Figure 2.2 - Site Contours (Noosa Council Intramaps, 2022)
2.3. Proposed Development Drainage Pattern
2.3.1 Stormwater Concept
The internal stormwater drainage network will be provided to ensure collection of surface run-off as well as allowing
for capture of upstream run-off at the boundary and discharge from subsoil drainage of retaining walls.
Roof run-off from the new building will be drained via downpipes into a stormwater attenuation tank. The tank is
sized to reduce the overall developed site flows to pre-development levels, ensuring discharge from the site
minimises any impact to the downstream environment.
The internal drainage and attenuated roof outflows will be conveyed and discharged via kerb adaptors replacing
the existing within Safari Street, being the lawful point of discharge from the development consistent with the existing
drainage characteristics.
The roof and allotment drainage system for the proposed site shall be designed to comply with:
1. Noosa Shire Council Planning Scheme Policy (PSP) - Engineering Design Standards – Roads, drainage and
earthworks;
2. The Queensland Urban Drainage Manual (QUDM); and
3. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage.
Refer to Appendix A Proposed Development Concept Plan for the proposed stormwater drainage layout plan
illustrating the concept described above.
Project number 20220130
File RECOR Preliminary Stormwater Management Report - 20220130.docx, 2022-05-19 Page 6 of 16
Revision 1
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.