2022-11-08 Services & Organisation Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SERVICES & ORGANISATION COMMITTEE MEETING REPORT 8 NOVEMBER 2022
4 CAPITAL PROGRAM DELIVERY STATUS – 30 SEPTEMBER 2022
Author Infrastructure Planning, Design and Delivery Manager – Craig Eldridge
Infrastructure Services Department
Index ECM/ Subject/ 2022-2023 Annual Capital Works Program
Attachments Nil.
EXECUTIVE SUMMARY
• This report provides a status update for the Capital Works Program as at 30 September
2022.
• The total proposed expenditure for capital works for the 22/23 financial year is ($57.1m),
inclusive of carry-forwards ($11m), expenditure in direct control of Infrastructure Delivery
($50.7m) and other such as community projects, ICT and fleet ($6.4m).
• As at 30 September 2022, Council has expended a total of 22% of the 22/23 financial year
budget with $20.9m in commitments.
• It is important to note that much of the first quarter of each financial year is taken up with
planning and preparing tenders based on the annual budget once confirmed.
• The ongoing reduced availability of labour, equipment and materials and a ‘hot’
construction industry is proving challenging however works are currently being managed
within overall budget limitations where feasible.
• The Road Reseal Program has expended $885,000 of the $5.7m budget for 22/23
financial year.
• Council has a current forecast of grant funding revenue of $17.6m while Council’s
contribution to projects with grant funding is at $17.4m and non-grant capital projects
amounts to $22.1m.
• The Design Services team are currently supporting the design of 14 projects with multiple
sub-projects with an estimated design value of $988,000 and estimated construction value
of $21m.
• The Planning team is currently supporting key master planning initiatives with multiple
sub-projects; estimated value $350,000 in 22/23 and an estimated future project
investment value of $15m+.
• There are currently 36 multi-year projects in various stages of completion.
RECOMMENDATION
That Council note the report by the Infrastructure Planning, Design & Delivery Manager to the
Services & Organisation Committee Meeting dated 8 November 2022 providing an update on
the delivery of the 22/23 Capital Program as at 30 September 2022.
REPORT
This report is to inform Council of the overall status of the Capital Works Program at the end of
September 2022.
Page 20 of 35
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.