Council archive · source document
Appendix 5. Geotechnical Engineering Report [As Published] · 132007.2399
October 2007 - 11 - 077682076(AB)
In particular the following measures apply to the liming process:
• Treatment should be carried out on prepared pads which may be the permanent
placement area. The earthworks strategy should be formulated to provide a number of
pads of appropriate size for practical spreading mixing and drying, so that adequate time
is available to complete the treatment and validation testing before placing the next layer.
• Treatment pads are to be contained by bunds with stormwater runoff directed to a
collection sump. Bunds to be constructed from low permeability materials that are not
ASS or have been fully lime treated.
• The treatment pad should be stripped of topsoil and proof rolled to achieve a uniform
density and reduced permeability, then a guard layer of neutralising agent should be
spread across the soil surface prior to placement of the first layer of fill. The rate of
neutralising agent applied should be based on 0.2 times the average total potential plus
existing acidity for every 1m depth of fill placed. For preliminary purposes an
application rate of 5 kg lime per m2 per vertical metre of fill thickness is suggested.
• Treatment should be carried out by spreading the soil in maximum 300 mm loose
thickness layers and moisture conditioning before spreading lime at the appropriate
application rate. The ASS may require reworking several times to achieve adequate
mixing of the neutralising agent and/or drying of the soil.
• It is proposed that treatment levels are assigned on the basis of the results of a detailed
ASS investigation. Liming rates from this preliminary investigation would be as follows:
o Existing fill/pale coloured soils 10 kg lime/m3
o Natural dark coloured clayey sands 50 kg lime/m3
o ‘Marine’ clay 100 kg lime/m3
Lime treatment rates should be confirmed following further investigation, together with
inspection and field testing by a suitably qualified and experienced environmental
scientist during excavation.
• Verification sampling and analysis is to be carried out on the treated soil using the
Chromium suite method at a rate of 1 test per 250 m³ to confirm that appropriate amounts
of the neutralising agent have been incorporated into the soil.
• An accurate spatial tracking system should be developed to control the movement and
final location of the treated soils so that initial testing (from this report) can be correlated
to the verification of prescribed treatment.
Golder Associates
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix 5. Geotechnical Engineering Report [As Published]Related documentApplication case desk ↗
About this file
- File size
- 6.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.