Development Application Part 2 - Environmental & Stormwater Management Plans · OPW11/0335
Plans and drawings: the text below has words only, no drawings.
Very large file (49.6 MB): may take a few minutes to open.
Commercial Section
1) Direction of flow from the Commercial area (hotel, restaurant roof, tank) into Wetland
C2
2) Direction of flow from the South balance (overland flow) and Commercial area
(restaurant podium) into Bio-retention Cl,
3) Direction of flow from Bio-retention C1 into Wetland C2.
Stormwater that has passed through all these treatment units enters the receiving node
(Appendix B). The design stormwater quality passing through the treatment units, as
well as into the receiving node, were modelled using MUSIC Version 4.
5.3. MODELLING OF THE STORMWATER TREATMENT TRAIN
Results of MUSIC modelling showed that there will be a decrease in stormwater runoff
from the Stage 1 development area. Loads of sediment, total nitrogen and total
phosphorus will be substantially removed from stormwater before entering the Noosa
National Park from the Stage 1 development area (Appendix B).
There will be an 84% reduction in stormwater entering Noosa National Park, from 6
MUyear to 0.9 MUyear. The annual load of total suspended solids from the
undeveloped commercial area is about 1000 kg/year, whereas the annual load from the
developed site is 140 kg/year (Appendix B). Likewise, annual loads for total nitrogen
and total phosphorus are also expected to be an order of magnitude lower than the
present load from the existing caravan park site (Appendix B).
Water Quality predictions from the MUSIC model (Appendix B) indicate that
contributions of total suspended solids, nitrogen and phosphorus in treated stormwater
from the developed site (Table 3) comply with the required water quality objectives
(Table 1 and Table 2). The median design concentrations are expected to be below the
required water quality objectives, and 90% of the time this should be the case (refer to
receiving node results listed in Appendix B).
The predicted maximum concentrations of suspended solids, nitrogen and phosphorus
in extreme stormwater flows might temporarily exceed the guidelines (Appendix B), but
the design concentrations (Table 3) will be improved from the existing water quality in
the terminal wetland measured after a stormwater flow event (refer to Table 3 in
Simmonds and Bristow, 201OErrorl Reference source not found.). The MUSIC
modelling indicated that the treatment train for the Essence of Peregian development will
improve the water quality of stormwater entering the terminal wetland.
©2011 Simmonds & Bristow Pty Ltd Pacific Plumbing - Scanlon Property Group Ply Ltd J-1109-155 - 8 September 2011
IICLIENTFILES1Contrast Constmcuons11109. 15Sc . Essence of Peregian SCEP Stage 1 Up1ateto9_outpul DocumentsU-11o9.1SScSMP_Scanlon Property
Group_SECP_ge_ta_110905 aoc Page 7 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.