Council archive · source document
Development Application Part 2 - Environmental & Stormwater Management Plans · OPW11/0335
Plans and drawings: the text below has words only, no drawings.
Very large file (49.6 MB): may take a few minutes to open.
Matrix Projects (QLD)- Essence of Peregian, David Low Way Peregian Beach QLD 4573 Page 13
Tree Mana;vement and Protection Plan
Site address: Essence of Peregian, David Low Way
Peregian Beach QLD
Unit Development and Construction
OPW
Contractor:
- Business:
- Mobile:
Site Arborist:
- Business:
- Mobile:
Tree contractor:
- Business:
- Mobile:
The following tree protection procedures are to be undertaken during the development
of the site to insure the safe, healthy, and long-term retention of retained trees
(numbered 7, 8 and 9 in the arborist report by Leaf & Limb Horticultural
Consultancy) identified in the operational works approved by Sunshine Coast
Regional Council. This document is to read in conjunction with the Arborist Report
prepared by Leaf & Limb Horticultural Consultancy for the site.
A laminated copy of these tree protection procedures is to be attached to any tree
protection fencing on the site, and a copy is to be retained on site by the building
contractor supervising the project.
The area within the Tree Protection Zone of any protected tree will be mulched to a
depth of 75mm with composted wood and leaf mulch (created by tree chipper), which
contains no soil fines. The TPZ is to be irrigated once per week or have five 200-litre
drip drums installed (filled twice a week).
Pre Construction
• Prior to construction works, a site arborist shall be contracted to supervise all
tree protection procedures detailed in this document. The site arborist is
required to have a minimum level 5 AQS qualification in Arboriculture, and a
minimum 5 years experience in tree protection on construction sites. Their
details are to he tilled in on all tree protection fencing signage.
• Prior to construction works, a tree contractor shall be contracted to conduct all
pruning operations detailed in this document or instructed to by the site
arborist. The tree contractor cannot be the site arborist due to perceived
conflict of interest. The tree contractor must have a minimum level 3 AQS
qualification in Arboriculture, and be able to follow AS4373-2007. Their
details are to be filled in at the top of the document.
Leaf and Limb I lorticultural Consultancycci
Prepared by Samuel Cowie I I'h of June 2009
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.