Matrix Projects (QLD)- Essence of Peregian, David Low Way Peregian Beach QLD 4573       Page 1 l



5       Conclusions


5.1     Condition No 16
        Given the extensive nature of the bulk earthworks across the majority of the
        site, the overall age/poor health and structure of the Melaleucas on the site,
        retention of any trees outside of the building footprints isn't possible for a
        long-term health and structural arboricultural perspective.

5.2     Condition No 17
        The requirement to install sheet piling outside of the building located in the
        south-eastern corner of the site will impact heavily on Trees No 1, 2, 3 and 4.
        Tree No 1 has a poor retention value due to the basal structural defect and poor
        useful life expectancy, where as Trees No 2, 3 and 4 will be severely impacted
        by the sheet piling. Combined with their overall small stature, therefore
        lacking significance when compared to larger trees, removal and replacement
        of all 4 trees is the best option and will increase the future treescape of the
        nature strip and site.

        Tree No 5 is neither in good health or structure, therefore removal and
        replacement with a superior specimen at the landscape phase is the best option.

        Tree No 6 has a short useful life expectancy due to the loss of a major first
        order branch, including a major future structural issue, therefore the retention
        v a lue i s lo w and removal is r ccommc ndcd.



        Trees No 7, 8 and 9 are also poor specimens for retention. This is due to their
        advanced age and prevalence of the decay fungus Phellinus throughout their
        branch structure. The client requests and prefers the retention of these trees,
        and given the driveway footprint, retention maybe possible under supervision
        of a qualified sit arborist and as per AS4970-2009.

5.3     Condition No 49
        Assessment of the KHMP by James Warren and Associates found no trees
        specified for retention due to Koala activities, therefore the requirements of
        this condition aren't applicable.

5.4     Tree Protection (Western Reserve)
        Although not addressed under the conditions of DA consent, the trees and
        vegetation located on the western side of the gabion wall are retainable (no
        obvious impacts or future targets in their vicinity). Protection of the
        vegetation and trees maybe done by installation of appropriate fencing and
        signage with the assumed erosion control measures placed on the western side
        of the gabion wall during construction.




Leaf and Limb Horticultural ConsultancyC
Prepared by Samuel Cowie                                                     I 1 `h of June 2009

Used in these records

About this file

File size
49.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application Part 2 - Environmental & Stormwater Management Plans.pdf · 49.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.