Officer:	:Monkeith Kadhum
Direct Telephone:	 07 53296293
Our Reference:	:OPW16/0304
Your Reference:	:B080

13 December 2016

Robin Russell & Associates Pty Ltd
204/6 Barbara Street
STAFFORD QLD  4053

[email protected]

Dear Sir/Madam

Decision Notice
Sustainable Planning Act 2009
I refer to your application and advise that on 12 December 2016, Council decided to approve the application in full subject to conditions.
Details of the decision are as follows:
1.	APPLICATION DETAILS

Application No:	OPW16/0304
Street Address:	50 Gateway Dr NOOSAVILLE  QLD  4566
Real Property Description:	Lot 81 SP 216079
Planning Scheme:	The Noosa Plan (28 October 2016)

2.	DECISION DETAILS

The following type of approval has been issued:
Development Permit for Operational Work: Electrical Reticulation, Street Lighting (Gateway Rise - Stage 2)
3.	RELEVANT PERIOD OF APPROVAL

The relevant period for this development approval is 2 years starting the day that this development approval takes effect.

4.	ASSESSMENT MANAGER CONDITIONS

Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
B080-01B (Energex Project S0104663)	B	Electricity Reticulation - Gateway Rise Noosaville - Stage 2, prepared by Robin Russell and Associates Pty Ltd	15/05/2014
B080-02B (Energex Project S0104663)	B	Electrical Schedules - Gateway Rise Noosaville - Stage 2, prepared by Robin Russell and Associates Pty Ltd	15/05/2014

Prior to Commencement of Construction
Council must be advised of the appointment of a Principal Contractor in terms of the Work Health and Safety Act 2011.
Any construction works to be undertaken in the vicinity of Public or Council's existing (on-maintenance or off-maintenance) infrastructure must not adversely affect the integrity of the infrastructure.   Any damage to the external road pavement, pathway or any municipal infrastructure as a direct consequence of construction activities associated with this approval shall be remedied by the applicant at no cost to Council.  The work site and the areas may be affected by the works must be photographed prior to any works commencing on the site and be submitted to Council.
Electrical Reticulation
Electrical reticulation works cannot commence until they are fully approved by Energex and a copy of the Energex approval has been submitted to Council.
Electrical works must be coordinated with other civil works associated with Development Permit for Reconfiguring a Lot No: REC07/1626.2 (File: 152007.1626.2) and must not be in conflict with any existing or proposed infrastructures and services.
Any street lighting associated with this permit must be “Rate 2” light in accordance the requirements of Energex.
Electrical pillars should be located on alternative boundaries to water meters and where not achievable due to site constraints, electrical pillars should be located clear of the water meters in accordance with Unitywater and Energex guidelines.
General
All works must be constructed and work procedure undertaken in accordance with:
All the relevant codes and policies of The Noosa Plan, particularly Section: 3.24 of PSP 5 – Engineering Design Standards – Roads, Drainage and Earthworks.
Provision of the Work Health and Safety Act and such other legislation as is applicable to workplace health and safety.
The list of approved plans of this Decision Notice, the conditions of this Decision Notice and the relevant conditions of the higher order approval for Reconfiguring a Lot, permit No: REC07/1626.2 (File: 152007.1626.2)
All works associated with this permit approval must be carried out in a safe manner for the members of the public without adverse or undue impact on other properties or the users of the roads and pathways network, where required all traffic control signage must be in accordance with the Manual of Uniform Traffic Control Devices (MUTCD).
The applicant must ensure sediment from the work site does not leave the site or ends into the street stormwater drainage system, watercourses and/or wetlands due surface runoff or on tyres of vehicles and/or machineries.  It is essential to implement appropriate approved erosion and sediment control measures as may be necessary during all phases of works and that non essential exposure of soil is prevented by restricting the extent of clearing and minimising the duration of soil exposure to adverse weather conditions. Disturbed areas must be stabilised without delay and prior to rainfall occurring.
The supervising Consultant must ensure that the works have been inspected and confirm their acceptability and compliance at the completion of construction.
Supply Council with a full set of “As Constructed” drawings in the format described in Planning Scheme Policy No. 5 of The Noosa Plan.
5.	REFERRAL AGENCIES
Not Applicable.
6.	REFERENCED DOCUMENTS
Not Applicable.
7.	ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ.  The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Environmental Advisory Note
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations under the ACH Act.
8.	PROPERTY NOTES
Not Applicable.
9.	PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME
Not Applicable.
10.	FURTHER DEVELOPMENT PERMITS REQUIRED
Not Applicable.
11.	SELF ASSESSABLE CODES
Not Applicable.
12.	SUBMISSIONS
Not Applicable.
13.	REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not Applicable.
14.	RIGHTS OF APPEAL
You are entitled to appeal against this decision.  A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval.  If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued.  Only one “negotiated decision notice” may be given.  Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”.
15.	OTHER DETAILS
If you wish to obtain more information about Council’s decision, electronic copies are available on line at www.noosa.qld.gov.au, or at Council Offices.

