                                                                             SWMS:05 – Trestle Platforms < 2m in Height
Safe Work Methods
                                                                                                                                                           Responsible
                                                                                 H                      Controls / Work Methods                                               Residual Risk
                                                                                                                                                           person/s for
          Job Steps                   Potential Hazards         L     C      R   O              1. Eliminate 2. Substitute 3. Isolate 4. Engineer           Monitor &
                                                                                 C                               5. Admin 6. PPE                                               L    C        R
                                                                                                                                                             Review
                                                                                  1     Do not support items (tools etc) on the handrail or trestle
                                                                                         ladder rung.
                                                                                  1     No objects are to be dropped from the platform – must
                                                                                         be passed down.
                                  Platform collapse / tip-      B     5     E     5     A trestle platform is only to be used on a hard, flat and      Person(s) using        E    5        H
Accessing and working from
                                  over                                     24            level surface to avoid instability.                            Trestle platform                     15
trestle platform (Cont)
                                                                                          Each trestle ladder is to be secured to prevent it moving.
                                                                                  4
                                                                                          Ensure that the planks do not span more than the
                                                                                           intended load
                                                                                  4
                                                                                          The height of the platform is to be less than 2m.
                                                                                  4       Ensure the SWL is not exceeded.
                                                                                 4


Methods for monitoring and reviewing effectiveness of chosen control measures
Hutchinson Builders & Subcontracted Personnel:
Workers:                                        Follow procedure and report trestle platform hazards
Hutchinson Builders Foreman:                    Ensure competent persons erect trestle platforms and regularly inspect trestle platforms erected on site
                                       Monitor SWMS controls on site using the Observation Log

Developed & approved on site by:

Name:                                                            Position:                                                     Date:

Matt Leeke / Terry Strahan / Jesse Joyce                         Site Manager/ Foreman

                                                                 Workers Representative



584 Milton Road TOOWONG QLD 4066                             SWMS Approved by:    Jamie Gilbert                                                                 VERSION 7 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                          Position: National Health & Safety Co-ordinator                                                                       Page 42
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.