Response:

Further to discussions with Council it is not considered that there is a current requirement to duplicate Walter
Hay Drive. Cardno met with Council officers to obtain plans showing this duplication, but Council advised there
is no plan indicating this duplication at present. This road is not controlled by DTMR and therefore the design
team has concluded that there is no requirement for future duplication and subsequent dedications. As such it
is not considered reasonable or relevant to consider a duplication within the design as part of the current
Preliminary Approval.

HYDROLOGY & WATER QUALITY FLOODING

Issue
For PMF events trafficability has been assumed if the depth is less than 400mm with a DV product of
0.45m2/s. Insufficient justification has been provided to confirm that this depth and DV product is
acceptable for emergency vehicles to access the site.

Information Required

86      Provide confirmation from the Queensland Government Department of Community Safety that the
          proposed traffic ability criteria are acceptable for emergency vehicles.

Response:
During PMF events, access for emergency vehicles would be required. These vehicles are typically larger than
standard vehicles and so can handle greater flow depths across roads. Based on Project 10 of Australian Rainfall
and Runoff (AR&R): Appropriate Safety Criteria for Vehicles (2011), large 4WDs can cross roads with maximum
depths of 500mm, with a limiting dV product of 0.6 m2/s. Large passenger cars can cross roads with maximum
depths of 400mm, with a limiting dV product of 0.45 m2/s. For PMF events trafficability was therefore
conservatively assumed if the depth was less than 400mm with a dV product of 0.45 m2/s.

The Queensland Department of Community Safety was contacted regarding the traffic ability criteria used for
emergency vehicles. They advised that scenarios were assessed on a case by case basis and that a specific
guideline was not used. However, it should be noted that the AR&R project references the Emergency
Management Australia (EMA) manual for emergency vehicle 4WD operation that states that “if water reaches to
the bumper bar or higher, upon entering the water accelerate until a bow wave forms in front of the vehicle.
Maintain this bow wave at all costs, to keep water out of the engine.” In water depths of greater than 750mm, it
is suggested that either a snorkel extension to the engine air inlet and exhaust system is fitted or a canvas sheet
or tarp is placed across the grille to prevent water entering the engine bay.”

For similar developments in Brisbane a maximum depth of 500mm and dV product of 0.6 m2/s has been utilised
to determine PMF trafficability for emergency vehicles. This is based on the Brisbane City Council (BCC)
Subdivision and Development Guidelines (2008), Chapter 1 Part A which states that with flood depths less than
500mm and a dV product less than 0.6 m2/s, that evacuation of persons and possessions via trucks is possible
and that fit adults can wade through floodwaters.

Please refer to Section 7.2.1 of the amended Flood Study (see Attachment 13) for further detail regarding this
matter.

Issue
A sensitivity analysis has been undertaken to determine the impact of culvert blockage. In accordance with
QUDM; 20% blockage of the proposed culverts has been considered. 20% culvert blockage is considered
suitable in situations where there is a relief overland flowpath which will function prior to houses being
inundated. However, the proposed minimum road level of 4.00m AHD for the Northern Keyser Creek
Crossing means that proposed floor levels on upstream lots will be inundated prior to any relief overland
flowpath beginning to function.

Information Required
                                                      55

Used in these records

About this file

File size
1.6 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Council Lake Weyba Information Response 28-10-13_FINAL.pdf · 1.6 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.