1.14 Erosion and Sediment Control
j Erosion and sediment control is considered for both work areas as summarized below:
o The driveway works to Park Road will require silt fences to be installed to the perimeter of the
i works, Sand bags will be placed in the gutters during excavation and concreting to prevent
runoff into the council storm water system
o €rosion and sediment control for the proposed garage will require a silt fence to the perimeter
i of the proposed excavation.
o Erosion and sediment control to the proposed master suite will also require a silt fence to the
i perimeter of the site (this will also double as the control fence for the excavator)
o The permanent storm water drainage system will be connected to the council system as an early
works operation. This will be done to prevent any concentrations of runoff discharging onto the
i sand slope.
o Allservices trenches (water, electricity, telephone, sewer, storm water) will be dug by hand
i o All measures will be in place prior to commencement of construction
1.15 Conclusion
i In conclusion, we believe that if these procedures are adopted. The building can be safely constructed
with minimal impact en surrounding property.
Sign BMCESee the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001A7F25.001.pdfRelated documentPublic source context ↗
09/0578 - Operational Works - Landscaping, Carparking, Access, Frontage Works, Stormwater Drainage, Site Civil Works, Sewer & Water Reticulation [As Published]Related documentApplication case desk ↗
About this file
- File size
- 6.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.