MCU14/0056 Stormwater Quantity Management Plan Att D Information response
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnRFI Item
The adverse impacts from sheet flow on the state controlled road network are prevented
SWC Response
The development does not result in adverse impacts from sheet flow on the state controlled
road network. All runoff will be directed into the waterway on the eastern side of the site.
RFI Item
Existing stormwater drainage infrastructure on state controlled roads is not interfered with
or damaged such as through concentrated flows, surcharging, scour, or deposition; and the
quality of stormwater discharging onto the state controlled road is not reduced through
erosion and sedimentation.
SWC Response
The development marginally increases the velocity at a single cross-section in the hydraulic
model. The velocity at XS20 is increase by .03m/s. This increase is considered to have a
negligible impact on any potential erosion and scouring and no impact on state controlled
roads is expected.
J4279 Report 1.0.doc
14 January 2015 Page 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.