SWMS:02 – Elevating Work Platforms
Safe Work Methods
H Controls/Work Methods Residual Risk
Responsible person/s
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer L C R
5. Admin 6. PPE
for Monitor & Review
C
Establish an exclusion zone below the work area
(e.g. barricade tape minimum 900mm high).
1 Only tools, materials and equipment that can be
safely handled by a person working from the
bucket are to be transported.
1
Do not support material on the edge of bucket.
Operating & working from Roll-over C 5 E The operating surface is to be flat and level – to EWP Operator E 5 H
boom-type EWPs (Cont) 22 suite manufacturers’ operational specification. 15
4 If outriggers have been installed by the
manufacturer, they are to be used to stabilise the
EWP.
1
Do not operate on unstable / soft surfaces.
1 Ensure the SWL is not exceeded.
Contact with overhead C 5 E 5 The operator is to identify overhead obstacles EWP Operator E 5 H
structures/power lines 22 (including services such as powerlines etc.) & the 15
stability of surface prior to operation.
No part of the EWP or person / equipment within
1 the EWP is to enter a power line exclusion zone.
Note: This is 3m minimum for low voltage, if
unsure check with site manager.
2 Only bucket controls are to be used while
personnel are in the bucket.
Rescue procedure Inability to respond C 5 E 5 Site emergency procedures to be initiated. EWP Operator D 4 H
promptly/effectively to 22 5 Review the situation for hazards prior to starting 14
emergency situation involving rescue (e.g. electrical hazards).
EWP. 5 Competent person to be available on site to
operate the ground controls of the EWP where
safe to do so during an emergency.
3 Do not place others at risk during rescue/
response.
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 8 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 20
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.