SWMS:03 – Mobile Scaffolds
Project Details
Project: Responsible Person: Matt Leeke 0414 691 314
71 SEAVIEW TCE SUNSHINE BEACH QLD 4567
Site Manager: Matt Leeke 0414 691 314
Site Foreman : Terry Strahan 0419 762 427
Activity Description: Site Foreman : Jesse Joyce 0403 745 840
Erecting, dismantling and carrying out work activities from mobile scaffolds
HSO: Terry Strahan 0419 762 427
Referenced SWMS:
SWMS: 04 – SWMS 06
Plant and Equipment Involved: Mobile scaffold
Lanyards / wrist straps
Various drills, saws and hand tools
energised electrical installations
Work at Heights >2m Disturbance of asbestos Confined spaces
or services
High Risk Activities: Structural alterations requiring Excavation >1.5 metres or near a a contaminated or flammable
Demolition of a structure
Carried out in or near the following: temporary support tunnel atmosphere
A work area with moving water or other liquid that
tilt-up or precast concrete Other: ____________________
powered mobile plant involves a risk of drowning
PPE Required: Hard Hat Safety glasses / goggles Hearing Protection Fall Arrest Harness Disposable overalls:
(Tick as relevant) Safety Boots Face Shield Gloves Respirator High Visibility Vest
Maintenance / Prestart Checks Conduct visual inspection of mobile scaffold and components prior to use
Required: Maintenance of scaffolding components in accordance with the manufacturers recommendations
Certificates of Competency Certificate of Competency required for the erection, modification and dismantling of any scaffold where a person could fall 4m or more, and
Required: for all other scaffolds from the ground level, if the height of the structure will be more than 4 metres.
Training / Competencies Required: Course Codes: OHSCER219A (Perform Basic Scaffolding) (minimum)
Certificate of training for persons erecting mobile scaffolds <4m in height
Induction into this Work Method Statement
Work Health &Safety Regulation 2011, Part 6, Scaffolding Code of Practice2009 - QLD
Health, Safety or Environmental Codes or Standards
Subdivision 4.
Legislation: Applicable to the Works: AS/NZS 1576 Scaffolding Part 1 – General requirements
VIC Occupational Health & Safety Act 2004, Part
3 AS/NZS 4576 Guidelines for Scaffolding
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 8 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 23
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.