132005.638.04 - Other Change To An Existing Approval For Material Change Of Use - Expansion Of Special Purpose (Waste Disposal And Recycling Facility) & Ongoing Clearing Purposes At 561 Eumundi Noosa Road Doonan · Attachment 1 - 132005.638.04 - Proposed Conditions

of 7

Page text shows just the words. Original shows the document exactly as it was published.

PLANNING & ENVIRONMENT COMMITTEE MEETING REPORT                               9 DECEMBER 2025



        GC 147 MPAC 19        0     Transfer View prepared by Flexure Pty Ltd     14/02/2025

        GC 147 MPAC 21        0     Recycle prepared by Flexure Pty Ltd           14/02/2025

        GC 147 MPAC 22        0     Recycle/Reviva prepared by Flexure Pty Ltd 14/02/2025

      Building Height
47.   The maximum height of the development must not exceed 9 metres above the ground level.
      Including where excavation is undertaken the exposed portion of the external façade of the
      building.
      Building Appearance
48.   External design features, materials and finishes must be as shown on the Approved Plans,
      with no inclusions or alterations made without approval in writing by Council.
      Water & Sewer Connections
49.   The development must be provided with a potable water supply having a capacity sufficient
      for the use.
50.   An underground connection to reticulated sewerage must be provided to the premises in
      accordance with the standards and requirements of Northern SEQ Distributor–Retailer
      Authority (Unitywater).
51.   A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
      must be submitted to Council that certifies an underground connection to reticulated water
      and sewerage has been provided to the premises.
ECOLOGY AND ENVIRONMENT
52.   A detailed offset delivery plan (ODP) must be developed generally in accordance with the
      Environmental Offsets Act 2014, and Revised Determination and Location of Offset
      Requirements – Site A on Lot 77 SP298776, dated 6th February 2025, prepared by Native
      Foresters.
53.   Certification must be submitted to Council from a qualified person* which certifies that the
      subject works have been undertaken in accordance with the Offset Delivery Plan prior to the
      commencement of the use of the additional area.
      *(Refer to Advisory Note)
54.   All recommendations outlined in Section 7.0 of the Flora and Fauna Assessment must be
      fully implemented before the commencement of the new facilities. Certification prepared by
      a suitably qualified person, must be provided to confirm that all works have been completed
      in accordance with the Flora and Fauna Assessment.
55.   Rehabilitation and weed management of the 30-metre-wide vegetation buffer area west of
      the Cleanaway Depot must be undertaken generally in accordance with the
      recommendations of the Revised Determination and Location of Offset Requirements – Site
      A on Lot 77 SP298776 Letter.
56.   Certification must be submitted to Council from a qualified person* which certifies that the
      rehabilitation and weed management works have been undertaken in accordance with the
      Revised Determination and Location of Offset Requirements – Site A on Lot 77 SP298776
      Letter.
      *(Refer to Advisory Note)
Log in to download the original file

ATTACHMENT 1 - 132005.638.04 - PROPOSED CONDITIONS.pdf · 111 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.