6.0 MITIGATION MEASURES
6.1 GENERAL
The following measures have been implemented or are recommended to mitigate against the impacts to
the identified ecological resources within the site.
6.2 FLORA SPECIES AND VEGETATION COMMUNITIES
To mitigate against the impact of clearing a small number of individual trees, the vegetation within the
mapped Riparian Protection Area will have a rehabilitation program enacted to remove weed invasion
and improve the ecological resilience of the vegetation along the waterway corridor. The following
general recommendations are provided to reduce environmental impacts associated with the proposed
development and to achieve compliance with the Biodiversity, Waterways and Wetlands Overlay Code:
Protection of adjacent vegetation
The balance of vegetation within the site is to be retained and impacts avoided as a result of the proposed
clearing by the following:
All trees within the area to be cleared are to be felled into adjacent areas proposed to be cleared
or already cleared areas.
No vegetation is to be felled into adjacent areas where vegetation is to be retained.
Appropriate measures are to be taken to mitigate disturbance of adjacent areas of vegetation by
machinery (e.g. installation of temporary exclusion fencing).
Erosion and sediment control
Appropriate erosion and sediment control measures be employed during site clearing and
earthworks to mitigate site risk
Control measures to be maintained for the duration of construction works.
Property maintenance
Weeds are to be managed to prevent spread during construction works.
6.3 FAUNA SPECIES
The impact of the development to fauna is proposed to be mitigated/minimised by engagement of a
suitably qualified fauna spotter/catcher during vegetation clearing works and enacting a rehabilitation
program within the riparian vegetation to enhance habitat quality and complexity. Appropriate erosion
and sediment control measures will be implemented during construction and vegetation clearing stages
of the development to limit sedimentation impacts to adjoining waterways.
AUGUST 2026 ECOLOGICAL ASSESSMENT REPORT Page: 21
380 MCKINNON DRIVE, COOROIBAH
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix C - Ecological Assessment Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.0 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.