SERVICES & ORGANISATION COMMITTEE MEETING REPORT 8 NOVEMBER 2022
The gravel resheeting program kicked off during the 4th quarter of the 21/22 financial year due
to optimum weather conditions and will continue throughout the 22/23 financial year. The road
reseal program has expended $885,000 of the $5.7m budget for the 22/23 financial year. Of the
total expenditure, the following roads were completed within the Road Reseal Program this
quarter:
o Tomkinsons Road – Cootharaba
o Pearl Steet - Cooroy
o Hospital Lane - Cooroy
o Overlander Avenue - Cooroy
o Blueberry Drive – Cudgerie
o Black Mountain Road – Black Mountain.
The Shire Wide Pathway Program continues into the 22/23 financial year, with the following
pathways completed in the first quarter:
o Butler Street & Crank Street Footpath and Ghostgum Court Missing Link - Tewantin
o Ernest Goodchap Street Path Linkage - Tewantin
o Bluebell Court Link – Noosaville.
Upcoming pathway projects include:
o Maple Street Pathway Overlander Avenue to Bruce Highway Overpass – Cooroy
o Stan Memorial Avenue Missing Pathway Link – Pomona
o Tewantin Road Missing Pathway Link – Cooroy.
The Bus Stop Disability Compliance Program will commence with the following stops
programmed:
o David Low Way (Woodland Drive) - Peregian Beach
o Gympie Terrace (Werin Street) - Tewantin
o Hilton Terrace (Noosa Convention Centre) - Tewantin
o Eumundi Noosa Road (Rene Street) - Noosaville
o Greenridge Pinbarren Road – Pinbarren.
Page 22 of 35
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.