT,NSC Leadership Team
31 AM Decision‐Making 40 days
32 Review / Refine "8 Point Score" Approach for AM applicability 1 mon Bryan O'Connor,AMT
(medium)
33 Develop asset management decision‐making criteria for individual 2 mons AMN,AMT,Bryan O'Connor
AMPs (short)
34 Develop and Agree SAMP Template (short) 1 mon CH2M,AMT,AMN,Bryan O'Connor
35 Develop and document SAMP (short) 3 mons AMN,AMT,Bryan O'Connor
36 Leadership 320 days
37 Review / Update AM Policy (short) 1 mon Bryan O'Connor,CH2M,AMT
38 Roles and Responsibility 100 days
39 Review existing Roles / Responsibility Matrix (medium) 2 mons Bryan O'Connor,Will Burgess-Dean
40 Develop comprehensive RACI Chart for the AMS (medium) 3 mons AMN,Bryan O'Connor,Will Burgess-Dean
41 Planning 1146 days
42 Risk Framework and Methodology 400 days
43 Determine AMS risk/opportunity assessment requirements 2 mons Paul Bright,AMT,Bryan O'Connor
(medium)
44 Amend existing Council Risk approach, as necessary (medium) 18 mons AMT,Bryan O'Connor,Paul Bright
45 Life‐cycle Analysis 40 days
46 Integrate with SMEC Modelling (short ‐ exist project) 2 mons Bryan O'Connor
47 Investment Planning 80 days
48 Review existing Council asset investment review / approval 2 mons Wayne Jensen,AMT
processes (medium)
49 Develop / refine Investment Planning Framework (medium) 2 mons Wayne Jensen,AMT
50 Investment Delivery 1146 days
51 Contracts 690 days
52 Capture of LoS and Delegation of AM Responsibilities (medium / 2 mons AMT,Bryan O'Connor,Phill Parkman
long) ‐ Note: Outsourced Delivery consideration
53 Guidelines for Alternative Forms of AM Contracting (long) 2 mons Phill Parkman,AMT
54 Project Management 140 days
55 Note: No Corporate PM Procedures ‐ Consolidate? (long) 4 mons Nick Wellwood
56 PM Training Regime (medium / long) 3 mons Nick Wellwood,Will Burgess-D
57 Handover (as Con) 120 days
58 Handover Procedures in‐Development ‐ Part of PD Toolkit (short) 2 mons Bryan O'Connor,Mark Lewis,Wayne Jensen,As Constructed Working Group
59 Project Capitalisation Process Development ‐ Document 4 mons Bryan O'Connor,Nick Wellwood,Wayne Jensen,Beth Potter,As Constructed Working Group
Procedures (medium)
60 Asset Management Planning Platform 355 days
61 Develop and Agree AMP Templates (short) 1 mon Bryan O'Connor,AMN,External Provider
62 Asset Strategies 280 days
63 Capture and document existing asset strategies (short) 2 mons Bryan O'Connor,AMT
64 Develop / refine asset‐specific Levels of Service (short / medium) 12 mons Bryan O'Connor,AMT
65 State of the Assets Report 40 days
66 Develop State of the Asset Report ‐ Consider Annual Report? 2 mons AMN,Bryan O'Connor,External Provider
(medium) ‐ Note: High‐level at first
67 Asset Management Plans 205 days
68 Develop Draft List of AMPs and their likely sequence. 1 mon AMT,Bryan O'Connor
69 Precinct Plans 120 days
70 Hastings Street Precinct Plan (medium) 3 mons
71 Noosa Riverside Precinct Plan 3 mons
72 Pilot Asset Management Plans 60 days
73 Sand Pumping AMP (short) 3 mons Bryan O'Connor,External Provider,Stephen James,Ashley Saward
74 Noosa Aquatic Centre AMP (short) 3 mons Bryan O'Connor,David Shing,External Provider
75 Asset Class AMPs 80 days
76 Stormwater AMP 3 mons Bryan O'Connor,External Provider
77 Roads AMP 2 mons Bryan O'Connor,External Provider
