GENERAL COMMITTEE MEETING AGENDA 14 NOVEMBER 2022
Capital Program
Actual capital expenditure (excluding commitments) is $17.6 million (YTD budget $20.5 million).
Detailed discussion of progress in the delivery of the capital works program is provided through a
separate quarterly report by the Asset Planning Manager.
Figure 5: Capital Program Delivery Performance
$25.0
$19.6 YTD Budget ($m)
$20.0
$16.9 YTD Actual ($m)
$15.0
$10.0
$5.0
$0.4 $0.2
$0.5 $0.5
$0.0
Capital works Other capital Loan redemption
Cash Management and Investment Performance
Total cash on hand at the end of October was $111.8 million. Included in this balance are funds
held in trust and for restricted purposes (e.g. unexpended levy and grant funds), prepaid grants
including the financial assistance grant, QRA disaster funding and other capital works grants,
prepayment of Waste Levy subsidy (4 years), and unspent monies committed for funding capital
projects which are underway and will continue during the financial year.
The following pie charts present the mix of cash held at October 2022 by agency (graph on the
left) and by credit risk rating (graph on the right). All funds have been invested in accordance with
the Investment Policy and in consideration of the principles of ethical investment, preservation of
capital, return on investment and counterparty thresholds.
Figure 6: Closing Cash Held by Agency and Credit Rating
NAB
9%
CBA A1 +
30% (Commercial Banks)
39%
QTC A1 +
61% (QTC)
61%
Page 37 of 62
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.