Yours faithfully

Monkeith Kadhum
Development Engineer

Enc:	Approved Plans/Documents
Appeal Rights

cc	Unitywater

	Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009

The following is an extract from the Sustainable Planning Act 2009  (Chapter 7).
MATERIAL CHANGE OF USE, RECONFIGURING A LOT & OPERATIONAL WORKS

Division 8 	Appeals to court relating to development applications and approvals

461 	Appeals by applicants
(1) 	An applicant for a development application may appeal to the court against any of the following—
(a) 	the refusal, or the refusal in part, of the development application;
(b) 	any condition of a development approval, another matter stated in a development approval and the identification or inclusion of a code under section 242;
(c) 	the decision to give a preliminary approval when a development permit was applied for;
(d) 	the length of a period mentioned in section 341;
(e) 	a deemed refusal of the development application.
(2) 	An appeal under subsection (1)(a), (b), (c) or (d) must be started within 20 business days (the applicant’s appeal period) after—
(a) 	if a decision notice or negotiated decision notice is given—the day the decision notice or negotiated decision notice is given to the applicant; or
(b) 	otherwise—the day a decision notice was required to be given to the applicant.
(3) 	An appeal under subsection (1)(e) may be started at any time after the last day a decision on the matter should have been made.

462 	Appeals by submitters—general
(1) 	A submitter for a development application may appeal to the court only against—
(a) 	the part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	the part of the approval relating to the assessment manager’s decision under section 327.
(2) 	To the extent an appeal may be made under subsection (1), the appeal may be against 1 or more of the following—
(a) 	the giving of a development approval;
(b) 	any provision of the approval including—
(i) 	a condition of, or lack of condition for, the approval; or
(ii) 	the length of a period mentioned in section 341 for the approval.
(3) 	However, a submitter may not appeal if the submitter—
(a) 	withdraws the submission before the application is decided; or
(b) 	has given the assessment manager a notice under section 339(1)(b)(ii).
(4) 	The appeal must be started within 20 business days (the submitter’s appeal period) after the decision notice or negotiated decision notice is given to the submitter.

463 	Additional and extended appeal rights for submitters for particular development applications
(1) 	This section applies to a development application to which chapter 9, part 7 applies.
(2) 	A submitter of a properly made submission for the application may appeal to the court about a referral agency’s response made by a prescribed concurrence agency for the application.
(3) 	However, the submitter may only appeal against a referral agency’s response to the extent it relates to—
(a) 	if the prescribed concurrence agency is the chief executive (environment)—development for an aquacultural ERA; or
(b) 	if the prescribed concurrence agency is the chief executive (fisheries)—development that is—
(i) 	a material change of use of premises for aquaculture; or
(ii) 	operational work that is the removal, damage or destruction of a marine plant.
(4) 	Despite section 462(1), the submitter may appeal against the following matters for the application even if the matters relate to code assessment—
(a) 	a decision about a matter mentioned in section 462(2) if it is a decision of the chief executive (fisheries);
(b) 	a referral agency’s response mentioned in subsection (2).

464 	Appeals by advice agency submitters
(1) 	Subsection (2) applies if an advice agency, in its response for an application, told the assessment manager to treat the response as a properly made submission.
(2) 	The advice agency may, within the limits of its jurisdiction, appeal to the court about—
(a) 	any part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	any part of the approval relating to the assessment manager’s decision under section 327.
(3) 	The appeal must be started within 20 business days after the day the decision notice or negotiated decision notice is given to the advice agency as a submitter.
(4) 	However, if the advice agency has given the assessment manager a notice under section 339(1)(b)(ii), the advice agency may not appeal the decision.

465 	Appeals about decisions relating to extensions for approvals
(1) 	For a development approval given for a development application, a person to whom a notice is given under section 389, other than a notice for a decision under section 386(2), may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.
(3) 	Also, a person who has made a request under section 383 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

466 	Appeals about decisions relating to permissible changes
(1) 	For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval—
(a) 	if the responsible entity for making the change is the assessment manager for the application—
(i) 	the person who made the request; or
(ii) 	an entity that gave a notice under section 373 or a pre-request response notice about the request;
(b) 	if the responsible entity for making the change is a concurrence agency for the application—the person who made the request.
(2) 	The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376.
(3) 	Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

467 	Appeals about changing or cancelling conditions imposed by assessment manager or concurrence agency
(1) 	A person to whom a notice under section 378(9)(b) giving a decision to change or cancel a condition of a development approval has been given may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.

[word/footer1.xml]
Page 4 of 6

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 6

[word/header1.xml]
OPW16/0304

[Attachment: image4.png (image text)]
 
 
 

 
 
 

a
mm

  

NOOSA
COUNCIL

Used in these records

About this file

File size
101 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice OPW16_0304.docx · 101 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.