geotech and slope stability · MCU22/0145
PROPOSED UNIT DEVELOPMENT
3 HENDERSON STREET, SUNSHINE BEACH
Executive Summary
This report details the results of a geotechnical investigation undertaken for a proposed unit development at
3 Henderson Street, Sunshine Beach. The investigation was performed by Tectonic at the request of
HR Design Group. The investigation comprised drilling of boreholes at two locations across accessible
areas of the development footprint, together with in-situ soil strength testing. This report summarises the
results of the investigation and provides geotechnical recommendations regarding slope stability, earthworks
and footings, together with advice for temporary and permanent basement retention.
Provided drawings indicates that the development will comprise a four-storey unit building, over a single level
basement carpark. Excavation is anticipated to be up to 4 m in depth, with filling likely to be less than 0.5 m
high for landscaping. Temporary retention will be required as the basement excavation will extend close to
some of the site boundaries.
The subsurface conditions encountered in the boreholes are summarised as follows:
Asphalt (borehole BH1 only) – about 20 mm thick; then or from the ground surface
Fill – comprising very loose to loose gravelly/silty sand to depths between 0.3 m and 0.7 m below
ground level (BGL); overlying
Aeolian Sands – comprising mostly poorly graded sands that were loose to depths of between
1.1 m and 2.8 m BGL; then becoming medium dense and increasing to dense below depths of
about 4 m BGL.
No signs of groundwater seepage (‘springs’) were observed during our walk-over. Groundwater was not
encountered in the boreholes at the time of investigation.
Provided the recommendations within this report are adhered to, and subject to detailed design and
construction of the footing and retention systems by a suitably qualified and experienced structural RPEQ,
there would be a Low Risk to property from slope instability.
Excavations through the soils encountered in the boreholes should be achievable using conventional
earthmoving plant (e.g. small or larger excavators with toothed buckets). Temporary, unsurcharged cuts
could be formed at 1V:2H in the very loose to loose sands, and at 1V:1.5H in medium dense (or denser)
sands, for batters up to 3 m in height, provided groundwater seepage is not encountered and sands do not
slough from the batter face as they dry out. It is expected that space restrictions will limit battering of
temporary cuts on the site and so some form of temporary retention system, such as sheet piles, may be
required. Deeper unretained cuts, if required, should be specifically assessed by Tectonic.
Footings for the proposed development and any ancillary structures (e.g. retaining walls) must penetrate
through any fill materials and unsuitable natural soils (i.e. very loose to loose sands) to found at least 0.5 m
into medium dense (or denser) natural sands. Such materials were encountered in the boreholes below
depths of about 1 m to 2.8 m BGL (existing ground levels). High-level footings would be acceptable in
excavation areas where medium dense (or denser) natural sands are exposed at the subgrade level. Piled
footings would be required unless excavations expose such materials at or near foundation subgrade level.
Given the sandy soil profile, where deepened footings are required, steel screw piles are considered to be an
appropriate pile type. Due to the presence of loose sands, together with the close proximity of adjacent
buildings, open bored piers or driven piles are not considered to be suitable for this site.
29 June 2022
Report No. 22227-001-Rev0 ii
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
geotech and slope stability.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.