                                                                                SWMS:02 – Elevating Work Platforms
   Safe Work Methods
                                                                                  H                    Controls/Work Methods                                              Residual Risk
                                                                                                                                                   Responsible person/s
          Job Steps                    Potential Hazards           L   C    R     O            1. Eliminate 2. Substitute 3. Isolate 4. Engineer                          L    C    R
                                                                                                                5. Admin 6. PPE
                                                                                                                                                   for Monitor & Review
                                                                                  C
                                                                                        Establish an exclusion zone below the work area
                                                                                         (e.g. barricade tape minimum 900mm high).
                                                                                  1     Only tools, materials and equipment that can be
                                                                                         safely handled by a person working from the
                                                                                         bucket are to be transported.
                                                                                  1
                                                                                        Do not support material on the edge of bucket.
Operating & working from        Roll-over                          C   5    E           The operating surface is to be flat and level – to        EWP Operator           E     5       H
boom-type EWPs (Cont)                                                      22            suite manufacturers’ operational specification.                                                15
                                                                                  4     If outriggers have been installed by the
                                                                                         manufacturer, they are to be used to stabilise the
                                                                                         EWP.
                                                                                  1
                                                                                        Do not operate on unstable / soft surfaces.
                                                                                  1     Ensure the SWL is not exceeded.
                                Contact      with      overhead    C   5    E     5     The operator is to identify overhead obstacles            EWP Operator           E     5       H
                                structures/power lines                     22            (including services such as powerlines etc.) & the                                             15
                                                                                         stability of surface prior to operation.
                                                                                        No part of the EWP or person / equipment within
                                                                                  1      the EWP is to enter a power line exclusion zone.
                                                                                         Note: This is 3m minimum for low voltage, if
                                                                                         unsure check with site manager.

                                                                                  2     Only bucket controls are to be used while
                                                                                         personnel are in the bucket.
Rescue procedure                Inability      to       respond    C   5    E     5     Site emergency procedures to be initiated.                EWP Operator           D     4       H
                                promptly/effectively          to           22     5     Review the situation for hazards prior to starting                                             14
                                emergency situation    involving                         rescue (e.g. electrical hazards).
                                EWP.                                              5     Competent person to be available on site to
                                                                                         operate the ground controls of the EWP where
                                                                                         safe to do so during an emergency.
                                                                                  3     Do not place others at risk during rescue/
                                                                                         response.

584 Milton Road TOOWONG QLD 4066                           SWMS Developed by:    Jamie Gilbert                                                             VERSION 8 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                        Position:             National Health & Safety Co-ordinator                                                        Page 20
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