SUPERSEDED Decision Notice - Minor Change - MCU22 0172 01, OPW22 0234 01 & RAL22 0024 01 [As Published] · MCU22/0172.01
66. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
67. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
68. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
Certification
69. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
As Constructed Plans and ADAC XML Files (Council)
70. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
information shall include:
a. As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing
presentation, as-constructed survey capture and associated guidelines for preparation
of a compliant ADAC XML digital file are available on the webpage titled “As-
Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
Development / Development Tools & Guidelines / As-Constructed Guidelines.
c. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Licensed Surveyor in regard to the cadastral and locational information, levels
and applicable survey datum.
Page 10 of 16
Document Set ID: 22449772
Version: 3, Version Date: 05/06/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - Minor Change - MCU22 0172 01, OPW22 0234 01 & RAL22 0024 01 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 197 KB (small file)
- File type
No other editions are linked here.