JONES FLINT & PIKE PTY. LTD. ABN 79050414045
JONES FLINT & PIKE
development consultants, ,
planners, surveyors, landscape architects
MAROOCHYDORE
13th January, 2009
BRISBANE
M2248 - 09 UF&P House
17 | Cnr Emest and Merivale Streets, South Brisbane,
= / phone (07)3844 7161 fax (07)3846 1959
~ RO.Box 3634, South Brisbane, Queensland 4101
e-mail [email protected]
The Manager of Land Use
isunshine Coast Regional Counc SUNSHINE COAST a .
Tewantin Office phone (07) $443 2500 fax (07) $443 4759
PO Box 141 PO.Box 6, Maroochydore, Queensland 4558
e-mail [email protected]
TEWANTIN QLD 4565
SUNSHINE COAST
GLADSTONE
59 Goondoon Street,
phone (07)4972 2100 fax (07/4972 Saad
. PO.Box 172, Gladstone, Queensland 4680
Mr Denis Wallace e-mail [email protected]
Development Permit for Operational Works —
Prescribed Tidal Works — Refurbishment of a
Jetty located at 172 Gympie Terrace, Noosaville
and described as Lot 164 on CP907410.
www.|fp.com.au
Your Reference: 2007/1173
Dear Sir,
We refer to Council's correspondence and Decision Notice Approval (Council Reference:
2007/1173) dated 1° December, 2008 that was received in our office on 3 December, 2008, and
our notification to Council of the suspension of the appeal period dated 18" December, 2008.
On behalf of Heritage Jetties Pty Ltd and in accordance with s.3.5.17 of the Integrated Planning
Act 1997 (IPA), we hereby seek the Council's consideration in regard to amending the following
conditions attached to the aforementioned Decision Notice Approval.
At the outset it should be noted that the applicant believes that some of the conditions contained
in the Decision Notice are not only unreasonable but also have no nexus with the code against
which the application is required to be assessed. This view has been supported by expert legal
advice. This submission is based on the expert legal advice that has been provided to the
applicant.
We believe that in order to provide an understanding of our rationale in regard to the specific
conditions of approval that will be addressed it is important to preface this submission with some
general comments about our understanding of the assessment managers powers to impose
| conditions in regard to this application.
Section 3.5.30 of the Integrated Planning Act 1997 (IPA) provides as follows:
“3.5.30. Conditions must be relevant or reasonable
1) Acondition must -—
a) Be relevant to, but not an unreasonable imposition on, the development or
use of premises as a consequence of fhe development; or
b) Be reasonably required in respect of the development or use of premises
as a consequence of the development.
2) Subsection (1) applies despite the laws that are administered by, and the policies
that are reasonable identifiable as policies applied by, an assessment manager or
concurrence agency.”
J.C. Franklin, GDURP MRAP| MDIA
\A.Thomson, BApp Sc(Sury} ADIp(Sury) MSSI
MT. Fitzgerald, 8Surv MSSI
BW. Butter, BApp Sc(Surv) MSSI
MEMBER OF AUSTRALIAN SPATIAL INFORMATION BUSINESS ASSOCIATION - QUALITY ASSURED SUPPLIER - MEMBER OF URBAN DEVELOPMENT INSTITUTE OF AUSTRALIA
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 3 pages
Page 2
M2248 - 09 Page 2 13/01/2009 The effect of sub-section 3.5.30 (2) is that the tests for lawfulness of conditions contained in section 3.5.30 (1) cannot be overridden by the terms of the laws or policies which the assessment manager or concurrence agency administers. The relevant development application is for operational work which is in the nature of building work. It is a particular species of development application confined to land below the high water mark being “prescribed tidal work”. As explained in the development application, the work involves refurbishment of an existing jetty so that it may operate more effectively from a maritime operation and safety perspective. The relevant code against which the operational work application is to be assessed is the Prescribed Tidal Work Code (the Code). The Code provides assessment criteria and the matters it deals with are amenity and aesthetics, public access, restriction of non-maritime use of tidal water, the provision of infrastructure, allocation of water areas and design and safety requirements. The intention behind the Code is to provide consistency in local government assessment of prescribed tidal work across Queensland. The assessment manager’s duty is to assess and decide the development application having regard to the factual circumstances of the application against the requirements of the Code. The assessment manager must approve the development application “if the assessment manager is satisfied the application complies with all applicable codes whether or not conditions are required for the development to comply with the codes.” (IPA section 3.5.13(2)) No conflict with the Code has been identified. In our view conditions may only be imposed to ensure that the development complies with the Code. In other words, there must be a nexus between the Code and the condition. It is our understanding that this is not a development application where the assessment manager is being asked to impose conditions which overcome conflict with the Code. Conditions may extend to both the operational work and any use of the jetty structure as a consequence of the operational work. However this does not entitle the assessment manager to treat the application as if it were a material change of use application and to condition an approval on that basis by having regard to matters extraneous to the Code. It is on the basis stated above that the following request to amend the conditions of approval is submitted. For clarity, the condition is shown in italic text and our comments and suggested amendments are shown in upright text. Condition 3 The jetty shall be licensed with the Council upon completion of the structural work and be licensed annually thereafter, The license may limit the number of vessels and their capacity in accordance with this approval. In our opinion this is not a valid condition. The licensing of the jetty may be required independently under a local law. An obligation to obtain/renew such a license cannot be imposed as a condition of an operational works application. The relevant local law will apply according to its terms independently of the operational works permit. There would be on objection to this requirement being relocated to the advisory notes section of the Decision Notice, but it should not remain as a condition of the development permit.