78 Bridges AMP 2 mons Bryan O'Connor,Allan Hull,Dave Pierce,External Provider
79 Community Buildings AMP 3 mons Bryan O'Connor,Alison Hamblyn,External Provider
80 Support 480 days
81 Asset Management Competency Framework and Plan
82 Determine minimum competencies for AMS roles (medium) ‐ Note: 1 mon AMT,Bryan O'Connor,Will Burgess-Dean
can adopt IAM Competency Framework as a starting point
83 Map competencies of staff assigned to AMS roles (medium) 1 mon Bryan O'Connor,Will Burgess-Dean
84 Undertake competency Gap Analysis (medium) 1 mon Bryan O'Connor,Will Burgess-Dean
85 Develop Competence Development Plan (medium) 3 mons AMT,Bryan O'Connor,Will Burgess-Dean
86 Awareness 280 days
87 AM Induction Pack (medium) 2 mons Bryan O'Connor
88 Staff AM Training Materials 3 mons Bryan O'Connor
89 Develop Asset Information Strategy 180 days
90 Review Current Status (short) 120 days
91 Review Asset Hierarchy (short) 2 mons AMN,Bryan O'Connor,Craig Smit,GIS,Wayne Jensen
92 Map AMS workflows (short/medium) 3 mons Craig Smit,Bryan O'Connor,Wayne Jensen,Allan Hull
93 Determine data requirements for workflow steps (short/medium) 3 mons Bryan O'Connor,Craig Smit
94 Develop / revise Data Standards, as necessary (short) 2 mons AMN,Bryan O'Connor,Wayne Jensen
95 Develop Asset Information Improvement Program (short) 3 mons AMN,Bryan O'Connor,Wayne Jensen
96 Document Control (short/medium) 46 days
97 Determine AMS document control requirements (short / medium) 1 mon Deb Iezzi,Michael Shave,Nick Wellwood,NSC Leadership Team
98 Refine existing Corporate document control system, as necessary 1 mon Michael Shave,Deb Iezzi,Nick Wellwood,NSC Management Team
(medium)
99 Operation 750 days
100 Document the AMP to Budget Process (medium) 2 mons Bryan O'Connor,Wayne Jensen,Martin Drydale,AMT
101 Management of Change 100 days
102 Identify and document possible changes and their influence, by 3 mons AMN,Bryan O'Connor,Nick Wellwood,Paul Bright
asset class (medium)
103 Develop and document measures to mitigate the risks related to the 2 mons AMN,Bryan O'Connor,Nick Wellwood,Paul Bright
changes (medium)
104 Control of Outsourced Activities 40 days
105 Develop Strategic Sourcing Strategy (medium) 2 mons NSC Management Team,Paul Bright,Phill Parkman
106 Performance Evaluation 80 days
107 Quality Management Plan 80 days
108 Investigate integration of AMS in current QMP ‐ Internal Audit 2 mons AMN,Bryan O'Connor,Paul Bright,Phill Parkman
(medium)
109 Develop a Quality Management Plan for Council's AMS (medium) 2 mons Bryan O'Connor,NSC Leadership Team,Paul Bright,Phill Parkman
110 Improvement 562 days?
111 Root Cause Analysis 562 days
112 Capture and document routine Failures: WMS (short/medium) ‐ 24 mons AMN,Bryan O'Connor,Craig Smit
Considered in mobility program
113 Include routine failure review process in maintenance work 6 mons AMN,Bryan O'Connor
management system (medium)
114 Refine capital project post‐delivery reviews to capture AMS 6 mons Bryan O'Connor,Allan Hull,Martin Drydale
requirements ‐ includes triggers for revision of Standards (medium)
115 Develop Improvement Process for the AMS (medium) 6 mons AMN,Deb Iezzi,NSC Leadership Team
116
Project: Noosa Draft RoadMap Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Wed 24/08/16 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.