Decision Notice OPW26 0049 ( As Published)

of 9

Page text shows just the words. Original shows the document exactly as it was published.

                      b.      Adequate parking arrangements for works and deliveries;
                      c.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD); and
                      d.      provision for safe vehicle and pedestrian access across the frontage of the site both
                              during daily construction and after daily construction has ceased.
               11.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               12.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               13.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               14.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               15.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Material Change of Use approval viz.
                              51996.1942.01 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Pavement Design and Construction
               16.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Retention of Existing Trees and Vegetation
               17.    All trees and vegetation identified for retention must be protected in accordance with AS
                      4970, Protection of trees on development sites.
               18.    A qualified person* must be engaged for the duration of the works to supervise tree protection
                      within the development site and frontages, prior to, during and following construction in
                      accordance with AS 4970, Protection of trees on development sites.
                      Works within Road Reserve/Reinstatement
               19.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.




                                                                                                       Page 3 of 9
Document Set ID: 24898632
Version: 2, Version Date: 25/06/2026
Log in to download the original file

Decision Notice OPW26 0049 ( As Published).pdf · 155 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.