Stormwater Management Plan
Original PDF page 21, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn65-67 Elanda Street, Sunshine Beach
Site Based Stormwater Management Plan
_____________________________________________________________________________________________
• Contractor’s Construction Management Plan to include day to day management
requirements.
4.2.4 Post Construction
Following construction any disturbed areas will be stabilised through revegetation which is
to be maintained until established.
4.2.5 Operational Phase
Building applications for future dwellings on the allotments shall address their impacts on
stormwater quality on an individual basis.
File Name: WCD-22936 – 65-67 Elanda_SWMP.docx
Revision: C 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.