Page 3
M2248 - 09 Page 3 43/01/2009 Condition 4 Vessels moored or operating from the structure shall not exceed for (4) vessels with a combined capacity of 129 passengers. The development application is for operational work. There is no material change of use involved. The application must be assessed as an operational works application against the relevant Code. The Council as assessment manager may impose conditions which are reasonably required by the developments, or which are relevant to but not an unreasonable imposition on the development. In this case the “development” is the operational work, and there is no material change of use. The jetty structure is already used for the purpose of a commercial jetty. That use exists and is not a consequence of the refurbishment. It is accepted that the prescribed tidal work code refers in specific outcome 11.1 to parking facilities. The acceptable solution states “the infrastructure for prescribed tidal work is consistent with each relevant planning schemes standard.” The planning scheme standard requires car spaces according to the floor area of the commercial premises, and the number of parking spaces provided complies, based on the floor area of the building on the jetty. Condition 4 purports to restrict or contro! the use which, in our view, is inappropriate in response to a development application for operational work, the use being pre-existing. The relevant Code concerns amenity and aesthetics, public access, restriction of non-maritime uses, provision of infrastructure, allocation of water areas and design and safety matters. The Code is not concerned with the size or passenger capacity of the vessels moored or operating from the structure. The subject development application complies with the provisions of the Planning Scheme regarding car parking in relation to the floor area of the commercial premises which is the acceptable solution made relevant under the Code. In the circumstances it is difficult to understand how a condition of the nature of condition 4, which purports to limit the number of vessels and passenger capacity operating from the jetty would be lawful in response to the operational works application, particularly as such a condition is not required for the purposes of meeting the Code. It is requested that the condition be deleted as it is an unreasonable imposition on the development. Condition 5 A shuttle bus shall operate in association with each business that operates from the site in order to bring passengers to and from the site. The shuttle buses shall be parked within the lease area when not in use and not otherwise parked in Gympie Terrace or its associated parking areas. For the same reasons ‘given in respect of Condition 4, a requirement that the relevant businesses which will operate the vessels moored at the jetty each have a shuttle bus is not a reasonable or relevant condition. The condition is not a condition which has any nexus with the Code. It is requested that the condition be deleted as it is an unreasonable imposition on the development. Condition 7 Boat repair activities shall not be conducted from the structure. This condition relates to the use of the jetty structure following refurbishment. St effectively prohibits any boat repair activities. While the jetty is not a slipway, it is normal practice along the river and in other similar localities for vessels to undergo routine maintenance and minor repairs, which do not require the vessel to be slipped, while the vessel is stationary at its usual mooring. The condition places an unreasonable restriction on the operation of the vessel which is unrelated to the requirements of the Code against which the development application for operational work
Page 4
M2248 - 09 Page 4 13/01/2009 has been assessed. It is requested that the condition be deleted as it is an unreasonable imposition on the development. Condition 8 The rails to the abandoned slipway structure shall be removed prior to completion of the works. The operation of the old slipway which exists within the leased area is not part of the current development application for operational work. We cannot see any basis upon which the Council can impose a condition requiring its removal. Such a condition is irrelevant to the subject matter of the operational works application and has no nexus with the Code under which the application is assessed. The issue the Council seems to be raising is that the use of the slipway has been abandoned which even if it were true, there is no power for the Council to require the slipway structure to be removed through a condition on the subject development application for operational work. It is requested that the condition be deleted as it is an unreasonable imposition on the development. Condition 9 Wastewater and sullage shall only be disposed of at approved pump-out facilities. This condition requires waste water and sullage from the relevant vessels operating from the jetty to be disposed of at approved pump-out facilities. It needs to be borne in mind that the development application is for operational work. It does not relate to the day to day operation of the charter boat businesses which will utilise the jetty facilities. Ordinarily those businesses would engage private contractors to take waste water and sullage from the vessels. Private waste removal contractors are separately licensed under different laws with which they are required to comply. Neither the operators of the charter boats nor the applicant for the operational works approval has any means of controlling the activities of private waste contractors. If such private waste contractors were to breach the law by wrongfully disposing of waste water and sullage extracted from vessels at the subject jetty, of from other vessels, then presumably that contractor would be the subject of legal action either by the Council or the Environmental Protection Agency under the applicable laws. However, that is not a matter which is appropriate for conditioning in response to this operational works application. It is requested that the condition be deleted as it is an unreasonable imposition on the development. If you require any further information please contact the writer. 4 a f t Yours faithfully, JONES FLINT & PIKE Cc: Heritage Jetties Pty Ltd
Used in these records
Representations Received [As Published]Related documentApplication case desk ↗
About this file
- File size
- 276 KB (small file)
- File type
No other editions are linked here.