                                                                                                              Hutchinson Builders – ABN:52 009 778 330

                                              WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                                                 Version: 9.2



      9.2           Weekly Site Safety Inspection/Daily Visual Inspection ........................................................32
      9.3           Task Observations ................................................................................................................32

10. Incident Reporting and Investigation (MP:08) ........................................................................... 33
    10.1     Internal Incident Reporting Process (Procedure MP:08) .....................................................33
    10.2     Investigation Process (MP:08) ..............................................................................................34
    10.3     Notification...........................................................................................................................34
    10.4     Rehabilitation & Return to Work .........................................................................................35
    10.5     Record Keeping ....................................................................................................................35
    10.6     Health and Safety Reporting ................................................................................................35

11. Management Of Change (MP:12).............................................................................................. 36

12. Record Maintainance & Retention ............................................................................................ 38

13. Personal Safety (SP:04)............................................................................................................. 39
    13.1     Personal Protective Equipment............................................................................................39
    13.2     Heat Exhaustion ...................................................................................................................39
    13.3     UV Protection .......................................................................................................................40
    13.4     Working Alone ......................................................................................................................40
    13.5     Wet Weather Procedure ......................................................................................................40

14. Manual Handling...................................................................................................................... 42
    14.1    Legislation ............................................................................................................................42
    14.2    General Guidance .................................................................................................................42

15. Permits to Work ....................................................................................................................... 43
    15.1     Isolation/ Tag and Lockout ...................................................................................................43
    15.2     Hot Work ..............................................................................................................................44
    15.3     Working at Heights ...............................................................................................................44
    15.4     Excavation & Penetrations ...................................................................................................45
    15.5     Coring / Drilling ....................................................................................................................45

16. High Risk Work Systems ........................................................................................................... 46
    16.1     Demolition ............................................................................................................................46
    16.2     Asbestos ...............................................................................................................................47
    16.3     Removal of lead materials....................................................................................................48
    16.4     Tower Crane Selection & Positioning ...................................................................................48
    16.5     Scaffolding ............................................................................................................................48
    16.6     Tilt up & Pre-cast Panels ......................................................................................................49
    16.7     Erecting Structural Steel .......................................................................................................49
    16.8     Swing Stage Placement, Erection & Dismantling .................................................................49
    16.9     Erecting, Climbing, Servicing & Dismantling of a Tower Crane ............................................50
    16.10    Electrical ...............................................................................................................................50
    16.11    Electrical Tools and Equipment ............................................................................................50
    16.12    Concrete Pumping ................................................................................................................51

17. Plant and Equipment (PP:07) .................................................................................................... 52
    17.1     Mobile Plant and Equipment ...............................................................................................52
    17.2     Pre Start Checks ...................................................................................................................53
    17.3     Elevated Work Platforms .....................................................................................................53
    17.4     Lasers....................................................................................................................................53
    17.5     Plant Using Compressed Air .................................................................................................54

                                                                                                                                                Page 3 of 58

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.