NOOSA CITY PLAN - WATER QUALITY AND DRAINAGE CODE Job Ref No.: 22159
Performance Outcomes and Acceptable Solution
Table 9.4.8.3 – CRITERIA FOR ASSESSMENT
PO13 AO13.1 PO The stormwater discharge from the site will remain
Development is designed and The location and form of stormwater generally as per existing conditions.
constructed to maintain surface and discharge points do not alter the pre-
ground water balances that sustain the development hydrology of receiving surface
environmental values of water water or groundwater.
dependent ecosystems, including
downstream aquatic, riparian, wetland AO13.2
and terrestrial ecosystems. Developments located on groundwater
recharge or discharge areas are designed
and managed in accordance with a
groundwater recharge and discharge
management plan prepared by a suitably
experienced and qualified groundwater
hydrologist. The groundwater recharge or
discharge must demonstrate that the
development does not affect groundwater
balances beyond the property boundaries.
Editor's Note—PSP6 Engineering Design
Standards Roads, drainage and earthworks
provides guidance on prepare a
groundwater recharge and discharge plan.
Construction and establishment of A comprehensive erosion and sediment control plan
stormwater management systems AO14.1 PO will be developed at the detailed design phase of the
An erosion and sediment control plan project, and meet councils requirements.
PO14 prepared in accordance with the
Construction methods provide for International Erosion Control Association
appropriate controls to avoid entry and Best Practice Books demonstrates that the
transport of litter, sediment, and capture and release of stormwater
associated prescribed water achieves the design objectives listed in
contaminants into receiving waters. Table A: Construction phase – stormwater
management design objectives of the State
1. Solution: PO = Performance Outcome
A/O = Acceptable Outcome
N/A = Not applicable to this proposal
Noosa Civic Village Mixed Use Development, Noosaville
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 5 - Servicability Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 21.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.