Assessment by Cardno) at very high speeds (80- 100km/h). Austroads suggests that the
combination of these high volumes and high speeds warrant segregated cycling facilities (not-on-
road facilities). In this regard, please indicate the exact route that will be taken for the segregated
facility highlighting any land resumptions that may be necessary and any infrastructure needed to
support this, such as underpasses/overpasses and any bridges.
Response:
Proposed shared facilities for Noosa on Weyba are shown within Attachment 3 A1 Concept Master Plan. This
indicative plan provides a preliminary cycleway design addressing Council’s concerns. Please note however that the
final concept would be subject to detailed design as part of further approvals required.
Issue
Multi-lane roundabouts provide a high risk to pedestrians and cyclists, which combined with high traffic
volumes and approach speeds could be extremely dangerous for residents of the proposed development.
Such arrangements would severely limit Active Transport objectives for the development.
Information Required
77 Demonstrate how pedestrians and cyclists will be able to safely cross all major roads and
intersections (including the underpass) impacted upon by the subject development, but primarily
the multi-lane roundabout on Walter Hay Drive. Details of levels, alignments of approach and
departure routes, etc. should be provided.
Response:
Please refer to Attachment 6 which includes the amended Urban Design Report. A specific plan within the report
addressing ‘Open Space, Road and Mobility (Pedestrian And Cycle)’ demonstrates desired pedestrian connections,
existing recreational trails, proposed cycleway extension and existing off road shared path (cycleway and pedestrian
path). Whilst detailed design of this infrastructure will be undertaken as part of further approvals, the preliminary
analysis has concluded that pedestrians and cyclists will be able to safely cross all major roads and intersections.
Issue
Flood immunity of pathway network
Information Required
78 Demonstrate that all pathways and segregated cycling facilities will achieve a minimum flood
immunity equivalent or greater than a 1 in 20 year Average Recurrence Interval. Should this
not be reasonably achievable in all areas please outline where and why this cannot be achieved
and provide information on the level of immunity that can be achieved.
Response:
Please refer to the amended Cardno Flood Report report included within Attachment 13 which confirms that all
pathways and segregated cycling facilities could achieve an acceptable level of flood immunity. Please note that
detailed design of this infrastructure would be logically undertaken as part of further approvals required.
We would anticipate in this instance that appropriate conditions could be imposed as part of any approval regarding
flood immunity for pathways and segregated cycling facilities.
Issue
Crime Prevention Through Environmental Design (CPTED)
Information Required
79 Demonstrate that CPTED issues will be addressed for all pathways and public spaces.
52
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Council Lake Weyba Information Response 28-10-13_FINALRelated documentApplication case desk ↗
About this file
- File size
- 1.6 MB (small file)
- File type
No other editions are linked here.